Analisis Pengendalian Persediaan Material Jenis MRO Berdasarkan Kelompok Material (Studi Kasus: Kangean Energy Indonesia LTD)

Putra, Ade (2016) Analisis Pengendalian Persediaan Material Jenis MRO Berdasarkan Kelompok Material (Studi Kasus: Kangean Energy Indonesia LTD). Undergraduate thesis, Institut Teknology Sepuluh Nopember.

[thumbnail of 2512100155-Undergraduate_Thesis.pdf]
Preview
Text
2512100155-Undergraduate_Thesis.pdf - Accepted Version

Download (2MB) | Preview

Abstract

Saat ini industri minyak dan gas (migas) sedang mengalami masa sulit
dikarenakan anjloknya harga minyak dunia hingga di bawah $25 per barel yang
sebelumnya sempat $110 per barel. Untuk mengatasi permasalahan tersebut
perusahaan migas harus mengurangi biaya-biaya yang dikeluarkan. Salah satu
biaya yang dapat dikurangi oleh perusahaan migas adalah terkait biaya persediaan
(inventory cost). Saat ini KEI menerapkan metode Minimum Maximum Level
(Min Max) untuk mengendalikan persediaan seluruh material jenis MRO. Pada
kenyataannya karakteristik dari masing-masing material MRO itu berbeda-beda
seperti harga, pola penggunaan, lead time, sistem pengadaan dan lain-lain
sehingga perlu dilakukannya pengelompokkan material. Kemudian parameterparameter
dari metode Minimum Maximum Level yang diterapkan seperti nilai
minimum dan maksimum ditentukan dengan teknik perhitungan yang berbeda
dengan teori yang ada. Selain itu KEI juga belum mempertimbangkan besar
inventory cost (holding cost, reorder cost dan shortage cost) dari masing-masing
material MRO.
Langkah pada penelitian ini dimulai dari pengelompokkan material yang
mengadopsi konsep Standar NORSOK yang memperhatikan aspek tingkat
konsekuensi dan tingkat jumlah permintaan. Kemudian dilakukan peramalan
permintaan dengan simulasi Monte Carlo. Setelah itu dilakukan perhitungan
komponen biaya persediaan di masing-masing material MRO. Selanjutnya
dilakukan perhitungan parameter metode pengendalian persediaan pada metode
(s,Q), (R,s,S) dan Eksisting. Lalu dilakukan pembuatan MRP per material MRO
di masing-masing metode. Kemudian dihitung total biaya persediaan dari MRP
yang telah dibuat. Hasil yang didapat ialah terdapat 9 kelompok material MRO
dimana sebagian besar material tergolong tidak kritis. Holding cost dan shortage
cost material MRO berbeda-beda menyesuaikan karakteristik dari material MRO
itu sendiri. Sementara reorder cost material MRO bernilai Rp9,071,839.08 per
satu kali pemesanan. Pemilihan metode terbaik di setiap kelompok material
memperhatikan metode yang menghasilkan total biaya persediaan terkecil.
==========================================================================================================
Today oil and gas industry is having difficult era due to oil price drops
below $25 per barrel which previously had $110 per barrel. To overcome this
problem, oil and gas company should reduce their costs. One of cost that can be
reduced by oil and gas company is inventory cost. Currently KEI applies Min Max
method to control all of MRO material. Whereas the characteristics among MRO
materials are different like price, demand pattern, lead time, procurement system
etc, so it is necessary grouping of material. Moreover the parameters of Min Max
method that applied, like maximum and minimum value, are calculated by
different way from theory. And also KEI has not considered the inventory cost
(holding cost, reorder cost and shortage cost) of each MRO material.
The methodology in this research starts from grouping material which
adopts Standar NORSOK concept that notice about consequences rate and
demand rate. After that, demand forecasting by Monte Carlo simulation. After
that, calculating the component of inventory cost in each MRO material.
Furthermore, calculating the parameters of inventory control method on (s,Q)
method, (R,s,S) method and Existing method. Afterwards, making a MRP in each
MRO material in each inventory control method. Then calculating the total
inventory cost from the MRP. The results show there are 9 groups of MRO
material where mostly materials belong to uncritical material. The holding cost
and shortage cost among MRO material are different, adjust of the characteristics
MRO material itself. While the reorder cost MRO material per order is
Rp9,071,839.08. Choosing the best method in each group is by seeing the method
that generate the lowest inventory cost.

Item Type: Thesis (Undergraduate)
Additional Information: RSI 658.787 Nai a-1
Uncontrolled Keywords: biaya persediaan, metode (R,s,S), metode (s,Q), pengelompokkan material, pengendalian persediaan.
Subjects: H Social Sciences > HD Industries. Land use. Labor > HD55 Inventory control
Divisions: Faculty of Industrial Technology > Industrial Engineering > 26201-(S1) Undergraduate Thesis
Depositing User: Mr. Tondo Indra Nyata
Date Deposited: 13 Jan 2020 06:56
Last Modified: 13 Jan 2020 06:56
URI: http://repository.its.ac.id/id/eprint/72652