Analisa Risiko Rantai Pasok Konstruksi Dengan Menggunakan Model Simulasi

Rachmasari, Herlinda (2019) Analisa Risiko Rantai Pasok Konstruksi Dengan Menggunakan Model Simulasi. Masters thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 0921650024017-Master_Thesis.pdf]
Preview
Text
0921650024017-Master_Thesis.pdf - Accepted Version

Download (2MB) | Preview

Abstract

Industri konstruksi merupakan sektor yang memiliki kekomplekan dan kinerja yang buruk. terutama dalam waktu dan biaya. Salah satu kekomplekan proyek adalah dalam manajemen rantai pasok konstruksi. Risiko rantai pasok sering terjadi dikarenakan spesifikasi disain kurang optimal, pemilihan rantai pasok yang kurang baik, pengiriman material yang bermasalah atau manajemen dalam penyimpanan material yang tidak tertata. Manajemen rantai pasok konstruksi merupakan suatu gagasan yang mengatur siklus rantai pasok konstruksi dengan mengindentifikasi risiko yang dapat menyebabkan kegagalan dalam proyek. Identifikasi risiko yang dilakukan dari tahap awal konstruksi dapat meminimalisir dampak risiko pada proyek konstruksi. Risiko yang telah teridentifikasi selanjutnya dianalisis dengan suatu model simulasi agar dapat diberikan strategi penanganan yang tepat sehingga menghindari terjadi keterlambatan proyek terutama pada waktu dan biaya. Tujuan dalam penelitian ini adalah memberikan strategi pada setiap aktivitas rantai pasok yang paling beresiko pada proyek konstuksi. Model simulasi dibantu dengan simulasi Monte Carlo dengan menggunakan Microsoft excel. Distribusi tiap risiko dibantu dengan program easy fit dan nilai random dengan menggunakan program @risk.
Hasil akhir penelitian ini menemukan bahwa dari 30 risiko yang telah dilakukan simulasi monte, 4 risiko masuk dalam penilaian risiko tinggi, 11 risiko masuk penilaian risiko medium dan 15 risiko masuk penilaian risiko rendah. 4 risiko yang mendapat nilai tinggi selanjutnya dilakukan wawancara dengan project manager kontraktor utama untuk ditemukan strategi penanganan risiko tersebut. Respon dari 4 risiko tersebut adalah pengurangan dampak risiko dengan mengikuti standart operasional proyek konstruksi berupa pengajuan ijin material dan ijin pelaksanaan pekerjaan, serta memperhatikan jumlah pasokan di gudang tidak boleh kurang dari 30% agar tidak terjadi waktu tunggu dilapangan. Hasil penelitian ini nantinya dapat memberikan laporan kepada project manager sehingga dapat mengantisipasi dampak risiko rantai pasok konstruksi yang mungkin terjadi pada pelaksanaan kontruksi
================================================================================================
The construction industry is a sector that has complexity and bad performance, especially with overtime and budget. One of the project complications is in construction supply chain management. Supply chain risk often occurs due to less optimal design specifications or bad supply chain selection, the problematic of material transportation and management material in warehouse that unorganized. Construction supply chain management is an idea that regulates the supply chain construction cycle by identifying risks that can cause failure in the project. Risk that identification during stages of construction can minimize the impact of risks on construction projects. The risks that have been identified then analyzed by a simulation model so that appropriate treatment strategies can be given to avoid project delays, especially on time and costs. The purpose of this research is to provide strategies for each supply chain activity that is most at risk in construction projects. The simulation model is support by Monte Carlo simulation with Microsoft excel program.
The final result of this study found that out of 30 risks that have been carried out monte simulation, 4 risks are included in the high risk assessment, 11 risks are entered in the medium risk assessment and 15 the risk of entering the risk assessment is low. 4 risks that get high scores are then interviewed with the main contractor project manager to find the risk management strategy. The response of these 4 risks is to reduce the impact of risk by following the operational standards of construction projects in the form of material permit applications and permits to carry out work, and noting the amount of supply in the warehouse should not be less than 30% so there is no waiting time in the field. The results of this study will be able to provide reports to the project manager so that they can anticipate the impact of supply chain risk construction that may occur in the implementation of construction

Item Type: Thesis (Masters)
Additional Information: RTMT 658.155 Rac a-1 2019
Uncontrolled Keywords: Manajemen Risiko Rantai Pasok Konstruksi, Industri Konstruksi, Simulasi Monte Carlo
Subjects: H Social Sciences > HD Industries. Land use. Labor > HD61 Risk Management
T Technology > T Technology (General) > T56.8 Project Management
T Technology > TH Building construction
T Technology > TS Manufactures
Divisions: Faculty of Business and Management Technology > Management Technology > 61101-(S2) Master Thesis
Depositing User: HERLINDA RACHMASARI
Date Deposited: 31 Jul 2021 08:45
Last Modified: 13 Sep 2021 06:55
URI: http://repository.its.ac.id/id/eprint/61169

Actions (login required)

View Item View Item