Analisis Perbandingan Waktu Dan Biaya Bekisting Metode Konvensional Dengan Metode Aluminium Formwork Pada Proyek Bess Mansion Surabaya

Ihsan, Raihan Ilyasa (2020) Analisis Perbandingan Waktu Dan Biaya Bekisting Metode Konvensional Dengan Metode Aluminium Formwork Pada Proyek Bess Mansion Surabaya. Other thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 03111640000127-Undergraduate_Thesis.pdf]
Preview
Text
03111640000127-Undergraduate_Thesis.pdf

Download (4MB) | Preview

Abstract

Peningkatan tuntutan konsumen terhadap kebutuhan properti tersedia sesuai waktu yang ditentukan proyek properti menjadi salah satu faktor yang menentukan dalam membangun kredibilitas sebuah perusahaan jasa konstruksi, terutama dalam proyek gedung bertingkat. Dalam proses pelaksanaan konstruksi gedung bertingkat, pekerjaan percetakan beton (bekisting) memerlukan biaya yang besar dalam pelaksanaannya, sehingga diperlukan penentuan metode yang memiliki nilai yang ekonomis dari segi biaya maupun waktu pelaksanaannya. Maka dari itu, pihak perusahaan jasa konstruksi harus melakukan berbagai hal terobosan teknologi dalam metode pelaksanaan konstruksinya.
Dalam pelaksanaan pekerjaan bekisting pada proyek pembangunan Apartemen Bess Mansion yang berlokasi di Kota Surabaya, Jawa Timur menggunakan metode bekisting konvensional yang merupakan bekisting berbahan dasar kayu. Sedangkan, saat ini pekerjaan bekisting berkembang dengan banyaknya metode yang mempengaruhi biaya dan waktu pelaksanaan pekerjaannya. salah satu nya yaitu metode aluminium formwork, yang merupakan material bekisting berbahan dasar aluminium dimana bahan material ini ramah lingkungan dan ekonomis. Oleh karena itu, diperlukan adanya penelitian tentang perbandingan dari segi waktu dan biaya dari kedua metode bekisting tersebut.
Penelitian ini membahas perbandingan pekerjaan bekisting metode konvensional dengan metode aluminium formwork agar perusahaan jasa konstruksi dapat memilih metode konstruksi yang akan digunakan dalam pembangunan gedung bertingkat yang lebih menguntungkan dari segi waktu maupun biaya.
Dari penelitian ini, didapatkan hasil pekerjaan bekisting untuk kolom, balok, pelat lantai dan tangga dengan menggunakan bekisting konvensional memerlukan biaya sebesar Rp. 10.593.794.954,14,- dan memerlukan waktu selama 478 hari sementara dengan menggunakan aluminium formwork memerlukan sebesar Rp 11.308.383.251,40,-. Dan memerlukan waktu selama 292 hari.
=========================================================================================================
Increasing consumer demand for available property according to the time determined by the property project is one of the determining factors in building the credibility of a construction service company, especially in building projects. In the process of implementing multi-story building construction, concrete printing work (formwork) requires a large cost in its implementation, so it is necessary to determine a method that has economic value in terms of cost and time of implementation. Therefore, the construction service company must do various technological breakthroughs in its construction implementation method.
In the implementation of formwork work on the Bess Mansion Apartment construction project located in the city of Surabaya, East Java using the conventional formwork method which is a formwork made from wood. Whereas, now the formwork work is developing with many methods that affect the cost and time of implementing the work. one of them is the aluminum formwork method, which is an aluminum formwork material which is environmentally friendly and economical. Therefore, research is needed on the comparison in terms of time and cost of the two formwork methods.
This research discussing comparison of conventional method formwork work with aluminum formwork methods so that construction service companies can choose the construction method that used in the construction of multi-storey buildings that are more profitable in terms of time and cost.
The results of this research are on the construction of Surabaya Bess Mansion Apartment, the formwork for columns, beams, floor plates and stairs using conventional formwork costs Rp. 10.593.794.954,14.- and takes 478 days while using aluminum formwork requires Rp 11.308.383.251,40-. And takes 292 days.

Item Type: Thesis (Other)
Uncontrolled Keywords: Formwork. Conventional Formwork, Aluminium Formwork, Time, Cost. Bekisting, Bekisting Konvensional, Aluminium Formwork, Waktu, Biaya.
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22201-(S1) Undergraduate Thesis
Depositing User: Raihan Ilyasa Ihsan
Date Deposited: 19 Aug 2020 07:03
Last Modified: 29 Aug 2023 14:47
URI: http://repository.its.ac.id/id/eprint/79241

Actions (login required)

View Item View Item