Perencanaan Biaya dan Penjadwalan Pada Pembangunan Apartemen Taman Sari Mahogany Karawang (Tower A)

Saputra, Kurniadi (2018) Perencanaan Biaya dan Penjadwalan Pada Pembangunan Apartemen Taman Sari Mahogany Karawang (Tower A). Undergraduate thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 10111516000036-Undergraduate_Theses.pdf] Text
10111516000036-Undergraduate_Theses.pdf - Published Version
Restricted to Repository staff only

Download (9MB) | Request a copy

Abstract

Perencanaan dilakukan pada Pembangunan Apartemen Taman Sari Mahogany yang berlokasi di Karawang dengan luas bangunan ± 1324,60 m². Proyek akhir ini akan dibahas tentang perencanaan metode pelaksanaan yang sesuai dengan urutan teknis pelaksanaan guna menghasilkan jadwal dan biaya pelaksanaan yang terkontrol penggunaan sumber daya peralatan dan tenaga.
Perencanaan penjadwalan pelaksanaan menggunakan sumber referensi dari Ir. A. Soedradjat S, Analisa (cara modern). Biaya pelaksanaan ditentukan berdasarkan ketentuan format perhitungan AHSP (Analisa Harga Satuan Pekerjaan Bidang Umum Pekerjaan Umum dan Perumahan Rakyat).
Perhitungan produktivitas tenaga kerja dan produktivitas alat berat menggunakan data analisa dari sumber-sumber referensi tersebut. Adapun volume pekerjaan dihitung berdasarkan gambar pelaksanaan yang ada, sehingga dapat diketahui sumber daya yang diperlukan serta waktu pelaksanaan setiap aktivitas pekerjaan. Untuk perhitungan biaya dengan menjumlah biaya upah tenaga, sewa peralatan dan biaya material yang diperlukan.
Perencanaan penjadwalan pelaksanaan proyek menggunakan aplikasi Microsoft Office Project 2013. Data yang di input pada Microsoft Office Project 2013 adalah durasi, sumber daya, dan ketentuan ketergantungan antar aktivitas pada pelaksanaan proyek. Kontrol yang diperlukan adalah kontrol resource graph, kontrol total biaya dan kontrol network diagram. Kontrol resource graph untuk menghilangkan atau meminimalisasi idle penggunaaan sumber daya alat, kontrol total biaya per satuan pekerjaan harus sama dengan harga satuan pekerjaan dengan perhitungan AHSP (Analisa Harga Satuan Pekerjaan Bidang Umum Pekerjaan Umum dan Perumahan Rakyat), kontrol network diagram agar seluruh ketentuan teknis dan urutan pekerjaan sesuai dengan persyaratan teknis pekerjaan yang ditinjau.
Dari perencanaan biaya dan penjadwalan yang telah disusun didapatkan hasil berupa durasi pelaksanaan selama 506 kerja kalender dan total biaya pelaksanaan sebesar Rp. 40.186.214.870,00.
============ Planning is done on the development of Taman Sari Mahogany Apartments located in Karawang with building area ± 1324.60 m². This final project will be discussed about the planning of implementation methods in accordance with the technical sequence of implementation in order to produce a schedule and cost implementation of controlled use of equipment and energy resources
Planning of implementation scheduling using reference source from Ir. A. Soedradjat S, Analysis (modern way). The cost of implementation is determined based on the provisions of the AHSP calculation format (Analisa Harga Satuan Pekerjaan Bidang Umum Pekerjaan Umum dan Perumahan Rakyat).
Calculation of the productivity of labor and productivity of heavy equipment using the data analysis from the reference sources. As for the volume of work is calculated based on the existing implementation of theimage, so that it can be known the resources required and the time of execution of each activity of the work. For the calculation of the costs with the cost of labor, wages make a lease of equipment and material costs required.
Planning scheduling project implementation using Microsoft Office applications Project is 2013. The input data on a Microsoft Office Project 2013 is duration, resources,and conditions of dependency between activities on the implementation of the project. The required controls are resource graph control, total cost control and network diagram control. Resource graph control to eliminate or minimize idle of device resource usage, total cost control per work unit must be equal to unit cost of work with AHSP calculation (Analisa Harga Satuan Pekerjaan Bidang Umum Pekerjaan Umum dan Perumahan Rakyat), network diagram control for all technical requirements and work sequence in accordance with the technical requirements of the reviewed work.
From planning fees and scheduling the results obtained has been compiled in the form of the duration of the implementation during calendar working day is 506 days and total cost of implementation is Rp. 40.186.214.870,00.

Item Type: Thesis (Undergraduate)
Uncontrolled Keywords: Biaya; Waktu; Penjadwalan; Metode Konstruksi; Microsoft Project; cost; time; scheduling; methods of construction; Microsoft Project
Subjects: H Social Sciences > HD Industries. Land use. Labor > HD1391 Apartment houses
T Technology > TH Building construction
T Technology > TH Building construction > TH438 Construction industry--Management. Project management.
Divisions: Faculty of Vocational > Civil Infrastructure Engineering (D3)
Depositing User: Kurniadi Saputra
Date Deposited: 12 Feb 2018 08:44
Last Modified: 12 Feb 2018 08:44
URI: http://repository.its.ac.id/id/eprint/51230

Actions (login required)

View Item View Item