Teknik Pelaksanaan dan Anggaran Biaya Proyek Tol Gempol Pasuruan Seksi A1; Gempol – Bangil Sta 0+000 – Sta 6+800 Dengan Menggunakan Perkerasan Kaku, Pasuruan

Rachmawati, Hasna and Septavianti, Dina (2015) Teknik Pelaksanaan dan Anggaran Biaya Proyek Tol Gempol Pasuruan Seksi A1; Gempol – Bangil Sta 0+000 – Sta 6+800 Dengan Menggunakan Perkerasan Kaku, Pasuruan. Diploma thesis, Institut Technology Sepuluh Nopember.

[thumbnail of 3112030054-3112030068-Non Degree.pdf]
Preview
Text
3112030054-3112030068-Non Degree.pdf - Published Version

Download (4MB) | Preview

Abstract

Proyek pembangunan Tol Gempol – Pasuruan
merupakan rangkaian jalan tol yang dibangun sepanjang
34,14 km yang menghubungkan antara kota Surabaya di
sebelah utara dengan Gempol di sebelah selatan.
Keberadaan jalan tol ini sangat penting dalam
kelancaraan arus lalu lintas. Adanya bencana lumpur
Lapindo menjadi salah satu faktor alasan perlunya
dibangun jalan tol. Seiring meningkatnya jumlah lalu
lintas yang diakibatkan bertambahnya jumlah kendaraan
dan kondisi geometrik yang sudah tidak seimbang.
Dalam pembangunan jalan Tol Gempol – Pasuruan
Seksi A1; Gempol – Bangil Sta 0+000- Sta 6+800 dengan
menggunakan perkerasan kaku diperlukan teknik
pelaksanaan dan penjadwalan kerja yang baik untuk
mengendalikan waktu pelaksanaan dan biaya yang
dibutuhkan. Berdasarkan perencanaan teknik
pelaksanaan dan penjadwalan kerja yang telah disusun,
didapatkan total biaya yang dibutuhkan untuk
pembangunan proyek ini sebesar Rp.235.691.408.811,00
selama 605 hari kalender.
============================================================================================================
Toll road construction project is a series of toll roads that
built along 34,14 km. this toll road is connecting between
north of Surabaya with south of Gempol. The existence
of this toll road is very important to make the road
smooth. Lapindo mud disaster is one of factors to built
this toll road. The increasing amount of urban traffic
happen because the increasing of vehicles amount and
geometric conditions is not balanced.
The construction of this toll road required the
implementation and scheduling techniques that work well
for controlling the time and cost estimate. Based on the
implementation of the technical planning and scheduling
of work that has been compiled obtained cost amount for
this project is Rp. Rp.235.691.408.811,00 selama 605
calendar days.

Item Type: Thesis (Diploma)
Additional Information: RSS 625.7 Rac t
Uncontrolled Keywords: jalan tol, teknik pelaksanaan, anggaran biaya, perkerasan kaku.
Subjects: T Technology > TE Highway engineering. Roads and pavements > TE175 Road and highway design
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22401-(D3) Diploma 3
Depositing User: Mr. Tondo Indra Nyata
Date Deposited: 20 Jun 2019 08:09
Last Modified: 20 Jun 2019 08:09
URI: http://repository.its.ac.id/id/eprint/63186

Actions (login required)

View Item View Item