Perbaikan Proses Pemuatan Produk Pupuk Curah Dari Gudang Curah 50.000 Ton Ke Pelabuhan PT. Petrokimia Gresik Dengan Pendekatan Simulasi Untuk Menurunkan Biaya Handling Dan Biaya Demurrage

Kusuma, Indra Permata (2021) Perbaikan Proses Pemuatan Produk Pupuk Curah Dari Gudang Curah 50.000 Ton Ke Pelabuhan PT. Petrokimia Gresik Dengan Pendekatan Simulasi Untuk Menurunkan Biaya Handling Dan Biaya Demurrage. Masters thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 6032201133-MASTER_TESIS.pdf] Text
6032201133-MASTER_TESIS.pdf - Accepted Version
Restricted to Repository staff only until 1 April 2024.

Download (4MB) | Request a copy

Abstract

PT. Petrokimia Gresik memiliki Terminal untuk Kepentingan Sendiri (TUKS) untuk melakukan proses bongkar muat sebagai penunjang kegiatan produksi maupun pendistribusian pupuk. Proses pemuatan dievaluasi dari waktu pemuatan di Gudang Curah, waktu pengiriman dari Gudang Curah 50.000 ton ke Pelabuhan, waktu pemuatan di kapal, serta besarnya demurrage. Tingginya biaya handling disebabkan pada proses pemuatan pupuk curah masih bergantung pada penggunaan wheel loader, dump truk dan vessel crane. Permasalahan terjadi ketika terdapat kendala peralatan dalam proses pemuatan dan pengiriman, yang menyebabkan adanya antrian kapal dan terjadinya peningkatan waktu pemuatan yang melebihi waktu standar, serta peningkatan demurrage yang ditanggung oleh perusahaan.
Ada empat alternatif yang diajukan untuk menurunkan tingginya biaya handling dan biaya demurrage, yaitu (1) Penambahan Armada Pengangkutan; (2) Melakukan Adendum Perjanjian Armada; (3) Pembangunan Proyek Conveying system kapasitas 500 t/h; (4) Pembangunan Proyek Conveying system dengan kapasitas 1000 t/h. Tujuan yang ingin dicapai adalah menentukan skenario alternatif terbaik dalam usaha perbaikan kondisi saat ini. Pupuk curah yang diteliti adalah jenis Pupuk Phonska, Pupuk Urea dan Pupuk NPS. Langkah-langkah dalam penelitian ini adalah (1) model development ; (2) verifikasi dan validasi ; (3) pengembangan skenario alternatif ; (4) analysis of result. Simulasi dilakukan dengan menggunakan metode simulasi kejadian diskrit serta dibantu dengan perangkat lunak Arena 14.0.
Hasil simulasi menunjukkan bahwa, alternatif Pembangunan Proyek Conveying system dengan kapasitas 1000 t/h. Alternatif tersebut dapat mengurangi biaya handling sebesar 89.748% pertahun dan mengurangi biaya demurrage secara keseluruhan dari kondisi eksisting. Berdasarkan perhitungan nilai Net Present value (NPV) sebesar Rp. 276.256.856.453,- Return On Investment (ROI) didapatkan 48.66% dan Payback Period (PP) sebesar 3 Tahun 1 bulan.
=======================================================================================================
PT. Petrokimia Gresik has a Private Interest Terminal to carryiout the loading
andiunloading process to support fertilizer productioniand distribution. The loading
process is evaluated from the time of loading at the warehouse, the time of delivery
from the warehouse of 50,000 tons to the port, the time of loading on the ship, and
the amount of demurrage. The high handling costs are since the bulk fertilizer
loading process still relies on wheel loaders, dump truks and vessel cranes.
Problems occur when there are equipment constraints in the loading and delivery
process, which causes a queue of ships and an increase in loading times that exceeds
the standard time and an increase in demurrage borne by the company.
There are four alternativesiproposed to reduce the high handling costs and
demurrage costs, namely (1) Additional Fleet Transportation; (2) Addendum to the
Fleet Agreement; (3) Construction of a conveying system project with a capacity of
500 t/h; (4) Construction of Project Conveying system with a capacity of 1000 t/h.
The goal to be achieved is to determine the best alternative skenario to improve the
current condition. The bulk fertilizers studied were Phonska Fertilizer, Urea
Fertilizer, and NPS Fertilizer. The steps in this research are (1) model development,
(2) verification and validation, (3) development of alternative skenarios, (4)
analysis of results. The simulation is carriediout using the discrete event simulation
method and is assisting by the Arena 14.0 software.
The simulation results show an alternative to the Construction Project
Conveying system with a capacity of 1000 t/h. These alternatives can reduce
handling costs by 89.748% per year and reduce overall demurrage costs from the
existing condition. Based on the calculation of theiNet Present Value (NPV) of Rp.
276.256.856,453,- Return On Investment (ROI) obtained 48.66% and Payback
Period (PP) of 3 Years 1 month

Item Type: Thesis (Masters)
Uncontrolled Keywords: Simulation, Arena, Demurrage, Bulk Fertilizer, Handling, Simulasi, Arena, Pupuk Curah
Subjects: H Social Sciences > HD Industries. Land use. Labor > HD28 Management. Industrial Management
H Social Sciences > HE Transportation and Communications > HE551 Cargo handling.
T Technology > TS Manufactures > TS161 Materials management.
Divisions: 61101-Magister Management Technology
Depositing User: Indra Permata Kusuma
Date Deposited: 10 Nov 2021 08:36
Last Modified: 10 Nov 2021 08:36
URI: http://repository.its.ac.id/id/eprint/92058

Actions (login required)

View Item View Item