Abstract

Sebuah kawasan superblok tentu mempunyai kompleksitas yang tinggi, baik dalam proses pembangunan maupun nantinya ketika sudah beroperasional, sehingga diperlukan desain yang tepat di awal. Pada proyek Ciputra World phase 3 terutama pada sistem kelistrikan (PLN kombinasi dengan genset), diperlukan pemilihan desain yang tepat. Dalam penentuan desain yang akan digunakan ada beberapa pertimbangan, sehingga keputusan yang diambil adalah alternatif yang mempunyai nilai tertinggi dan bisa diterima oleh semua stakeholder. Beberapa pertimbangan dalam penentuan desain pada proyek ini adalah initial cost, life cycle cost, recovery sistem ketika lampu mati, tahan terhadap gangguan dari luar,mudah dalam perawatan, harga per kwh yang kompetitif, ketersedian sumber bahan bakar, penghematan energi selama operasional gedung.
Berdasarkan latar belakang di atas, metodologi yang digunakan dalam menentukan pemilihan desain terbaik untuk sistem kelistrikan di proyek Ciputra World phase 3 adalah value based, dimana fungsi dan biaya dari masing-masing alternatif akan dibandingkan. Untuk fungsi akan dianalisa menggunakan FAST dan biaya akan dihitung berdasarkan LCC masing - masing alternatif. Untuk proses AHP data yang digunakan adalah hasil kuesioner dengan para responden yang berasal dari manajemen Ciputra World Surabaya. Dengan latar belakang dan pengalaman yang berbeda beda pada setiap responden, maka untuk mendapatkan keputusan berbasis kelompok dilakukan agregasi dari semua responden.
Dari hasil penelitian, responden 1 dan 2 memilih alternatif 1 (1 PLN – Diesel Engine) sebagai desain terbaik, sedangkan responden 3 memilih alternatif 3 (2 PLN – Gas Engine) sebagai desain terbaik, sedangkan dengan agregasi didapatkan alternatif 1 sebagai desain terbaik dengan nilai 2,92.
============================================================
A superblock area has a high complexity, both in the development process and later when it is operational, so it required the right design at the beginning. At project Ciputra World phase 3, especially on the electrical system (PLN combination with generator), required the selection of appropriate design. In determining the design which will be used there are several considerations, so the decision will be made is an alternative that has the highest value and be acceptable to all stakeholders. The considerations in determining the design of this project are the initial cost, life cycle cost, recovery system when PLN shutdown, resistant to interference from outside, easy in maintenance, Competative price per kwh, availability of fuel sources, energy saving during building operations.
Based on the background above, the methodology to be used in determining the selection of the best design for the electrical system in Ciputra World phase 3 is a value based, where the function and costs of each alternative will be compared. The Function will be analyzed using FAST and The Cost will be calculated based on LCC each alternative. For AHP process data used are the result questionnaires with respondents coming from management Ciputra World Surabaya. With the background and experience that is different for each respondent, to get a decision based on group used aggregation system of value from all respondents.
The results of research shows stakeholder 1 and 2 choose alternative 1 (1 PLN – Diesel) as the best design while stakeholder 3 choose alternative 3 (2 PLN – Gas Engine) as the best design. Based on Agregation the result shows alternative 1 be the best design for electrical system at Ciputra world phase 3 with value 2,92.

Item Type: Thesis (Masters)
Uncontrolled Keywords: Value Based Decision, Analisa Fungsi, Biaya, AHP
Subjects: T Technology > TJ Mechanical engineering and machinery > TJ164 Power plants--Design and construction
Divisions: Faculty of Business and Management Technology > Management Technology > 61101-(S2) Master Thesis
Depositing User: Nasychun Amin
Date Deposited: 23 Jun 2021 08:33
Last Modified: 23 Jun 2021 08:33
URI: http://repository.its.ac.id/id/eprint/55006

Actions (login required)

View Item View Item