Alternatif Peningkatan Ruas Jalan Kec. Ngantru-Kab.Tulungagung KM SBY STA 143+750 - 148+090

Kurnia Dewi, Cintya and Kusuma Putera, Jefri (2017) Alternatif Peningkatan Ruas Jalan Kec. Ngantru-Kab.Tulungagung KM SBY STA 143+750 - 148+090. Diploma thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 3114030016-3114030113-Non_Degree .pdf]
Preview
Text
3114030016-3114030113-Non_Degree .pdf - Published Version

Download (10MB) | Preview

Abstract

Pelebaran jalan Kec. Ngantru-Kab.Tulungagung KM SBY STA 143+750 - 148+090 merupakan bentuk peningkatan layanan jalan guna memperlancar mobilisasi. karena dengan berjalannya waktu dan masa pelayanan jalan, kondisi jalan ini akhirnya akan mengalami penurunan kekuatan dan kurangnya ruas jalan untuk menampung kendaraan yang lewat.
Pada ruas jalan Kec. Ngantru-Kab.Tulungagung KM SBY STA 143+750-148+090 merupakan jalan utama penghubung antara kedua kabupaten . untuk mengatasi kepadatan dan demi meningkatkan kelancaran lalu lintas maka pada ruas jalan tersebut pemerintah memerlukan peningkatan jalan berupa pelebaran jalan.
PT.Ridlatama Bahtera Konstruksi adalah kontraktor yang menjadi pelaksana untuk menjalankan proyek pelebaran jalan ini. Pelebaran jalan ini menggunakan perkerasan aspal dengan metode fleible pavement.
Didalam pelaksanaan terdapat berbagai aktifitas pekerjaan yang setiap pekerjaannya dilakukan perhitungan produktifitas dan biayanya. dan mengetahui resiko kecelakaan kerja yang mungkin terjadi selama pelaksanaan proyek yang dapat mempengaruhi waktu dan biaya proyek.
Berdasarkan perhitungan produktifitas dan analisa biaya dari semua pekerjaan didalam sumber daya yang dibutuhkan didapatkan hasil Rencana Anggaran Biaya sebesar Rp. 31.275.127.727. dan waktu pelaksanaan proyek dengan menggunakan metode PDM dapat diselesaikan dengan waktu 244 hari kalender kerja. kemudian didapat dari survei dilapangan untuk hasil risiko kecelakaan kerja yang sering terjadi selama pelaksanaan proyek yaitu tertabrak alat berat dan tertabrak kendaraan lalu lintas dilokasi pekerjaan.
=============================================================================================================
Road widening of Ngantru Sub-District,Tulung Agung district KM SBY STA 143+750-148+090 is an increase of road service to facilitate the mobilization. because with the passage of time and road service,the condition of this road will eventually to accomodate passing vehicles.
In Ngantru Sub-District,Tulung Agung District, KM SBY STA 143+750 - 148+090 is the main liasion beetwen Tulung Agung and Kediri Districts. to overcome the density and for the smoothness of the traffic, the government needs road improvement in the form widening roads.
PT. Ridlatama Bahtera Construction is the contractor who is the excutor to run this road widening project. This road widening uses asphalt as pavement material. in the implementation that may affect the time and cost of the project.
Based on the calculation of productivity and cost analysis of all work within the required resources, the result of the budget plan is RP. 31.275.127.727 and the time of project implementation using PDM can be implemented with 244 working calendar days. then obtained from the field survey for the results of the risk of occupational accidents that often occur during the implementation of the project is workers hit by heavy equipment and hit by traffic vehicles in the work location

Item Type: Thesis (Diploma)
Uncontrolled Keywords: Biaya, Pelebaran jalan, FWD
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
T Technology > TE Highway engineering. Roads and pavements
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22401-(D3) Diploma 3
Depositing User: Cintya Kurnia Dewi
Date Deposited: 10 Aug 2017 01:35
Last Modified: 05 Mar 2019 04:34
URI: http://repository.its.ac.id/id/eprint/42892