ANALISIS PERBANDINGAN WAKTU DAN BIAYAPELAKSANAAN PEMBANGUNAN GEDUNG JANTUNG RUMAH SAKIT UPT VERTIKAL SURABAYA DENGAN MENGGUNAKAN BEKISTING METODE KONVENSIONAL DAN ALUMINIUM FORMWORK

Iftiawan, Firstama Panduwinata (2025) ANALISIS PERBANDINGAN WAKTU DAN BIAYAPELAKSANAAN PEMBANGUNAN GEDUNG JANTUNG RUMAH SAKIT UPT VERTIKAL SURABAYA DENGAN MENGGUNAKAN BEKISTING METODE KONVENSIONAL DAN ALUMINIUM FORMWORK. Diploma thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 2035201068-Undergraduate_Thesis.pdf] Text
2035201068-Undergraduate_Thesis.pdf - Accepted Version
Restricted to Repository staff only

Download (46MB) | Request a copy

Abstract

Peningkatan tuntutan konsumen terhadap kebutuhan properti tersedia sesuai waktu yang ditentukan proyek properti menjadi salah satu faktor yang menentukan dalam membangun kredibilitas sebuah perusahaan jasa konstruksi, terutama dalam proyek gedung bertingkat. Dalam proses pelaksanaan konstruksi gedung bertingkat, pekerjaan percetakan beton (bekisting) memerlukan biaya yang besar dalam pelaksanaannya, sehingga diperlukan penentuan metode yang memiliki nilai yang ekonomis dari segi biaya maupun waktu pelaksanaannya. Maka dari itu, pihak perusahaan jasa konstruksi harus melakukan berbagai hal terobosan teknologi dalam metode pelaksanaan konstruksinya. Dalam pelaksanaan pekerjaan bekisting pada proyek pembangunan Gedung Jantung Rumah Sakit UPT Vertikal Surabaya, Jawa Timur menggunakan metode bekisting konvensional yang merupakan bekisting berbahan dasar kayu. Sedangkan, saat ini pekerjaan bekisting berkembang dengan banyaknya metode yang mempengaruhi biaya dan waktu pelaksanaan pekerjaannya. salah satu nya yaitu metode aluminium formwork, yang merupakan material bekisting berbahan dasar aluminium dimana bahan material ini ramah lingkungan dan ekonomis. Oleh karena itu, diperlukan adanya penelitian tentang perbandingan dari segi waktu dan biaya dari kedua metode bekisting tersebut. Metode yang digunakan untuk memperoleh data dalam penyusunan tugas akhir ini dengan menggunakan dua metode data. Pertama menggunakan data primer yang diperoleh dari observasi lapangan, wawancara, dan dokumentasi. Sedangakan metode yang kedua yaitu data sekunder dengan menggunakan data-data proyek seperti RKP, gambar kerja, dan literatur lain. Perhitungan waktu dan biaya pelaksanaan antara Bekisting Konvensional dan Aluminium Formwork menggunakan referensi utama dari Ir. A. Soedrajat S, Analisa (cara modern) Anggaran Biaya Pelaksanaan. Penelitian ini meninjau pada proyek pembangunan Gedung Jantung Rumah Sakit UPT Vertikal Surabaya dengan membandingkan metode antara Bekisting Konvensional dan Aluminium Formwork pada pekerjaan struktur atas meliputi kolom, shearwall, balok, dan pelat terhadap perhitungan waktu dan biaya. Lantai yang ditinjau pada penelitian ini mulai dari lantai basement sampai dengan lantai 11. Diperoleh hasil dari pengolahan data yang ada bahwa aluminium formwork dapat diselesaikan dengan durasi 172 hari sedangkan bekisting konvensional 212 hari. Ditinjau dari segi biaya total pekerjaan struktur atas pada metode aluminium formwork menghabiskan total biaya Rp 70.861.252.020.94. sedangkan metode bekisting konvensional mencapai Rp 61.226.868.258,00.
==============================================================================================================================
Increased consumer demands for property needs are available according to the specified time property projects become one of the decisive factors in building the credibility of a construction service company, especially in multi-storey building projects. In the process of implementing multi-storey building construction, concrete molding work (formwork) requires a large cost in its implementation, so it is necessary to determine a method that has an economic value in terms of cost and time of implementation. Therefore, the construction service company must make various technological breakthroughs in the construction implementation method. In the implementation of formwork work in the construction project of the UPT Vertical Hospital Heart Building Surabaya, East Java using conventional formwork methods which are wood-based formwork. Meanwhile, currently formwork work is developing with many methods that affect the cost and time of carrying out the work. one of them is the aluminum formwork method, which is an aluminum-based formwork material where this material is environmentally friendly and economical. Therefore, research is needed on the comparison in terms of time and cost of the two formwork methods. The method used to obtain data in the preparation of this final project uses two data methods. The first uses primary data obtained from field observations, interviews, and documentation. While the second method is secondary data using project data such as RKP, working drawings, and many literature. Calculation of the time and cost of implementation between Conventional Formwork and Aluminum Formwork using the main reference from Ir. A. Soedrajat S, Analysis (modern way) of Implementation Cost Budget. This research reviews the construction project of the UPT Vertical Surabaya Hospital Heart Building by comparing the method between Conventional Formwork and Aluminum Formwork on the upper structure work including columns, shearwall, beams, and plates against the calculation of time and cost. The floors reviewed in this study start from the basement floor to the 11th floor. Obtained results from processing existing data that aluminum formwork can be completed with a duration of 172 days while conventional formwork 212 days. In terms of the total cost of the upper structure work on the aluminum formwork method spent a total cost of Rp 70.861.252.020.94. while the conventional formwork method reached Rp 61.226.868.258,00.

Item Type: Thesis (Diploma)
Uncontrolled Keywords: Formwork, Conventional Formwork, Aluminum Formwork, Time, Cost, Bekisting, Bekisting Konvensional, Aluminium Formwork, Waktu, dan Biaya
Subjects: T Technology > TA Engineering (General). Civil engineering (General) > TA660.C6 Columns
T Technology > TH Building construction > TH11 Builders' and contractors' bulletins. Including prices, permits, etc.
T Technology > TH Building construction > TH2247 Shear walls--Materials
T Technology > TH Building construction > TH437 Building--Cost control.
T Technology > TH Building construction > TH438 Construction industry--Management. Project management.
Divisions: Faculty of Vocational > Civil Infrastructure Engineering (D4)
Depositing User: Firstama Panduwinata Iftiawan
Date Deposited: 01 Feb 2025 06:06
Last Modified: 01 Feb 2025 06:06
URI: http://repository.its.ac.id/id/eprint/117406

Actions (login required)

View Item View Item