Metode Pelaksanaan Proyek Pembangunan Bendung Gerak Sembayat Kabupaten Gresik

Kurniawan, Achmad Wachid Wahyu and Purwati, Mayta Ayu (2015) Metode Pelaksanaan Proyek Pembangunan Bendung Gerak Sembayat Kabupaten Gresik. Diploma thesis, Institut Technology Sepuluh Nopember.

[thumbnail of 3112030015-3112030050-Non Degree.pdf]
Preview
Text
3112030015-3112030050-Non Degree.pdf - Published Version

Download (2MB) | Preview

Abstract

Salah satu cara pemanfaatan sumber daya air yang
mencakupi kebutuhan air irigasi, kebutuhan air minum dan
pengendalian banjir tentunya bagi masyarakat yaitu pembangunan
bendung gerak. Desa Sidomukti Kecamatan BungahKabupaten
Gresik masih memiliki daerah-daerah yang sistem irigasi dan
pengolahan air minumnya kurang baik, terutama pada musim
kemarau.Melihat kondisi tersebut, maka pemerintah propinsi jawa
timur khususnya di Desa Sidomukti Kecamatan Bungah
Kabupaten Gresik membangun bendung gerak sembayat yang
letaknya di Kabupaten Gresik.Sistem manejemen kontruksi dapat
mengoptimalkan pemanfaatan sumber daya yang meliputi tenaga
manusia,peralatan,biaya,dan waktu pelaksanaan.
Dalam penulisan tugas akhir ini menggunakan metode
pelaksanaan yang sama persis seperti yang ada dilapangan
sehingga dari data yang kami dapat dari lapangan kami dapat
menghitung volume pekerjaan, jumlah alat berat yang
dibutuhkan, produktifitas alat berat, kebutuhan bahan dan
material, kebutuhan tenaga kerja, rencana anggaran biaya hingga
mendapatkan kurva s.
Pada proyek pembangunan Bendung Gerak Sembayat
Kecamatan Bungah Kabupaten Gresik memakan biaya
iii
Rp311.039.760.567. Mulai dari pekerjaan Persiapan, pekerjaan
sungai baru atau sudetan yang meliputi Perlindungan Dasar
Sungai bagian Hulu (Apron) dan Palung Sungai (Riverbed),
Perlindungan Dasar Sungai bagian Hilir (Apron) dan Palung
Sungai (Riverbed), Bendung Pelimpah/Overflow Weir, Pekerjaan
Jembatan, Dinding Abutment bagian hulu, setelah pekerjaan
sudetan (sungai baru) maka melanjutkan pekerjaan Saluran
bypass (bypass channel), pekerjaan Intake Irigasi. Pada proyek ini
menggunakan alat berat yaitu backhoe, bulldozer, dumptruck dan
compactor untuk pekerjaan clearing, galian, urugan, sedangkan
untuk pekerjaan struktur menggunakan truck mixer, concrete
vibrator, dan pekerjaan dewatering menggunakan alat seperti
engine pump, submergesible, dan juga pipa sebagai alat
pembantunya. Proyek ini memakan waktu selama 929 hari
kalender.
==========================================================================================================
One of function water resources mode which cover
irrigation water requirement, and the requirements of drink
water and flood control for the people is moving weir
construction desa sidomukti kecamatan bungah kabupaten
gresik still has regions that using a poor irrigation system and
drink water processing, especially in the summer condition. In
that case, so provincial government of east java especially in
desa sidomukti kecamatan bungah kabupaten gresik build the
sembayat moving weir and the location in kabupaten gresik.
Management system of construction can optimize the function
of the resources such as human force, equipment, cost and its
time will be held.
In this writing of final project is using similar
implementation method like what they do in the reality project/
field so from the data that we got from reality project/field we
could calculate the volume of work, total heavy equipment that
we need, heavy equipment productivity, material and stuff
requipment, workers need, budget plan till we got the S curve.
v
On the construction project of sembayat moving weir
kecamatan bungah kabupaten gresik is spending cost
Rp310.986.410.567 start from working preparation, the new
river work which covers head water of river and riverbed, and
protection the downstream of the river; over weir, bridge work,
the wall of abutment downstream. After the new river work
have done, irrigation intake work. This project uses weight
equipment such as backhoe, bulldozer and dumptruck for
clearing, digging and burying. While structuring uses truck
mixer amd concrete vibrator. In the meantime dewatering uses
engine pump, submergesible and also pipe as the medium. This
project took until 929 days of calendar.

Item Type: Thesis (Diploma)
Additional Information: RSS 627.8 Kur m
Uncontrolled Keywords: Metode Pelaksanaan Bendungan, Bendung Gerak Sembayat, Sumber Daya Air.
Subjects: T Technology > TC Hydraulic engineering. Ocean engineering > TC167 Dams, reservoirs
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22401-(D3) Diploma 3
Depositing User: Mr. Tondo Indra Nyata
Date Deposited: 19 Jun 2019 06:12
Last Modified: 19 Jun 2019 06:12
URI: http://repository.its.ac.id/id/eprint/63156

Actions (login required)

View Item View Item