Metode Pelaksanaan Bangunan Pelimpah Samping (Spillway) pada Proyek Pembangunan Waduk Bendo Ponorogo

Nugroho, Fakhri Adha and Asmarayuda, Alfangga Desmontha (2018) Metode Pelaksanaan Bangunan Pelimpah Samping (Spillway) pada Proyek Pembangunan Waduk Bendo Ponorogo. Diploma thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 10111500000112_10111500000116-Non_Degree.pdf]
Preview
Text
10111500000112_10111500000116-Non_Degree.pdf - Accepted Version

Download (15MB) | Preview

Abstract

Kabupaten Ponorogo terletak di Provinsi Jawa Timur, dengan ketinggian antara 92 sampai dengan 2.563 meter diatas permukaan laut, dan memiliki luas wilayah 1.371,78 km2. Meningkatnya perekonomian di Kabupaten Ponorogo mengakibat terpicunya pembangunan infrastruktur, salah satunya adalah pembangunan Waduk Bendo yang berfungsi untuk mengembangkan daerah Ponorogo yang berkaitan dengan pengembangan sumber daya air, guna memenuhi berbagai keperluan masyarakat seperti penyediaan air irigasi, air baku domestik dan industri serta pengendalian banjir.
Owner dari proyek Waduk Bendo Ponorogo ini adalah Kementrian PU Dirjen SDA BBWS Bengawan Solo. Pihak kontraktor dalam kegiatannya hanya mengandalkan gambar teknis dari owner dan dokumen metode pelaksanaan.
Pekerjaan pelimpah samping (spillway) terdiri atas beberapa pekerjaan pemetaan, pekerjaan pembersihan dan pengupasan, pekerjaan galian tanah, pekerjaan shotcrete, pekerjaan pemboran dan grouting, pekerjaan beton, dan pekerjaan urugan kembali. Total ada 7 item pekerjaan yang kami bahas pada proyek pembangunan bangunan pelimpah samping (spillway) Waduk Bendo, Ponorogo.
Pekerjaan spillway membutuhkan beberapa alat berat yang berfungsi sebagai penunjang pekerjaan dilapangan antara lain gps geodetic, total station, bulldozer, excavator, dumptruck, hydraulic breaker jack hammer, air compressor, concrete mixer, shotcrete machine, water tank truck, drilling machine, grouting pump, grouting mixer, batching plant, truck mixer, concrete pump, concrete vibrator dan membutuhkan waktu selama 895 hari atau 2 tahun 2 bulan.
==============================================================================================================
Ponorogo Regency is located in the
East Java
P
rovince, with
an altitude of 92 to 2,563 meters above sea
level, and has an area
of
1,371.78 km2. The increasing of economy in Ponorogo regency
is caused by the development of infrastructure, one of which is the
development of Bendo Reservoir that serves to develop the
Ponorogo area related to the development o
f water resources, to
meet various needs of the community such as the provision of
irrigation water, domestic and industrial water and the
environment.
The owner of the Bendo Ponorogo Dam project is the
Ministry of Public Works of the Director General of
Natural
Resources BBWS Bengawan Solo. Contractors in their activities
rely solely on the technical drawings of owners and documents.
The spillway consists several parts of construction works,
there are: Mapping (survey), Land clearing and Grubbing,
Excava
tion Works, Shotcreting, Drilling and Grouting, Concrete
Works, Back Pile Works. There are
7
item works on construction
method of spillway that we discuss.
The spillway construction needs several hevy equipment
likes gps geodetic, total station, bulldozer
, excavator, dumptruck,
hydraulic breaker jack hammer, air compressor, concrete mixer,
shotcrete machine, water tank truck, drilling machine, grouting
pump, grouting mixer, batching plant, truck mixer, concrete pump,
concrete vibrator and takes work time o
ver
895
days or
2
year past
2
month.

Item Type: Thesis (Diploma)
Additional Information: RSIS 627.883 Nug m-1 3100018077855
Uncontrolled Keywords: Construction method, Heavy equipment, Durations (job time), Metode pelaksanaan, produktifitas alat berat, durasi
Subjects: T Technology > TC Hydraulic engineering. Ocean engineering
T Technology > TC Hydraulic engineering. Ocean engineering > TC555 Spillways. Energy dissipation. Hydraulic jump.
Divisions: Faculty of Vocational > Civil Infrastructure Engineering (D3)
Depositing User: Alfangga Desmontha Asmarayuda
Date Deposited: 18 Dec 2018 09:27
Last Modified: 08 Oct 2020 06:48
URI: http://repository.its.ac.id/id/eprint/53113

Actions (login required)

View Item View Item