Pengaruh Faktor Internal Dan Eksternal Proyek Terhadap Kinerja Proyek Konstruksi Di Provinsi Kalimantan Selatan

Agsarini, Irmia (2015) Pengaruh Faktor Internal Dan Eksternal Proyek Terhadap Kinerja Proyek Konstruksi Di Provinsi Kalimantan Selatan. Masters thesis, Institut Technology Sepuluh Nopember.

[thumbnail of 3113203002-Master Thesis.pdf]
Preview
Text
3113203002-Master Thesis.pdf - Published Version

Download (1MB) | Preview

Abstract

Konstruksi merupakan sistem yang kompleks dimana keterlibatan banyak
pihak dari tahap pra-kontrak sampai dengan tahap pasca-kontrak dalam konstruksi
menimbulkan masalah-masalah yang akan mempengaruhi kinerja penyelesaian
proyek. Dalam pelaksanaan proyek konstruksi sering terjadi permasalahan antara
lain perpanjangan waktu pelaksanaan pekerjaan (time overrun), penambahan biaya
proyek (cost overrun) dan hasil pekerjaan yang tidak sesuai dengan mutu yang
direncanakan (kegagalan mutu). Waktu, biaya dan mutu adalah merupakan tiga
dimensi evaluasi kinerja yang paling dominan.
Penelitian ini bertujuan untuk mengetahui pengaruh faktor internal dan
eksternal proyek terhadap kinerja proyek konstruksi di Provinsi Kalimantan
Selatan. Faktor internal dan eksternal proyek diperoleh dari kajian terhadap
penelitian terdahulu berupa faktor penyebab time overrun, cost overrun dan
kegagalan mutu yang terdiri dari faktor ekonomi, faktor manajerial/organisasi,
faktor sumber daya dan faktor eksternal. Jenis penelitian ini berupa penelitian
konfirmatori. Metode analisis penelitian menggunakan Korelasi Kanonikal
(Canonical Correlation). Data penelitian dikumpulkan melalui kuesioner yang
disebarkan kepada Pimpinan dan Manager Proyek dari pihak kontraktor yang
melaksanakan proyek infastruktur jalan dan jembatan di Dinas Pekerjaan Umum
Provinsi Kalimantan Selatan.
Hasil analisis menunjukkan bahwa faktor internal proyek berpengaruh kuat
terhadap kinerja proyek konstruksi. Faktor internal yang dominan adalah faktor
managerial/organisasi, faktor sumber daya dan faktor ekonomi. Sedangkan untuk
kinerja proyek, kinerja yang paling dominan adalah kinerja biaya dan kinerja mutu.
====================================================================================================
Construction is a complex system in which the involvement of many parties
from pre-contract to post-contract stage in construction raises issues that will affect
the performance of project completion. In the implementation of construction
projects frequently arise issues, among others, the extension of the job execution
time (time overrun), the incremental cost of the project (cost overrun) and the work
is not in accordance with the planned quality (quality failures). Cost, time and
quality are the three most dominant's dimensions of performance evaluation.
This study aims to determine the influences of internal and external factors
of project on construction project performance in Province of South Kalimantan.
Internal and external factors were obtained from study of previous researches in the
form of the factors causing time overrun, cost overrun and quality failures which
consists of economic, managerial/organizational, resource and external factors.
This type of research is a confirmatory study. Research analysis method use
Canonical Correlation. Data research collected through questionnaires distributed
to leader and manager project of contractors who carry out infrastructure project at
Public Works Office of Province of South Kalimantan.
The analysis showed that the internal factors of the project has a strong
influence on construction project performance. The dominant factors of the internal
factors are managerial/organizational factor, resource factor and economic factor.
While the dominant factors for project performance are cost performance and
quality performance.

Item Type: Thesis (Masters)
Additional Information: RTS 658.404 Ags p
Uncontrolled Keywords: Faktor Internal, Faktor Eksternal, Kinerja Proyek, Korelasi Kanonikal.
Subjects: T Technology > T Technology (General) > T56.8 Project Management
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22101-(S2) Master Thesis
Depositing User: Mr. Tondo Indra Nyata
Date Deposited: 02 May 2019 02:29
Last Modified: 02 May 2019 02:29
URI: http://repository.its.ac.id/id/eprint/62889

Actions (login required)

View Item View Item