Abstract

Dalam proses pelaksanaan proyek yang disepakati dengan nilai kontrak yang besar dan waktu pelaksanaan yang lama perlu dilakukan pengendalian agar proyek dapat berjalan sesuai rencana yang ditetapkan. Proyek pembangunan gedung kampus II UIN Sunan Ampel Surabaya dengan nilai kontrak sebesar Rp.453.343.000.000,- dan durasi pelaksanaan proyek kurang lebih selama 32 bulan (multiyears mulai 27 Januari 2020 sampai dengan 29 Agustus 2022, untuk pembangunan beberapa gedung) memerlukan pengendalian. Tugas Akhir ini bertujuan untuk menganalisis kinerja waktu proyek pembangunan gedung kampus II UIN Sunan Ampel Surabaya, sebagai bagian dari pengendalian proyek.
Metode yang digunakan untuk analisis kinerja waktu adalah Earned Value Analysis. Metode Earned Value Analysis dapat mengetahui kinerja proyek dari segi waktu serta memperkirakan berapa waktu yang dibutuhkan untuk menyelesaikan proyek. Analisis kinerja waktu dilakukan untuk keseluruhan gedung, baik untuk kontrak multiyears maupun per tahun anggaran, dan untuk masing-masing gedung.
Dari hasil analisis pada peninjauan keseluruhan gedung, baik untuk kontrak multiyears maupun per tahun anggaran, didapatkan Schedule Performance Index (SPI) lebih dari satu, yang berarti proyek berjalan lebih cepat dari yang direncanakan. Untuk peninjauan masing-masing gedung, didapatkan SPI lebih dari satu untuk gedung AEFG, F1, dan C; serta SPI kurang dari satu untuk gedung AEFG, H, dan I. Dapat disimpulkan bahwa meskipun secara jadwal keseluruhan proyek lebih cepat dari yang direncanakan, namun ada gedung yang pelaksanaannya terlambat.
==================================================================================================================
In the process of implementing an agreed project with a large contract value and a long implementation time, it is necessary to control so that the project can run according to the established plan. The project for the construction of the campus II UIN Sunan Ampel Surabaya with a contract value of Rp.453,343,000,000, - and a project implementation duration of approximately 32 months (multiyears starting January 27, 2020 to August 29, 2022, for the construction of several buildings) requires control. This final project aims to analyze the time performance of the construction project of the campus II UIN Sunan Ampel Surabaya, as part of project control.
The method used for time performance analysis is Earned Value Analysis. The Earned Value Analysis method can determine project performance in terms of time and estimate how long it will take to complete the project. Time performance analysis is carried out for the entire building, both for multiyear contracts and per budget year, and for each building.
From the results of the analysis on the review of the entire building, both for multi-year contracts and per fiscal year, it was found that the Schedule Performance Index (SPI) is more than one, which means the project is running faster than planned. For a review of each building, more than one SPI was obtained for the AEFG, F1, and C buildings; and SPI is less than one for buildings AEFG, H and I. It can be concluded that although the overall project schedule is faster than planned, there are buildings whose implementation is delayed.

Item Type: Thesis (Undergraduate)
Uncontrolled Keywords: Time Performance Analysis, Earned Value Analysis, Analisa Kinerja Waktu, Earned Value Analysis
Subjects: T Technology > T Technology (General) > T56.8 Project Management
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22201-(S1) Undergraduate Thesis
Depositing User: Faizal Tri Mahardho
Date Deposited: 17 Aug 2021 04:42
Last Modified: 17 Aug 2021 04:42
URI: http://repository.its.ac.id/id/eprint/87051

Actions (login required)

View Item View Item