Kajian Pemilihan Pemenang Tender Konstruksi Tangki Timbun Dengan Pendekatan Analytical Hierarchy Process (AHP) Di Marketing Operation Region V Pertamina

Bachmid, Gadri (2017) Kajian Pemilihan Pemenang Tender Konstruksi Tangki Timbun Dengan Pendekatan Analytical Hierarchy Process (AHP) Di Marketing Operation Region V Pertamina. Masters thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 9114202413-Master_Theses.pdf]
Preview
Text
9114202413-Master_Theses.pdf - Published Version

Download (1MB) | Preview

Abstract

Evaluasi pada pemilihan kontraktor pemenang tender memerlukan penilaian terhadap proses sebagai unsur terpenting. Hal tersebut terjadi karena banyak kriteria yang menjadi bahan pertimbangan bagi pengguna jasa kontraktor. Salah satu pengguna jasa kontraktor di Indonesia adalah Technical Services Region V Pertamina yang bertanggung jawab terhadap setiap pelaksanaan proyek investasi yang berada di area Jawa Timur, Bali dan Nusa Tenggara. Akan tetapi permasalahan yang kerapkali muncul adalah kegagalan konstruksi dan pekerjaan yang berlangsung bertahun-tahun jauh melampaui batas waktu pekerjaan konstruksi. Fase konstruksi adalah implikasi langsung dari proses seleksi kontraktor yang dilakukan. Fase konstruksi yang buruk tentu tidak terlepas dari proses tender yang belum berjalan maksimal. Pada akhirnya output proses tender berupa pemenang tender yang tidak mumpuni, tidak akan mampu bekerja sesuai dengan standar yang diharapkan. Penelitian ini diharapkan dapat memberikan solusi untuk mengetahui performa yang dimiliki setiap kontraktor pembangunan tangki timbun dengan kualifikasi besar serta faktor apa yang paling berpengaruh dalam penentuan pemenang tender konstruksi tangki timbun dengan kualifikasi besar.
Desain penelitan ini adalah deskriptif, dengan metode studi kasus. Pendekatan yang dilakukan adalah penelitian campuran (mix methodology) yang menggabungkan pendekatan kualitatif dan kuantitatif. Data dalam penelitian ini dikumpulkan melalui kuisioner. Metode analisis data yang digunakan dalam penelitian ini menggunakan Analytical Hierarchy Process (AHP) dilanjutkan dengan melakukan sensitivity analysis untuk menentukan kriteria yang paling berperan dalam penentuan indeks performansi kontraktor.
Hasil yang diperoleh dari penelitian ini adalah PT. Bukaka Teknik terbukti memiliki indeks performansi kontraktor terbaik dan financial performance menjadi faktor yang paling berpengaruh dalam penentuan pemenang tender konstruksi tangki timbun dengan kualifikasi besar di Technical Services Region V Pertamina
============================================================
Evaluation on the selection of winning contractors of tenders requires an assessment of the process as the most important element. That is because there are so many criteria taken into account by their clients. One of the contractors’ service clients in Indonesia is the Technical Services Region V Pertamina who is responsible for any undertakings of investment projects in the area of East Java, Bali and Nusa Tenggara. However, the potential problems occuring frequently are construction failure and belated project which is underway for years past the expected time of construction work. The construction phase is a direct indication of the contractor selection process. Poor construction phase cannot be separated from the underprivilege tendering process. As a result of the bad contractor selection process, the projects are undertaken by the unqualified and inexperienced constractors. This research is expected to provide solutions to know performance of each storage tank construction contractors with high qualification and which factor that has the most influential factor in determining the winner of the construction of storage tanks tender with high qualification.
Design of this research is descriptive, with the case study method. The approach taken is a mixed research (mix methodology) that combines qualitative and quantitative approaches. The data in this study were collected through questionnaires. Methods of data analysis used in this study uses Analytical Hierarchy Process (AHP) and followed by sensitivity analysis to know the most influential criteria in determining contractors performance index.
Result of this research is that PT. Bukaka Teknik has the best contractors performance index and financial performance become the most influential factor in determining tender winner of storage tank construction with high qualification in Technical Services Region V Pertamina.

Item Type: Thesis (Masters)
Uncontrolled Keywords: Tender, Analytical Hierarchy Process (AHP), Sensitivity Analysis, indeks performansi kontraktor
Subjects: T Technology > TH Building construction
Divisions: 61101-Magister Management Technology
Depositing User: GADRI BACHMID
Date Deposited: 07 Mar 2017 02:26
Last Modified: 05 Mar 2019 04:39
URI: http://repository.its.ac.id/id/eprint/1943

Actions (login required)

View Item View Item