Aziz, Labib Zainul (2023) Analisis Penjadwalan Proyek Boiler Dengan CPM (Critical Path Methode) Dan PERT (Program Evaluation And Review Technique). Masters thesis, Institut Teknologi Sepuluh Nopember.
| ![[thumbnail of 6032211211-Master_Thesis.pdf]](http://repository.its.ac.id/style/images/fileicons/text.png) | Text 6032211211-Master_Thesis.pdf - Accepted Version Restricted to Repository staff only until 1 October 2025. Download (52MB) | Request a copy | 
Abstract
Sebelum proyek berjalan dilakukan perencanaan awal diantaranya perencanaan jadwal. Proyek Boiler 35 Ton/Jam sebanyak 3 Unit ini merupakan proyek milik PT Supreme Paper Solution dan menunjuk CV INTAN WELL sebagai kontraktor dengan durasi selama 90 hari dan nilai kontrak sebesar 4.3 miliar. Banyaknya aktifitas dan sumber daya yang diperlukan dalam penyelesaian proyek boiler ini sehingga diperlukan analisa penjadwalan yang optimal agar tidak terjadi keterlambatan proyek sehingga kontraktor tidak mendapatkan penalty fee dan tidak berdampak terhadap produksi perusahaan. Penelitian ini akan membentuk jaringan kerja (network diagram) serta WBS, menganalisis penjadwalan kerja dengan metode CPM dan PERT untuk acuan pelaksanaan instalasi yang sistematis dan efektif berdasarkan network diagram yang sudah dibuat, perbandingan durasi pelaksanaan Proyek antara metode CPM dan PERT dan membentuk S-Curve dari durasi yang dipilih. Hasil dari perencanaan jadwal ini dapat menjadi rekomendasi acuan pelaksanaan proyek dilapangan. Hasil dari penelitian ini Dengan metode CPM proyek Instalasi Boiler dapat diselesaikan dalam jangka waktu 90 Hari. Dan lintasan kritis terletak pada kode kegiatan A1, B1, B2, B3, B7, B9, B10, I1, I2, J1. Sedangkan dengan metode PERT Proyek Instalasi Boiler dapat diselesaikan dalam jangka waktu 104 Hari. Hasil lintasan kritis pada PERT sama dengan CPM. Pada metode ini dilakukan sampling varian durasi target untuk mengetahui probabilitas dengan hasil didapatkan prosentase probabilitas dengan nilai tertinggi 99% yaitu 115 hari. Jika dengan waktu target 110 hari didapatkan keberhasilan 92% dan jika dilakukan dengan waktu target 104 hari atau sama dengan waktu PERT maka didapatkan prosentase keberhasilan 50%. Jika waktu dimampatkan menjadi 97 hari probabilitasnya 5% dan 91 hari probabilitasnya 0%. Proyek ini harus dimonitor dengan ketat khususnya kegiatan kritis karena grafik kurva-s naik cukup signifikan. Sehingga durasi proyek yang direncanakan dapat terlaksana tepat waktu. Dapat diketahui biaya langsung dan tidak langsung pada waktu normal 104 hari sebesar Rp1,840,176.000. Dengan penambahan waktu 1 jam durasi 97 Hari biaya langsung dan tidak langsung sebesar Rp1,961,959.500. Selanjutnya dengan penambahan waktu 2 jam durasi 91 Hari biaya langsung dan tidak langsung sebesar Rp2,225,060.500. Dan jika durasi proyek diperpanjang selama 110 hari biaya langsung dan tidak langsung sebesar Rp1,946,340.000. Kemudian jika makin diperpanjang selama 115 hari biaya langsung dan tidak langsung sebesar Rp2,034,810.000.
=================================================================================================================================
Before the project runs, initial planning is carried out including schedule planning. The 35 Ton I Hour Boiler  Project for 3 Units is a project owned by PT Supreme Paper  Solution  and appoints  CV INTAN  WELL  as a contractor with a duration of 90 days and a contract value of 4.3 billion. The number of activities and resources required in completing  this boiler  project so that an optimal  scheduling analysis  is needed  so that there is no project delay so that the contractor does not get a penalty fee and does not have an impact on company  production. This   research   will  form a  network   diagram and  WBS,   analyse   work scheduling   with  the  CPM  and PERT methods for reference to systematic and effective installation implementation based  on the network  diagram that has been made, comparison of project implementation duration between the CPM and PERT methods  and form an S-Curve  of the selected duration. The results of this schedule planning  can be  a reference  recommendation for  project  implementation in the field. The 	results of this 	study  With  the 	CPM 	method 	the  Boiler 	Installation project can be completed  within a period of 90 days. And the critical  trajectory is locatedonactivitycodesA1, B1, B2, B3, B7, B9, B10, I1, I2, 11. Whereas with the PERT  method  the Boiler  Installation Project  can be completed  within  104 days. The critical  trajectory  on PERT is the same as CPM.  In this method,  sampling  of target duration  variants  is carried out to determine the probability with the results obtained  the  probability percentage  with the  highest  value  of 99%,  namely  115 days. If the target time is 110 days, 92% success is obtained and if it is done with a target time of 104 days or the same as the PERT time, the percentage  of success is 50%.  If the time is compressed  to 97 days  the probability is 5% and 91 days the probability 	is 	 0%.  This 	project 	must 	be 	closely 	monitored,	 especially 	critical activities because the s-curve graph rises significantly. It can be seen that the direct and  indirect  costs  at a normal  time  of 104  days  are  Rp1,840,176,000. With  the addition   of 1 	hour  of 	duration 97  days  direct  and indirect 	costs  amounted 	to Rp1,961,959,500. Furthermore, with the addition  of 2 hours  of duration  91 days direct and indirect costs amounted  to Rp2,225,060,500. And if the project duration is extended  for 110 days  direct and indirect  costs amounted  to Rp1,946,340,000. Then  if it is further  extended  for 115 days  the direct  and indirect  costs  are  IDR 2,034,810,000.
| Item Type: | Thesis (Masters) | 
|---|---|
| Uncontrolled Keywords: | Network Diagram, Critical Path Method (CPM), Program Evaluation And Review Technique (PERT) | 
| Subjects: | H Social Sciences > HD Industries. Land use. Labor > HD69.T54 Time management. Scheduling T Technology > TJ Mechanical engineering and machinery T Technology > TJ Mechanical engineering and machinery > TJ263.5 Boilers (general) | 
| Divisions: | Interdisciplinary School of Management and Technology (SIMT) > 61101-Master of Technology Management (MMT) | 
| Depositing User: | Labib Zainul Aziz | 
| Date Deposited: | 07 Sep 2023 06:03 | 
| Last Modified: | 15 May 2024 10:24 | 
| URI: | http://repository.its.ac.id/id/eprint/103694 | 
Actions (login required)
|  | View Item |