Analisis Perbandingan Penjadwalan Proyek Dengan Metode Critical Path Method (CPM) dan Critical Chain Project Management (CCPM)

Luthfi, Muhamad (2023) Analisis Perbandingan Penjadwalan Proyek Dengan Metode Critical Path Method (CPM) dan Critical Chain Project Management (CCPM). Other thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 04311940000085-Undergraduate_Thesis.pdf] Text
04311940000085-Undergraduate_Thesis.pdf - Accepted Version
Restricted to Repository staff only until 1 October 2025.

Download (9MB) | Request a copy

Abstract

Pada proyek pembangunan offshore platform dibutuhkan penjadwalan yang baik agar seluruh proses dalam proyek berjalan dengan lancar. Metode yang paling umum digunakan dalam merencanakan proyek adalah dengan Critical Path Method (CPM). Namun seiring berjalnanya waktu, muncul metode baru yang bernama Critical Chain Project Management (CCPM) di mana metode ini menghapus safety time yang digunakan pada setiap kegiatan yang kemudian digantikan dengan waktu penyangga (buffer). Proyek yang digunakan dalam tugas akhir ini adalah drawing topside & jacket wellhead platform. Penelitian ini memberikan perbandingan hasil penjadwalan berupa durasi dan biaya tenaga kerja langsung antara metode CPM dengan metode CCPM. Penjadwalan proyek dengan metode CPM menghasilkan durasi selama 152 hari dengan biaya tenaga kerja langsung sebesar Rp 447,200,000. Sedangkan metode CCPM menghasilkan durasi selama 125 hari dengan biaya sebesar Rp 366.704.000. Terdapat pengurangan durasi selama 27 hari dan penurunan biaya sebesar Rp 80,496,000. Dari hasil penjadwalan tersebut kemudian dilakukan simulai monte carlo dengan menggunakan software Crystal Ball berdasarkan tiga parameter durasi (minimum, most likely, maksimum) untuk mengetahui probabilitas penyelesaian proyeknya di mana hasil simulasi menunjukkan bahwa perkiraan penyelesaian proyek berada pada rentang antara sekitar 108 hari hingga 134 hari dengan rata-rata proyek dapat diselesaikan dalam waktu 122 hari.
=======================================================================================================================================
In an offshore platform development project, good scheduling is needed so that all
processes in the project run smoothly. The most common method used in planning projects is
the Critical Path Method (CPM). However, over time, a new method emerged called Critical
Chain Project Management (CCPM) in which this method removed the safety time used in each
activity which was then replaced with buffer time. The project used in this final project is
drawing topside & jacket wellhead platform. This study provides a comparison of the
scheduling results in the form of duration and direct labor costs between the CPM method and
the CCPM method. Project scheduling using the CPM method produces a duration of 152 days
with direct labor costs of IDR 447,200,000. While the CCPM method produces a duration of
125 days at a cost of Rp. 366,704,000. There is a reduction in duration of 27 days and a
reduction in costs of IDR 80,496,000. From the scheduling results, a monte carlo simulation is
then carried out using Crystal Ball software based on three duration parameters (minimum,
most likely, maximum) to determine the probability of completion of the project where the
simulation results show that the estimated project completion is in the range of around 108 days
to 134 days with an average project can be completed within 122 days.

Item Type: Thesis (Other)
Uncontrolled Keywords: CCPM, CPM, Monte Carlo
Subjects: H Social Sciences > HD Industries. Land use. Labor > HD69.T54 Time management. Scheduling
T Technology > T Technology (General) > T56.8 Project Management
Divisions: Faculty of Marine Technology (MARTECH) > Ocean Engineering > 38201-(S1) Undergraduate Thesis
Depositing User: Muhamad Luthfi
Date Deposited: 19 Jul 2023 08:25
Last Modified: 19 Jul 2023 08:25
URI: http://repository.its.ac.id/id/eprint/98596