Wicaksono, Irvianto Yudho (2016) Analisis Kinerja Pekerja pada Keterlambatan Proses Fabrikasi Pengerjaan Proyek COAL FIRED BOILER milik PT ALSTOM POWER ESI Surabaya. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.
Preview |
Text
4309100015-Undergraduate_Thesis.pdf - Accepted Version Download (2MB) | Preview |
Abstract
Suatu proyek cenderung akan mengalami keterlambatan apabila perencanaan dan pengendalian tidak dilakukan dengan tepat. Proses fabrikasi pengerjaan proyek Coal Fired Boiler milik PT ALSTOM ESI Surabaya mengalami berbagai hal yang dapat menyebabkan bertambahnya waktu pengerjaan sehingga penyelesaian proyek menjadi terlambat. Banyak faktor yang mempengaruhi diantaranya adalah peralatan produksi, material yang dibutuhkan, sumber daya manusia serta biaya. Menurut data PT ALSTOM 16.5% keterlambatan proyek disebabkan oleh kinerja pekerja. Tujuan utama dari penulisan tugas akhir ini adalah untuk menganalisis seberapa besar nilai kinerja pekerja terhadap pengaruh keterlambatan proyek. Setelah mengetahui seberapa besar nilai kinerja pekerja, maka selanjutnya akan menganalisis mengenai faktor-faktor apa saja yang mempengaruhi kinerja pekerja. Metode yang digunakan dalam tugas akhir ini adalah kombinasi dari SHELL MODEL dan RCA (Root Cause Analysis), sehingga dapat diketahui seberapa besar nilai kinerja pekerja dan apa saja penyebabnya serta cara penanganannya untuk proyek berikutnya.
=====================================================================================================
A project is prone to encounter delay if planning and controlling weren’t handled properly. Fabrication process of Coal Fired Boiler Project owned by PT ALSTOM ESI Surabaya experienced plenty of situations which caused increasing work time needed leading to delayed project completion. There are a lot of factor affecting them, such as production tools, materials needed, human resource, and cost. According to PT ALSTOM’s data 16.5% project delays were caused by worker performance. The main purpose of this final project is to analyze the amount of worker performance towards project delay. After finding out the amount of worker performance, then analyzing the factor affecting worker performance. The method employed for this final project is a combination between SHELL MODEL and RCA (Root Cause Analysis), leading to acknowledgement of the amount of worker performance, the causes, and the supervision for the further project.
Item Type: | Thesis (Undergraduate) |
---|---|
Additional Information: | RSKe 621.436 1 Wic a |
Uncontrolled Keywords: | Boiler, RCA, Kinerja, Faktor |
Subjects: | T Technology > TJ Mechanical engineering and machinery > TJ263.5 Boilers (general) |
Divisions: | Faculty of Marine Technology (MARTECH) > Ocean Engineering > 38201-(S1) Undergraduate Thesis |
Depositing User: | Yeni Anita Gonti |
Date Deposited: | 30 Apr 2020 04:14 |
Last Modified: | 30 Apr 2020 04:14 |
URI: | http://repository.its.ac.id/id/eprint/75912 |
Actions (login required)
View Item |