Abstract

Tujuan dilaksanakannya Proyek Relokasi Jalan Tol Surabaya – Gempol Ruas Porong – Gempol STA 34+860 – STA 39+000 adalah untuk menggantikan fungsi ruas jalan tol Surabaya – Gempol yang terputus akibat luapan lumpur PT. Lapindo Brantas, terputusnya jalur transportasi tersebut menyebabkan terjadinya kemacetan terutama di pulau Jawa, yang melelahkan dan juga menurunkan produktivitas warga. Proyek idealnya diselesaikan dalam kurun waktu yang optimum dan biaya yang ekonomis (rendah) namun tetap menjaga kualitas. Pada setiap proyek konstruksi, agar proyek dapat berjalan dengan baik, maka harus terdapat manajemen perencanaan yang baik sejak awal. Salah satu cara yang dilakukan adalah dengan menghitung Estimasi Waktu dan Biaya, guna untuk menentukan penjadwalan dan juga durasi pekerjaan proyek, serta menentukan Rencana Anggaran Biaya yang dibutuhkan untuk pekerjaan proyek tersebut. Dalam perhitungan pekerjaan ini, kami selaku penulis sebelumnya menentukan metode pelaksanaan untuk tiap item perkejaan, menghitung volume pekerjaan, kemudian menghitung produktivitas alat berat, dari hasil perhitungan alat berat dan volume kami dapat menghitung durasi tiap item pekerjaan. Kemudian dengan perhitungan durasi, kami dapat menentukan biaya yang dibutuhkan tiap item pekerjaan untuk dihitung biaya keseluruhan kebutuhan proyek tersebut. Kemudian kami cek kembali dengan menggunakan kurva-s. Berdasarkan hasil perhitungan penulis, didapatkan durasi pekerjaan yaitu 457 hari dengan biaya yang dibutuhkan sebesar Rp 489.339.052.309.
Kata Kunci : Durasi, Rencana Anggaran Biaya
=============================================================================================================
The purpose of the Surabaya - Gempol Toll Road Relocation Project, Section Porong - Gempol STA 34 + 860 - STA 39 + 000 is to replace the function of the Surabaya - Gempol toll road that was cut off due to the mudflow PT. Lapindo Brantas, the interruption of the transportation route has caused traffic jams, especially on the island of Java, which is tiring and also decreases the productivity of residents. Projects should ideally be completed in an optimum timeframe and at an economical (low) cost while maintaining quality. In every construction project, for the project to run well, there must be good planning management from the start. One way to do this is to calculate the Time and Cost Estimation, in order to determine the scheduling and duration of the project work, as well as determine the Cost Budget Plan needed for the project work. In the calculation of this work, we as the previous authors determine the implementation method for each work item, calculate the volume of work, then calculate the productivity of heavy equipment, from the results of the calculation of heavy equipment and volume we can calculate the duration of each work item. Then by calculating the duration, we can determine the cost needed for each work item to calculate the overall cost of the project needs. Then we check again using the s-curve. Based on the author's calculation, the duration of work is 457 days with the required cost of Rp. 489,339.052.309. Key Words : Duration, Budget Plan.

Item Type: Thesis (Diploma)
Additional Information: RSIS 625.7 Aru e-1
Uncontrolled Keywords: Duration, Budget Plan
Subjects: T Technology > T Technology (General) > T56.8 Project Management
T Technology > T Technology (General) > T58.8 Productivity. Efficiency
T Technology > TA Engineering (General). Civil engineering (General) > TA492.G5 Girders
T Technology > TA Engineering (General). Civil engineering (General) > TA683 Precast concrete construction. Prestressed concrete construction.
T Technology > TA Engineering (General). Civil engineering (General) > TA780 Piles and pile-driving
T Technology > TE Highway engineering. Roads and pavements
T Technology > TE Highway engineering. Roads and pavements > TE7 Transportation--Planning
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22401-(D3) Diploma 3
Depositing User: Fahmi Rachmansyah Djumharjadi
Date Deposited: 25 Mar 2025 02:07
Last Modified: 25 Mar 2025 02:07
URI: http://repository.its.ac.id/id/eprint/74022

Actions (login required)

View Item View Item