Perhitungan Rencana Anggaran Biaya, Waktu, dan Metode Pelaksanaan untuk Struktur Beton pada Pembangunan Gedung Tamansari Mahogany Condotel Karawang

Purnamastuti, Brigitta Riska (2018) Perhitungan Rencana Anggaran Biaya, Waktu, dan Metode Pelaksanaan untuk Struktur Beton pada Pembangunan Gedung Tamansari Mahogany Condotel Karawang. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 10111715000044-Undergraduate_Theses.pdf]
Preview
Text
10111715000044-Undergraduate_Theses.pdf - Accepted Version

Download (14MB) | Preview

Abstract

Gedung Tamansari Mahogany Condotel Karawang beralamat di Jalan Arteri Karawang Barat, Dusun Badami, No. 8, RT. 04 RW. 02, Kelurahan Marga Kaya, Kecamatan Teluk Jambe, Karawang, Jawa Barat. Gedung ini memiliki 13 lantai ditambah dengan 2 lantai basement dan 2 lantai rooftop yang terbuat dari dek beton. Tinggi gedung ini 48,6 meter dan dibangun pada lahan dengan luas ±8.500 m2. Gedung ini merupakan proyek dari PT. Wijaya Karya Bangunan Gedung.
Gedung condotel ini digunakan sebagai objek tugas akhir untuk direncanakan biaya dan waktu pelaksanaannya. Tugas akhir ini menggunakan referensi dari Ir. A. Soedrajat S dengan judul Analisa (cara modern) Anggaran Biaya Pelaksanaan dan Peraturan Menteri Pekerjaan Umum Nomor 28/PRT/M/2016 tentang Analisis Harga Satuan Pekerjaan Bidang Pekerjaan Umum. Setiap pekerjaan yang sudah disusun metode pelaksanaannya akan dapat ditentukan durasi dan produktivitasnya. Perhitungan anggaran biaya pelaksanaan untuk pembangunan gedung ini terbagi menjadi harga dasar alat, bahan dan upah. Harga dasar tersebut menggunakan harga yang ada di lapangan dan harga dari buku Jurnal Harga Satuan Bahan
Bangunan, Kontruksi, dan Interior Edisi 36 tahun XXIII 2017. Untuk perhitungan waktu pelaksanaan dilakukan analisa mulai dari menentukan metode pelaksanaan yang sesuai. Lalu menghitung kapasitas alat yang digunakan, bahan, dan jumlah pekerja yang dibutuhkan. Nantinya akan diketahui durasi per item pekerjaan tersebut. Setelah durasi per item pekerjaan diketahui, dapat dilakukan penjadwalan per item pekerjaan dengan menggunakan bantuan software Microsoft Project.
Dari perencanaan yang telah disusun didapatkan waktu pelaksanaan proyek tersebut adalah 108 hari dimulai dari tanggal 9 Oktober 2017 hingga tanggal 15 Februari 2018. Hari pelaksanaan pekerjaan dimulai dari hari Senin hingga hari Sabtu dengan jam kerja selama 8 jam mulai pukul 08.00 hingga pukul 16.00. Dan didapatkan total biaya pelaksanaan sebesar Rp. 8.879.407.354.
=========================================================
Tamansari Mahogany Condotel Karawang building is located at Jalan Arteri Karawang Barat, Badami Village, No. 8, RT. 04 RW. 02, Kelurahan Marga Kaya, Teluk Jambe Sub-District, Karawang, West Java. The building has 13 floors plus 2 basement floors and 2 roof top floor made of concrete deck. The height of this building is 48.6 meters and is built on an area of ± 8,500 m2. This building is a project of PT. Wijaya Karya Gedung Bangunan.
This condotel building is used as the final task object for planned expenses and execution time. This final project uses references from Ir. A. Soedrajat S with the title of Analysis (modern way) Budget of Implementation Implementation and Regulation of Minister of Public Works No. 28 / PRT / M / 2016 on Analysis of Unit Price of Work of Public Works Sector. Each work that has been prepared the method of implementation will be determined duration and productivity. The calculation of the implementation cost budget for the construction of this building is divided into the basic price of tools, materials and wages. The
base price uses the existing price in the field and the price of Journal of Building Material, Construction, and Interior Price Unit Price XXIII 2017 Edition 36. For the calculation of the implementation time is done by analysis starting from determining the appropriate method of implementation. Then calculate the capacity of the tools used, materials, and the number of workers required. Later will be known duration per item of the work. After the duration per work item is known, scheduling can be performed per work item using Microsoft Project software help.
From the planning that has been arranged, the project implementation time is 108 days starting from October 9th 2017 util February 15th 2018. The work day starts from Monday to Saturday with 8 working hours from 08.00 to 16.00. And get the total cost of implementation of Rp. 8.879.407.354.

Item Type: Thesis (Undergraduate)
Uncontrolled Keywords: Anggaran Biaya Pelaksanaan, Waktu Pelaksanaan
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
T Technology > TH Building construction > TH437 Building--Cost control.
T Technology > TH Building construction > TH438 Construction industry--Management. Project management.
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22301-(D4) Diploma 4
Depositing User: Brigitta Riska Purnamastuti
Date Deposited: 25 Jun 2021 10:48
Last Modified: 25 Jun 2021 10:48
URI: http://repository.its.ac.id/id/eprint/55303

Actions (login required)

View Item View Item