Analisa Kegagalan Pada Proses Tender Pekerjaan Konstruksi Di PT. X

Masitah, Dewi (2016) Analisa Kegagalan Pada Proses Tender Pekerjaan Konstruksi Di PT. X. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 4312100023-Undergraduate_Thesis.pdf]
Preview
Text
4312100023-Undergraduate_Thesis.pdf - Accepted Version

Download (1MB) | Preview

Abstract

istis. Untuk faktor estimasi, faktor-faktor
kegagalannya adalah terjadi kesalahan estimasi, estimasi kurang sesuai kondisi
sesungguhnya di lapangan, estimasi tidak kompetitif dan cenderung underprice,
nilai tender menjadi overprice atau underprice, dan kurangnya kemampuan
marketing.. Untuk faktor estimasi, faktor-faktor kegagalannya adalah terjadi
kesalahan estimasi, estimasi tidak sesuai kondisi sesungguhnya di lapangan,
estimasi tidak kompetitif dan cenderung underprice, nilai tender menjadi
overprice atau underprice, dan kurangnya kemampuan marketing. Indikator
vkegagalan yang kritis adalah kurangnya tenaga ahli dalam penyusunan
dokumen tender dengan nilai Risk Priority Number (RPN) sebesar 21,75 dan
gagal dalam penawaran dengan nilai Risk Priority Number (RPN) sebesar
25,986. Sumber penyebab dari indikator kegagalan yang paling kritis adalah
“Gagal dalam penawaran” karena mempunyai probabilitas yang lebih tinggi
yakni 0,6155 daripada “kurangnya tenaga ahli dalam penyusunan dokumen
tender“ sebesar 0,1592
======================================================================================================
The division of General Engineering PT. X is a fabrication and shipbuilding
companies often fail in winning the tender. So we need a way to improve the
quality of PT. X in handling the tender, is to perform failure analysis to determine
the cause of the failure of the tender using the Fault Tree Analysis (FTA) and
Failure Modes And Effects Analysis (FMEA). This study will explore and clarify
the factors that led to a division of General Engineering PT. X fails tender and
knowing efforts to prevent the failure of the tender. Identification of the factors of
failure in the tendering of construction work in PT. X factor in terms of tender
documents and estimates. To factor the tender documents, the factors of failure
are specifications in the tender documents are not clear, the design is not in
accordance with the scope of work, still raw design, Scope of work not terdifinisi
clearly, and schedule the implementation of the Owner unrealistic. For estimation
factors, factors of failure is happening estimation error, the estimation does not
match the actual conditions in the field, estimation and uncompetitive and tends to
underprice, tender value becomes overprice or underprice, and the lack of
marketing skills. Critical failure indicator is the lack of experts in the preparation
of tender documents with the value of the Risk Priority Number (RPN) 21.75, and
fails in bid price Risk Priority Number (RPN) amounted to 25.986. The root cause
of the failure of the most critical indicators is "Failed in the offer" because it has a
higher probability than the 0.6155 that "the lack of experts in the preparation of
tender documents" of 0.1592

Item Type: Thesis (Undergraduate)
Additional Information: RSKe 623.87 Mas a
Uncontrolled Keywords: Tender, Pekerjaan Konstruksi, FMEA, FTA.
Subjects: V Naval Science > VM Naval architecture. Shipbuilding. Marine engineering > VM731 Marine Engines
Divisions: Faculty of Marine Technology (MARTECH) > Ocean Engineering > 38201-(S1) Undergraduate Thesis
Depositing User: Mr. Tondo Indra Nyata
Date Deposited: 06 Apr 2020 02:09
Last Modified: 06 Apr 2020 02:09
URI: http://repository.its.ac.id/id/eprint/75684

Actions (login required)

View Item View Item