Pemilihan Vendor Komponen Electrical untuk Mendukung Proyek Bangunan Lepas Pantai Menggunakan Metode Fuzzy SWOT-DEA

Azhari, M. Iqbal Putra (2025) Pemilihan Vendor Komponen Electrical untuk Mendukung Proyek Bangunan Lepas Pantai Menggunakan Metode Fuzzy SWOT-DEA. Masters thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 6032231047-Master_Thesis.pdf] Text
6032231047-Master_Thesis.pdf - Accepted Version
Restricted to Repository staff only

Download (23MB) | Request a copy

Abstract

Analisis vendor komponen electrical pada sebuah proyek EPC (Engineering, Procurement, Construction) bangunan lepas pantai merupakan salah satu tahapan yang dilalui pada tahap Detailed Engineering Design. Pada tahap pengadaan, tim engineering melakukan evaluasi vendor yang diminta tim procurement dalam melakukan penyeleksian vendor untuk proses pengadaan komponen yang akan digunakan oleh tim construction pada saat konstruksi.
Pemilihan vendor merupakan salah satu keputusan penting karena keputusan ini akan berdampak pada penyelesaian proyek baik dari aspek kualitas maupun pemenuhan jadwal. Berbagai kriteria digunakan dalam memilih vendor komponen electrical yang disesuaikan dengan kebutuhan dari sebuah proyek agar dapat diselesaikan sesuai dengan yang dipersyaratkan proyek.
Analisis pemilihan vendor komponen electrical dilakukan menggunakan metode pengambilan keputusan multi-kriteria dengan menggabungkan metode fuzzy SWOT dan DEA sebagai solusi yang efisien dan akurat dalam memilih vendor komponen electrical terbaik dengan mempertimbangkan aspek kualitatif dan kuantitatif berdasarkan kriteria yang telah ditentukan.
Analisis ini dilakukan pada 15 vendor electrical cable yang mengirimkan tawarannya pada proyek X di perusahaan EPC bangunan lepas pantai di Jakarta. Fuzzy SWOT digunakan untuk mengidentifikasi dan mengevaluasi vendor berdasarkan kriteria pemilihan, sedangkan DEA digunakan untuk mengukur efisiensi relatif dari setiap vendor setelah disaring pada analisis fuzzy SWOT.
Dari hasil penelitian, diperoleh bahwa vendor komponen electrical terbaik untuk direkomendasikan dan dipilih adalah dua vendor yang efisien yaitu vendor PT. STD dan PT. KBL dengan skor efisiensi 1.
Pendekatan pengambilan keputusan multi-kriteria melalui analisis fuzzy SWOT dan DEA untuk melakukan pemilihan vendor komponen electrical terbaik ini dapat digunakan oleh perusahaan untuk memberikan rekomendasi dan menentukan vendor secara objektif sehingga proses pengadaan dapat dilakukan secara efisien dan sesuai dengan kebutuhan proyek, sekaligus meminimalkan potensi keterlambatan proyek dan ketidaksesuaian kualitas pada fase konstruksi.
==========================================================================================================================================
Analysis of electrical component vendors in an EPC (Engineering, Procurement, Construction) offshore structure project is one of the stages that is passed in the Detailed Engineering Design stage. At the procurement stage, the engineering team evaluates the vendors requested by the procurement team in selecting vendors for the procurement process of components that will be used by the construction team during construction.
The selection of a vendor is one of the important decisions because this decision will have an impact on the completion of the project both in terms of quality and schedule compliance. Various criteria are used in choosing an electrical component vendor that is tailored to the needs of a project so that it can be completed according to the requirements of the project.
The analysis of the selection of electrical component vendors was carried out using a multi-criteria decision-making method by combining fuzzy SWOT and DEA methods as an efficient and accurate solution in selecting the best electrical component vendor by considering qualitative and quantitative aspects based on predetermined criteria.
This analysis was conducted on 15 electrical cable vendors who submitted their bids for project X at an offshore structure EPC company in Jakarta. Fuzzy SWOT is used to identify and evaluate vendors based on selection criteria, while DEA is used to measure the relative efficiency of each vendor after being screened on a fuzzy SWOT analysis.
From the results of the research, it was obtained that the best electrical component vendors to be recommended and selected are two efficient vendors, namely the vendor PT. STD and PT. KBL with an efficiency score of 1.
This multi-criteria decision-making approach through fuzzy SWOT and DEA analysis to select the best electrical component vendors can be used by companies to provide recommendations and determine vendors objectively so that the procurement process can be carried out efficiently and in accordance with project needs, while minimizing potential project delays and quality mismatches in the construction phase.

Item Type: Thesis (Masters)
Uncontrolled Keywords: Pemilihan Vendor, Komponen Electrical, Proyek Bangunan Lepas Pantai, MCDM, Fuzzy SWOT, DEA, Vendor Selection, Electrical Component, Offshore Project, MCDM, Fuzzy SWOT, DEA.
Subjects: T Technology > T Technology (General) > T56.8 Project Management
T Technology > T Technology (General) > T58.62 Decision support systems
T Technology > TC Hydraulic engineering. Ocean engineering > TC1665 Offshore structures--Materials.
Divisions: Interdisciplinary School of Management and Technology (SIMT) > 61101-Master of Technology Management (MMT)
Depositing User: M Iqbal Putra Azhari
Date Deposited: 02 Jul 2025 06:34
Last Modified: 02 Jul 2025 06:34
URI: http://repository.its.ac.id/id/eprint/119329