Perhitungan Waktu dan Biaya Pelaksanaan Proyek Pembangunan Apartemen Solo Urbana Residence Tower D dengan Metode Half Slab

Dewi, Izza Aulia (2022) Perhitungan Waktu dan Biaya Pelaksanaan Proyek Pembangunan Apartemen Solo Urbana Residence Tower D dengan Metode Half Slab. Diploma thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 2035201038-Undergraduate_Thesis.pdf] Text
2035201038-Undergraduate_Thesis.pdf - Accepted Version
Restricted to Repository staff only until 1 April 2024.

Download (50MB) | Request a copy

Abstract

Proyek Pembangunan Apartemen Solo Urbana Residence yang dimiliki PT. Mulia Properti Indah merupakan suatu proyek gedung apartemen di lahan seluas 1,6 Ha yang terdiri dari 7 tower yaitu tower A-G dengan jumlah lantai yang bervariasi yaitu 7-13 lantai dengan konsep Urban Smart Living and Investment. Proyek ini berlokasi di Jl. Ring Road Utara KM 6.7, Desa Mipitan, Kelurahan Mojosongo, Kecamatan Jebres, Kota Surakarta, Provinsi Jawa Tengah.
Dalam penyusunan proyek akhir ini akan membahas perhitungan waktu dan biaya dari Proyek Pembangunan Apartemen Solo Urbana Residence Tower D yang memiliki luas bangunan ±6.000 m2 dengan jumlah 13 lantai hunian dan 1 lantai atap. Perhitungan waktu dapat diperoleh dengan menghitung volume per item pekerjaan dibagi dengan kapasitas produksi tiap pekerjaan sehingga dapat diperoleh nilai produktivitas dan durasinya. Sedangkan untuk biaya pelaksanaan berkaitan dengan volume per item pekerjaan, nilai produktivitas, harga upah pekerja, harga sewa alat berat, dan harga material yang digunakan. Sehingga dapat disusun Rencana Anggaran Pelaksanaan (RAP) dan dapat diperoleh pula bobot tiap item pekerjaan.
Proyek Pembangunan Apartemen Solo Urbana Residence menggunakan metode pengecoran konvensional. Namun dalam penyusunan proyek akhir ini digunakan metode half slab untuk struktur pelat lantai. Dalam melakukan perhitungan rencana anggaran pelaksanaan digunakan harga dasar bahan dan harga upah pekerja di Kota Surakarta. Untuk penyusunan jadwal tiap item pekerjaan dilakukan dengan program bantu Microsoft Project. Hasil akhir dari penyusunan proyek akhir ini yaitu dapat memperoleh durasi dan biaya pelaksanaan Proyek Pembangunan Apartemen Solo Urbana Residence Tower D, metode pelaksanaan yang digunakan, serta kurva S.
Dari hasil perhitungan waktu dan biaya yang telah dilakukan, didapatkan durasi pekerjaan selama 238 hari kerja dan biaya pelaksanaan sebesar Rp 14.431.833.878,63.
=====================================================================================================
Construction Project of Solo Urbana Residence Apartment owned by PT. Mulia Properti Indah is an apartment building project on an area of 1,6 hectares consisting of 7 towers, namely tower A-G with varying number of floors, 7-13 floors with the concept of Urban Smart Living and Investment. This project is located on Jl. Ring Road Utara KM 6.7, Desa Mipitan, Kelurahan Mojosongo, Kecamatan Jebres, Kota Surakarta, Provinsi Jawa Tengah.
This final project will discuss the calculation of time and cost of Solo Urbana Residence Tower D Apartment which has a building area of ±6.000 m2 with a total of 13 residential floors and 1 mechanical electrical floor. Time calculation can be obtained by calculating the volume item of work divided by the production capacity of each work so that the productivity value and duration can be obtained. Meanwhile, the implementation costs relate to the volume item of work, the value of productivity, the price of workers' wages, the rental price of heavy equipment, and the price of the materials used. So that an Implementation Budget Plan (RAP) can be arranged and the weight of each item of work can also be obtained.
Construction Project of Solo Urbana Residence Apartment uses cast-in-situ method. However, this final project using the half slab method for the floor slab structure. In calculating the implementation budget plan, the basic price of materials and the price of workers' wages using prices in Surakarta. Arranging schedule of each item of work is done by Microsoft Project. Final result of this final project is to obtain duration and cost of implementation on Construction Project of Solo Urbana Residence Tower D Apartment, implementation method used, and S curve.
From the results of the time and cost calculations that have been done, the duration of work is obtained for 238 working days and the implementation cost is Rp 14.431.833.878,63.

Item Type: Thesis (Diploma)
Uncontrolled Keywords: Rencana Anggaran Pelaksanaan, Waktu Pelaksanaan, Half Slab, Kurva S, Implementation Budget Plan, Time of Implementation, Half Slab, S Curve.
Subjects: T Technology > T Technology (General) > T56.8 Project Management
Divisions: Faculty of Vocational > Civil Infrastructure Engineering (D4)
Depositing User: IZZA AULIA DEWI
Date Deposited: 14 Feb 2022 01:55
Last Modified: 14 Feb 2022 01:55
URI: http://repository.its.ac.id/id/eprint/93801

Actions (login required)

View Item View Item