Khafiyah, Firliana Adi Nur (2017) Penyusunan Program Pemeliharaan Jalan Arteri Surabaya – Mojokerto Km 15,97 – 26,06 Ruas Krian-Taman (By Pass Krian Taman). Diploma thesis, Institut Teknologi Sepuluh Nopember.
Preview |
Text
3113041065-Undergraduate_Theses.pdf - Published Version Download (100MB) | Preview |
Abstract
Tujuan pemeliharaan jalan adalah untuk mempertahankan kondisi jalan mantap sesuai dengan tingkat pelayanan dan kemampuannya pada saat jalan tersebut selesai dibangun dan dioperasikan sampai dengan tercapainya umur rencana yang telah ditentukan. Bertitik tolak dari kondisi mantap tersebut, pemeliharaan jalan perlu dilakukan secara terus-menerus/rutin dan berkesinambungan khususnya pada jenis konstruksi jalan yang menggunakan sistem perkerasan lentur (flexible pavement). Pemeliharaan jalan tidak hanya pada perkerasannya saja, namun mencakup pula pemeliharaan bangunan pelengkap jalan dan fasilitas beserta sarana-sarana pendukungnya. Penyusunan program pemeliharaan jalan arteri Surabaya-Mojokerto KM 15,97 – 26,06 Ruas Krian-Taman (by pass Krian-Taman) dibuat untuk mengetahui kondisi kerusakan jalan yang terjadi dan penyusunan kebutuhan sumber daya serta penjadwalan sumber daya yang akan dibutuhkan dalam pelaksanaan pemeliharaan jalan.
Metode yang digunakan adalah penelitian lapangan dengan data primer berupa kondisi kerusakan jalan dan prasarananya beserta ukuran kerusakannya, yang mengacu kepada Manual Konstruksi dan Bangunan Untuk Pemeliharaan Rutin yang dikeluarkan oleh Bina Marga tahun 2011. Selain data primer juga terdapat data sekunder berupa data patok. Dari kedua data tersebut dapat ditentukan jenis pemeliharaan jalan, kebutuhan sumber daya serta penjadwalan sumber daya pada pelaksanaannya.
Melalui metode tersebut, didapatkan jenis-jenis kerusakan yang terdapat di lapangan beserta metode perbaikannya. Dari metode perbaikan yang mengacu pada aturan Bina Marga, maka dapat diketahui kebutuhan peralatan dan tenaga. Lama waktu pekerjaan pemeliharaan yang didapatkan adalah 46 hari kalender dengan biaya total perbaikan rencana adalah Rp1,437,452,945.52.
===============================================================================================
The purpose of road maintenance is to maintain steady road conditions in accordance with the level of service and ability when the road is completed and operated until the designated life of the plan. Starting from the steady condition, road maintenance needs to be done continuously / regularly and continuously, especially on the type of road construction using flexible pavement system (flexible pavement). Maintenance of roads not only on the pavement alone, but also includes the maintenance of complementary buildings and facilities along with supporting facilities. Maintenance program arrangement of Surabaya-Mojokerto arterial road km 15,97 – 26,06 Krian-Taman passes (by pass Krian-Taman) is made to know the condition of road damage and the preparation of resource requirement and resource scheduling that will be needed in road maintenance implementation.
The method used is field research with primary data in the form of the condition of road damage and its infrastructure along with the size of the damage, which refers to the Construction and Building Manual for Routine Maintenance issued by Bina Marga in 2011. In addition to primary data there are also secondary data in the form of data stakes. From these two data can be determined the type of road maintenance, resource requirements and resource scheduling on the implementation.
With these methods, obtained the types of damage that existed in the field and methods of improvement. From the method of improvement that refers to the rules of Highways, it can be seen the needs of equipment and energy. The length of time the maintenance work obtained is 36 calendar days with total cost of repair plan is Rp1,437,452,945.52.
Item Type: | Thesis (Diploma) |
---|---|
Uncontrolled Keywords: | Road maintenance, road damage, project schedule |
Subjects: | T Technology > TA Engineering (General). Civil engineering (General) T Technology > TE Highway engineering. Roads and pavements > TE7 Transportation--Planning |
Divisions: | Faculty of Vocational |
Depositing User: | Firliana Adi Nur Khafiyah |
Date Deposited: | 02 Oct 2017 04:05 |
Last Modified: | 08 Mar 2019 06:16 |
URI: | http://repository.its.ac.id/id/eprint/44680 |