Metode Pelaksanaan Pembangunan Terowongan Pengelak (Tunnel) Pada Proyek Waduk Bendung Ponorogo

Pambudi, Lilianto Rio and Ichsandi, Mustar (2017) Metode Pelaksanaan Pembangunan Terowongan Pengelak (Tunnel) Pada Proyek Waduk Bendung Ponorogo. Diploma thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 3114030070-3114030103-Non_Degree.pdf]
Preview
Text
3114030070-3114030103-Non_Degree.pdf - Published Version

Download (7MB) | Preview

Abstract

Waduk Bendo merupakan sebuah proyek yang di kelola oleh Kementrian Pekerja Umum Balai Besar Wilayah Sungai (BBWS) Bengawan Solo yang terletak pada wilayah dukuh Bendo, Desa Ngindeng, kecamatan Sawoo, Kabupaten Ponorogo, Provinsi Jawa Timur. Dalam pembangunan sebuah bendungan diperlukan beberapa bangunan penting dan penunjang beroperasinya sistem tersebut, salah satunya berupa bangunan pengelak atau terowongan pengelak (Diversion Tunnel). Bangunan pengelak adalah suatu bangunan yang berfungsi mengalihkan aliran sungai utama selama pekerjaan konstruksi bendungan dilaksanakan. Sedangkan terowongan pengelak berfungsi mengalirkan aliran sungai utama tersebut agar pekerjaan konstruksi bendungan dapat dilaksanakan. Dalam proses pembuatan terowongan pengelak perlu dikaji terlebih dahulu metode-metode yang digunakan dalam pembuatan terowongan pengelak agar penerapan dilapangan sesuai dengan perencanaan. Sehingga perlu dibuat penyusunan dokumen-dokumen metode pelaksanaan pada terowongan pengelak Waduk Bendo Ponorogo. Pada terowongan pengelak Waduk Bendo Ponorogo memiliki jenis transisi pada tiap kedalaman yang berbeda. Transisi yang dipakai adalah tipe transisi seperti tapal kuda. Dalam pengerjaan terowongan pengelak terdiri dari beberapa tahapan pelaksanaan yaitu : Pekerjaan Pemetaan (uitzet lapangan), Pekerjaan peledakan (Blasting), Pekerjaan Scalling and Mucking, Pekerjaan Pemasangan besi penyangga (Steel support), Pekerjaan Shotcrete, Pekerjaan Pembuatan Lantai Kerja, Pekerjaan Pengecoran dinding bagian bawah, Pekerjaan pengecoran dinding bagian atas, dan Pekerjaan Grouting. Dengan demikian diharapkan dokumendokumen penulisan metode pelakasanaan dapat membantu dalam pembuatan terowongan pengelak yang ada pada proyek Waduk Bendo Ponorogo.
=================================================================
Bendo Dam is a project managed by the Ministry of Public Works of the River Territory (BBWS) of Bengawan Solo which is located in the hamlet of Bendo, Ngindeng Village, Sawoo District, Ponorogo Regency, East Java Province. In the construction of a dam required several important buildings and support the operation of the system, one of them in the form of a dodge building or distraction tunnel (Diversion Tunnel). Duck building is a building that serves to divert the main river flow during dam construction work carried out. While the dormitory tunnel functions to drain the main river flow so that the dam construction work can be implemented. In the process of making the duck tunnel needs to be reviewed in advance the methods used in the manufacture of tunneling tunnels for the implementation of the field in accordance with the planning. So it is necessary to make the preparation of documents of the method of execution on tunnel dam dam Bendo Ponorogo. In Bendo Ponorogo damage tunnel tunnels have different types of transitions at different depths. The transition used is a transitional type such as a horseshoe. In the degrading tunnel work consists of several stages of implementation: Mapping Work (uitzet field), Blasting work, Scalling and mucking work, Iron Buffer Works, Shotcrete Works, Work Floor Works, Lower Wall Painting Works, Top wall casting work , And Grouting Works. It is hoped that the writing documents of the training method can assist in the making of the existing duck tunnel at the Bendo Ponorogo dam project.

Item Type: Thesis (Diploma)
Uncontrolled Keywords: Terowongan pengelak, waduk Bendo Ponorogo, Blasting, uitzet lapangan, Grouting, Diversion Tunnel, Bendo Ponorogo Dam, Uitzel Field
Subjects: T Technology > TH Building construction
Divisions: Faculty of Vocational > Civil Infrastructure Engineering (D3)
Depositing User: Lilianto Rio Pambudi
Date Deposited: 30 Oct 2017 02:08
Last Modified: 08 Mar 2019 03:59
URI: http://repository.its.ac.id/id/eprint/44949