Abstract

Dengan semakin pesatnya pertumbuhan pengetahuan dan teknologi di bidang konstruksi, membuat kita untuk lebih memperhatikan standar mutu serta produktivitas kerja agar dapat berperan serta dalam meningkatkan sebuah pembangunan konstruksi. Diperlukan suatu bahan bangunan yang memiliki keunggulan yang lebih baik dibandingkan bahan bangunan yang sudah ada selama ini. Selain itu bahan tersebut harus memiliki beberapa keuntungan seperti bentuk yang dapat menyesuaikan dengan kebutuhan, spesifikasi teknis, daya tahan yang kuat dan kecepatan pelaksanaan konstruksi serta ramah lingkungan. Dengan didasari pertimbangan tersebut, maka pada pembangunan gedung Rektorat dan IT Universitas Negeri Surabaya ini yang terdiri dari 14 lantai. Pada perencanaan awal dari pembangunan gedung tersebut dindingnya terbuat dari pasangan batu bata. Berdasarkan spesifikasi yang ada, maka direncanakan metode baru yang diharapkan dapat meminimalisir waktu dan biaya proyek pembangunan namun masih sesuai dengan spesifikasi yang ditetapkan pada perencanaan awal. Pada tugas akhir ini mencoba untuk membandingkan penggunaan material pada pembangunan Gedung Rektorat dan IT Universitas Negeri Surabaya dengan menggunakan material batu bata merah dan menggunakan material bata ringan I-CON. Dari analisa struktur dengan menggunakan SAP 2000 didapatkan hasil bahwa tidak ada perubahan pada dimensi balok dan kolom dikarenakan desain awal sudah maksimum untuk dimensi dan mutu betonnya. Pada pekerjaan dengan menggunakan material bata merah pada pekerjaan pasangan hingga finishing di dapatkan total biaya sebesar Rp 7.123.276.816,45 dengan estimasi waktu 241 hari. Pada pekerjaan dengan menggunakan material bata ringan pada pekerjaan pasangan hingga finishing di dapatkan total biaya biaya sebesar Rp 7.091.180.355,89 dengan estimasi waktu 213 hari. Dari hasil perhitungan diatas dapat disimpulkan bahwa penggunaan material bata ringan dapat menjadi alternatif dan diaplikasikan dalam pembangunan Gedung Rektorat Dan IT Universitas Negeri Surabaya.
==================================================================================================================================
With the rapid growth of knowledge and technology in the construction field, making us pay more attention to quality standard and labor productivity in order to participate in increasing construction development. Required the building material that has better advantage than the existing building materials. In addition the material must have some advantages such a form that can suit the needs, technical specifications, durability, speed of construction and green environment. With these considerations, then the development of rectorate building and IT Surabaya State University that has 14 floors. In the beginning plan and building development, the wall is made from bricks. Based on the existing specifications, planned with new method that is expected to minimize time and cost of building project. but still in accordance with the specifications that set at the beginning plan. In this final project, trying to compare material use on development of rectorate building and IT Surabaya State University with using materials of red brick and I-CON light brick. From structure analysis with SAP2000 showed that there is no change in the beam and column dimension due to the maximum design for dimension and quality of concrete. red brick material use on arrangement work till finishing is obtained cost IDR 7.123.276.816,45 with time estimate 241 days. Light brick material use on arrangement work till finishing is obtained cost IDR 7.091.180.355,89 with time estimate 213 days. From the above calculation, it can be concluded that the use of light brick material can be an alternative and applied to development of rectorate building and IT Surabaya State University

Item Type: Thesis (Other)
Additional Information: RSS 692.5 Sus p-2014
Uncontrolled Keywords: Beton ringan, CLC, Isolator panas, finishing, estimasi, Presisi, light concrete, CLC, hot insolator, finishing, estimate, precision
Subjects: T Technology > TH Building construction > TH437 Building--Cost control.
Divisions: Faculty of Civil, Planning, and Geo Engineering (CIVPLAN) > Civil Engineering > 22201-(S1) Undergraduate Thesis
Depositing User: Mr. Marsudiyana -
Date Deposited: 22 Jun 2023 08:15
Last Modified: 22 Jun 2023 08:15
URI: http://repository.its.ac.id/id/eprint/98212

Actions (login required)

View Item View Item