Perencanaan Dermaga Island Berth Untuk Kapal Tanker 85.000 Dwt Untuk Loading Oil Product : Bbm Ron 85 Di Tersus Pt Badak Ngl, Bontang

Utami, Adita (2016) Perencanaan Dermaga Island Berth Untuk Kapal Tanker 85.000 Dwt Untuk Loading Oil Product : Bbm Ron 85 Di Tersus Pt Badak Ngl, Bontang. Undergraduate thesis, Institut Teknologi Sepuluh Nopember Surabaya.

[thumbnail of 3112100145-undergraduate-theses-.pdf]
Preview
Text
3112100145-undergraduate-theses-.pdf - Published Version

Download (5MB) | Preview

Abstract

Seiring dengan peningkatan permintaan Bahan Bakar
Minyak (BBM) jenis premium yang diprediksi oleh BUMN
minyak dan gas (MIGAS) sebesar 31 juta kiloliter dimulai dari
tahun 2013, maka PT. Pertamina (Persero) berencana untuk
meningkatkan kapasitas kilang-kilang minyak yang ada dengan
cara melakukan pengembangan untuk kilang baru yang akan
diletakkan pada area offshore PT. Badak NGL Bontang. Kilang
tersebut direncanakan mengalami penambahan kapasitas
produksi sebesar 200.000 barel/hari.
Untuk mendukung peningkatan kegiatan produksi dan
pengiriman Bahan Bakar Minyak Premium diperlukan adanya
suatu dermaga yang dapat melayani peningkatan arus bongkar
muat minyak yang akan meningkat seiring dengan peningkatan
produksi. Dermaga Island Berth yang direncanakan adalah
dermaga minyak untuk kapal tanker dengan kapasitas 85000
DWT.
Perencanaan dermaga baru ini telah diwujudkan dalam
bentuk gambar rencana pengembangan dermaga. Namun untuk
mewujudkan pembangunan dermaga tersebut diperlukan detail
engineering desain yang meliputi perencanaan loading platform,
breasting dolphin, mooring dolphin, catwalk, dan floating
pontoon. Selain detail engineering desain perlu juga ditinjau
ii
kebutuhan kedalaman perairan pada area dermaga Island Berth,
hal ini dikarenakan kedalaman perairan harus mencukupi draft
dari kapal 85.000 DWT yang direncanakan akan bersandar di
dermaga minyak PT. Pertamina (Persero).
Pengerjaan konstruksi dermaga Island Berth sepenuhnya
dilakukan di laut, sehingga dalam pengerjaannya digunakan
kapal pontoon sebagai direksi kit. Perencanaan dermaga Island
Berth ini mencakup perencanaan fasilitas laut, perencanaan
struktur dermaga, dan perencanaan alat-alat yang digunakan
untuk proses bongkar muat. Selain itu perlu juga direncanakan
terkait metode pelaksanaan pembangunan yang akan digunakan
dalam pembangunan dermaga tersebut. Dalam perencanaan
dermaga juga harus ditinjau terkait rencana anggaran biaya dari
dermaga tersebut.
Dari hasil analisis perhitungan didapatkan kebutuhan
dermaga dengan ketentuan Loading Platform sebesar 35,5 x 24
m2, Breasting dolphin 8 x 8 m2, Mooring Dolphin 6,5 x 6,5 m2
,Catwalk dengan panjang 24, 28, dan 30 meter, dan struktur
floating pontoon. Rencana anggaran biaya yang diperlukan
untuk pembangunan dermaga ini adalah Rp. 192. 194.800.00
============================================================
The increasing needs of fuel which is predicted by BUMN Oil
and Gas division is about 31 million ton/year start from the
beginning of 2013, so PT. Pertamina (Persero) have a planned to
increase the capasity of the fuel refinary by develop new refinary
which is located in the offshore area of PT. Badak NGL, Bontang.
These refinaries were planned to increase the capasity of BBM
RON 85 about 200.000 barrel/day.
In order to support the increasing of production and
distribution of fuel, the port need to be able to serve ships which
has bigger capasity by the increasing of fuel’s production. Island
Berth’s design is expected to be able to handle ship up to 85000
DWT.
The drawing of this Island Berth have been planned as a
dock development. In order to realize this project, there should be
a detail of engineering design of the Island Berth include :
loading platform structure, breasting dolphin, mooring dolphin,
catwalk, and floating pontoon. Besides the detail of engineering
design, there should be an evaluation to evaluate the depth of the
Island Berth’s area because of the depth should be sufficient for
draft of 85000 DWT tankershp which si plan to berthing on the
dock of PT. Pertamina (Persero).
iv
The construction of the Island Berth is on the offshore area,
so during the construction process using pontoon ship as the
direction keet. The objective development of this Island Berth
contain of offshore fasilities, dock structure, and equipments
which is used for loading and unloading of oil product. Besides,
there should be plann for the construction method of the Island
Berth. In the dock development, there should be budget plan of
the project.
From the construction analysis, the requirement of the dock
design are : loading Platform 35,5 x 24 m2, Breasting dolphin 8 x
8 m2, Mooring Dolphin 6,5 x 6,5 m2 ,Catwalk 24, 28, and 30
meter, andd floating pontoon structure. The budget plan to
construct this project is about Rp. 192. 194.800.000.

Item Type: Thesis (Undergraduate)
Additional Information: RSS 627.98 Uta p
Uncontrolled Keywords: Dermaga Island Berth, Kapal Tanker 85000 DWT, Struktur Dermaga, Metode Pelaksanaan, Rencana Anggaran Biaya.
Subjects: T Technology > TC Hydraulic engineering. Ocean engineering > TC1680 Offshore structures
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22201-(S1) Undergraduate Thesis
Depositing User: EKO BUDI RAHARJO
Date Deposited: 09 Dec 2019 06:52
Last Modified: 09 Dec 2019 06:52
URI: http://repository.its.ac.id/id/eprint/72303

Actions (login required)

View Item View Item