Analisa penggunaan sumber daya manusia dengan perangkat lunak Stroboscope pada proyek pembangunan Water Tower PT. Gudang Garam Kediri

Utama, Anggarista Widya (2017) Analisa penggunaan sumber daya manusia dengan perangkat lunak Stroboscope pada proyek pembangunan Water Tower PT. Gudang Garam Kediri. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 3114105026-Undergraduate_Theses.pdf]
Preview
Text
3114105026-Undergraduate_Theses.pdf - Published Version

Download (8MB) | Preview

Abstract

Dalam sebuah pembangunan konstruksi, seringkali ditemukan berbagai masalah. Salah satu permasalahan yang sering ditemukan dalam proyek konstruksi jumlah kebutuhan sumber daya manusia. Kebutuhan jumlah sumber daya manusia pada suatu proyek konstruksi dapat berfluktuasi sepanjang waktu proyek. Dengan demikian diperlukan suatu cara untuk mengoptimalkan kebutuhan sumber daya manusia agar biaya konstruksi dapat menjadi lebih efisien. Banyak metode-metode yang digunakan untuk memperkecil fluktuasi jumlah sumber daya manusia. Salah satu metode yang dapat digunakan untuk memecahkan masalah tersebut adalah dengan cara simulasi konstruksi. Simulasi konstruksi adalah alat yang ampuh yang dapat digunakan oleh sebuah perusahaan konstruksi untuk sejumlah tugas seperti sebagai pengukuran produktivitas, analisis risiko, perencanaan sumber daya, desain dan analisis metode konstruksi, dan perencanaan situs. Keberhasilan simulasi di tingkat konstruksi telah menyebabkan upaya alami untuk menggunakan simulasi di tingkat konstruksi proyek
Untuk mencapai hasil proyek konstruksi yang optimal dalam hal efisiensi tenaga kerja program Stroboscope diaplikasikan pada proyek pembangunan water tower PT Gudang Garam Kediri. Sebelum melakukan simulasi pengumpulan data dan observasi pun dilakukan untuk menentukan produktivitas pada proyek tersebut. Setelah itu dilakukan penyusunan model simulasi kedalam program Stroboscope. Hasil dari simulasi ini adalah menghasilkan diagram pareto, dari diagram tersebut dapat digunakan sebagai parameter acuan atau batasan produktifitas. Dimana nilai working time dan nilai cost mendekati 0, semakin tinggi nilai produktifitas pekerjaan tersebut. Maka dari batasan tersebut kondisi Scenario simulasi II merupakan kondisi simulasi dengan produktifitas yang optimum. Dengan nilai total cost 2.95 milyar rupiah dan working time 45 hari

=========================================================================

In a project construction, often found various problems. One of the problems often found in construction projects the number of human resource needs. Needs of human resources in a construction project can fluctuate over time. Thus we need a way to optimize the human resource requirements in order that the construction cost can be more efficient. Many methods are used to minimize fluctuations in the number of human resources. One method that can be used to solve the problem is by means of simulation construction. Construction simulation is a powerful tool that can be used by a construction company for a number of tasks such as the measurement of productivity, risk analysis, resource planning, design and construction methods of analysis and site planning. The success of the simulation at the level of construction has led to a natural attempt to use the simulation on the level of construction project
To achieve optimal construction project in terms of labor efficiency stroboscope program was applied to the water tower construction project PT Gudang Garam Kediri. Before performing the simulation data collection and observation was performed to determine the productivity of the project. Once that is done the preparation of the program into the simulation model stroboscope.
The results of this simulation is to produce a Pareto diagram, from the diagram can be used as a reference parameter or limit productivity. That the value of working time and cost value close to 0, the higher the productivity of the work. So from this constraint condition Scenario II simulation is simulated conditions with optimum productivity. With a total value of 2.95 billion rupiah cost and working time 45 days

Item Type: Thesis (Undergraduate)
Uncontrolled Keywords: Idle time; optimal; Perencanaan konstruksi; tenaga kerja; simulasi konstruksi; Stroboscope; construction planning; labor; construction simulation;
Subjects: H Social Sciences > H Social Sciences (General)
Q Science > QA Mathematics > QA76 Computer software
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22201-(S1) Undergraduate Thesis
Depositing User: ANGGARISTA WIDYA UTAMA
Date Deposited: 28 Feb 2017 04:30
Last Modified: 05 Mar 2019 07:18
URI: http://repository.its.ac.id/id/eprint/2299