Optimasi Lokasi Untuk Penempatan Group Tower Crane Pada Proyek Ciputra World 2 Office Tower Jakarta

Kusumanto, Gusti Rizky (2016) Optimasi Lokasi Untuk Penempatan Group Tower Crane Pada Proyek Ciputra World 2 Office Tower Jakarta. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 3112100123-Undergraduate_Thesis.pdf]
Preview
Text
3112100123-Undergraduate_Thesis.pdf - Accepted Version

Download (2MB) | Preview

Abstract

Proyek Ciputra World 2 Office Tower Jakarta menggunakan
Tower Crane sebagai alat berat yang digunakan untuk
mengangkut alat kontruksi dan material konstruksi. Material
konstruksi yang diangkut meliputi besi tulangan dan batu bata
ringan sedangkan alat konstruksi berupa scaffolding dan
bekesting. Proyek Ciputra World 2 Office Tower Jakarta memiliki
aktivitas pengangkutan yang banyak dan area proyek yang luas
sehingga satu buah Tower Crane tidak cukup untuk memenuhi
seluruh aktivitas pengangkutan, maka digunakan lebih dari satu
Tower Crane. Mengingat Tower Crane yang digunakan lebih dari
satu buah maka penempatan Tower Crane harus ditempatkan pada
titik yang optimal.
Untuk memperoleh titik optimal Tower Crane ada 3 skenario
yang harus dilakukan dalam mengerjakan tugas akhir ini. Masingmasing
skenario memiliki perbedaan sendiri-sendiri seperti yaitu
pada skenario yang pertama ini dicari titik optimal Tower Crane
pada kondisi asli di lapangan sesuai dengan data denah titik
Supply dan radius Tower Crane 60 m.Lalu pada skenario yang
kedua dicari titik optimal Tower Crane pada kondisi titik Supply
yang telah di modifikasi penempatan dan jumlahnya tetapi radius
Tower Crane yang digunakan sama seperti data yang ada di
lapangan yaitu 60 m.Kemudian pada skenario yang ketiga dicari
titik optimal Tower Crane pada kondisi titik Supply seperti skenario 2 tetapi radius Tower Crane yang digunakan diperkecil
sampai mencapai radius yang optimal.
Dari 3 skenario yang telah dilakukan penelitian disimpulkan
bahwa skenario 2 dengan titik optimal group Tower Crane berada
pada koordinat TC1 (79 ; 35) dan TC 2 (55 ; 111) dengan nilai
konflik indek (NC) sebesar 0 persilangan dan keseimbangan beban
kerja antar Tower Crane (σ) 98,170 menit adalah skenario yang
paling optimal.
==================================================================================================================
Project Ciputra World 2 Office Tower Jakarta used Tower
Crane as Construction Device which used to lift Construction
Devices & Materials. Those Materials are Reinforcement Steels &
Light Bricks, while the Devices are formworks & scaffoldings.
Project Ciputra World 2 Office Tower Jakarta needs more than one
Tower Cranes because of frequent lifting activities and the
coverage area that needs the service. To optimize the usage, those
Tower Crane will be placed on optimum points.
To find the optimum point of Tower Crane, there are 3
conditions to fulfill in doing this final assignment. Each conditions
are different to each other, such as in first condition where
Optimum Point of Tower Crane be sought on real field condition
corresponding to sketch data of Supply Point in 60m radius of
Tower Crane. On the second condition, Tower Crane Optimum
Point be sought on Supply Points whose placements and amounts
has been modified, with the radius length referring to field data, 60
m. and the last condition, is to find Tower Crane Optimum Point in
condition of Supply Point similar to second point, but Tower Crane
radius length used, be diminished until it reached Optimum Point.
From these 3 scenarios that have been conducted, the
conclusion is that scenario number 2 with the optimum point group
Tower Crane with the coordinate on TC1 (79 ; 35) and TC 2 (55 ; 111) with the index conflict (NC) number of zero crossover and the
balance of weight between Tower Crane (σ) is 98,170 minutes,
which concluded as the most optimum scenario

Item Type: Thesis (Undergraduate)
Additional Information: RSS 621.873 Kus o
Uncontrolled Keywords: Tower Crane, Titik Optimal, Radius.
Subjects: T Technology > TH Building construction > TH900+ Construction equipment in building construction
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22201-(S1) Undergraduate Thesis
Depositing User: ansi aflacha
Date Deposited: 30 Mar 2020 06:44
Last Modified: 30 Mar 2020 06:44
URI: http://repository.its.ac.id/id/eprint/75604

Actions (login required)

View Item View Item