Studi Perancangan Koordinasi Proteksi Arus Lebih Pada Sistem Kelistrikan PT. Pupuk Sriwijaya Palembang Plant PIIIB

Nugraha, Rahmadilla Primasiwi (2022) Studi Perancangan Koordinasi Proteksi Arus Lebih Pada Sistem Kelistrikan PT. Pupuk Sriwijaya Palembang Plant PIIIB. Other thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 07111840000054-Undergraduate_Thesis.pdf] Text
07111840000054-Undergraduate_Thesis.pdf - Accepted Version
Restricted to Repository staff only until 1 October 2024.

Download (2MB) | Request a copy

Abstract

Keandalan dan kontinuitas suatu sistem tenaga listrik di industri dalam melayani konsumen sangat bergantung pada sistem proteksi yang sedang digunakan. Sistem proteksi memiliki perananan penting di dalam mengurangi kerusakan peralatan yang terganggu, mengisolir bagian sistem yang terganggu sekecil mungkin dan secepat mungkin, serta mencegah meluasnya gangguan yang mungkin terjadi. Dikarenakan konsumsi energi listrik oleh beban-beban industri berlangsung secara terus menerus, maka peralatan proteksi dengan koordinasi yang baik sangat dibutuhkan di dalam sistem untuk mencegah berkurangnya kontinuitas aliran daya, menurunnya keandalan, dan juga blackout pada sistem kelistrikan industri. Sebagai produsen pupuk nasional, PT. Pupuk Sriwidjaja Palembang saat ini mempunyai rencana untuk menambahkan pabrik baru bernama pabrik PIIIB dikarenakan pabrik PIII yang lama sudah sangat tua dan memiliki banyak masalah di dalam sistem kelistrikannya. Sehingga diperlukan adanya pembaruan peralatan dengan peralatan yang masih baru. Dengan penambahan pabrik baru tersebut, agar kontinuitas produksi tidak terganggu dan nilai keandalannya tinggi, maka dibutuhkan perencanaan pengaman yang baik pada desain sistem kelistrikan yang sudah ada. Oleh karena itu, melalui tugas akhir ini dilaksanakan studi perencanaan koordinasi proteksi arus lebih pada PT. Pupuk Sriwidjaja Palembang Plant PIIIB yang tepat dalam mendeteksi dan mengisolir gangguan sehingga tidak mengganggu sistem yang berjalan dan dapat mencegah kerusakan peralatan listrik yang mungkin akan terjadi.
===================================================================================================================================
The reliability and continuity of an electric power system in the industry in serving consumers is highly dependent on the protection system being used. Protection systems have an important role in reducing damage to disrupted equipment, isolating the parts of the system that are disturbed as small as possible and as quickly as possible, and preventing the spread of disturbances that may occur. Because the consumption of electrical energy by industrial loads continues, protection equipment with good coordination is needed in the system to prevent reduced continuity of power flow, decreased reliability, and also blackouts in industrial electrical systems. As a national fertilizer producer, PT. Pupuk Sriwidjaja Palembang currently has plans to add a new factory called the PIIIB factory because the old PIII factory is very old and has many problems in its electrical system. So it is necessary to update the equipment with new equipment. With the addition of the new plant, so that the continuity of production is not disturbed and the reliability value is high, a good safety planning is needed on the design of the existing electrical system. Therefore, through this final project, a planning study of the coordination of overcurrent protection in PT. Pupuk Sriwidjaja Palembang Plant PIIIB is appropriate in detecting and isolating disturbances so that it does not interfere with the running system and can prevent damage to electrical equipment that may occur.

Item Type: Thesis (Other)
Additional Information: RSE 621.317 Nug s-1 2022
Uncontrolled Keywords: Koordinasi Proteksi, Keandalan, Kontinuitas, Perencanaan, Coordination of Protection, Reliability, Continuity, Planning
Subjects: T Technology > TK Electrical engineering. Electronics Nuclear engineering > TK2861 Electric relays
Divisions: Faculty of Intelligent Electrical and Informatics Technology (ELECTICS) > Electrical Engineering > 20201-(S1) Undergraduate Thesis
Depositing User: - Davi Wah
Date Deposited: 23 Apr 2024 10:07
Last Modified: 23 Apr 2024 10:07
URI: http://repository.its.ac.id/id/eprint/107906