Pemilihan Proyek Pemeliharaan Peralatan Pembangkit Listrik Menggunakan Metode AHP dan Goal Programming

Setiyawan, Hery (2020) Pemilihan Proyek Pemeliharaan Peralatan Pembangkit Listrik Menggunakan Metode AHP dan Goal Programming. Masters thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 09211650015002-Master_Thesis.pdf]
Preview
Text
09211650015002-Master_Thesis.pdf

Download (4MB) | Preview

Abstract

PT XYZ Services adalah perusahaan penyedia jasa Operasi dan Pemeliharaan (O&M) pembangkit listrik di Indonesia meliputi pengelolaan, pengoperasian, dan pemeliharaan unit pembangkit. Salah satu Unit Jasa O&M adalah Unit Pembangkit Listrik Tenaga Uap (PLTU) XYZ dengan kapasitas 2 x 10 MW. Dalam kegiatan operasi dan pemeliharaan pembangkit listrik perlu dilakukan perencanaan dan pemeliharaan peralatan agar dapat berproduksi maksimal, andal, aman dan efisien sehingga dapat dicapai target kinerja unit.
Pemilihan proyek pemeliharaan peralatan yang tepat adalah kunci untuk mendukung kinerja pembangkit listrik, terutama untuk proyek yang bersifat improvement besar dan memerlukan biaya besar. Masalah perencanaan pemeliharaan adalah alokasi anggaran yang terbatas untuk mencapai tujuan dari berbagai kriteria dan tujuan pemeliharaan yang saling bertentangan. Penelitian ini menggunakan pendekatan kombinasi Analytical Hierarchy Process (AHP) dan Goal Programming (GP). Pada tahap pertama kriteria pemeliharaan yang bersifat kualitatif diukur menggunakan pendekatan AHP. Tahap kedua adalah menggunakan GP dengan memakai bobot kriteria dan alternatif yang didapat dari AHP untuk mengoptimasikan berbagai tujuan terhadap batasan yang ada.
Dari hasil AHP didapatkan bobot dan prioritas kriteria secara berurutan adalah Safety (0,539), Availability (0,221), Reliability (0,140), dan Efisiensi (0,100). Prioritas proyek pemeliharan dari AHP secara berurutan adalah proyek 1, proyek 3, proyek 2, proyek 4, dan proyek 5. Hasil kombinasi AHP- GP untuk optimasi pemilihan proyek terhadap batasan anggaran Rp. 20 Milyar didapatkan proyek yang optimal adalah proyek 1, proyek 3, proyek 4, dan proyek 5. Hasil penelitian ini dapat digunakan untuk menunjang manajemen perusahaan dalam pengambilan keputusan perencanaan dan pemilihan proyek pemeliharaan yang optimal.
=============================================================================
PT XYZ company is a provider of Operations and Maintenance (O&M) services for power plants in Indonesia including the management, operation, and maintenance of the power plant. One of the business unit is the XYZ Steam Power Plant (PLTU) with a capacity of 2 x 10 MW. In the operation and maintenance of power plants, it is necessary to plan and maintain equipment to be able to produce maximum, reliable, safe and efficient so that unit performance targets can be achieved.
The selection of proper equipment maintenance projects is the key to supporting the performance of power plants, especially for large projects for equipment improvement or replacement which require large costs. The problem of maintenance planning is the limited budget allocation to achieve the objectives of various conflicting criteria and maintenance objectives. This study uses a combination approach of Analytical Hierarchy Process (AHP) and Goal Programming (GP). In the first stage qualitative maintenance criteria are measured using the AHP approach. The second stage is to use GP by using the weighting of criteria and alternatives obtained from AHP to optimize various objectives against existing constraints.
From the AHP results obtained weights and priority criteria in sequence are Safety (0.539), Availability (0.221), Reliability (0.140), and Efficiency (0.100). The weight or priority of maintenance projects result from AHP in sequence are projects 1, project 3, project 2, project 4, and project 5. The results of the AHP-GP combination for optimization of project selection with a budget constraint Rp. 20 Billion obtained optimal projects are project 1, project 3, project 4, and project 5. The results of this study can be used to support organization management in making optimal planning and selection of maintenance projects.

Item Type: Thesis (Masters)
Uncontrolled Keywords: AHP, Goal Programming, Kinerja, Pemilihan Proyek, Pengambilan Keputusan, Performance, Project Selection, Decision Making
Subjects: T Technology > T Technology (General) > T58.62 Decision support systems
Divisions: 61101-Magister Management Technology
Depositing User: Hery Setiyawan
Date Deposited: 27 Aug 2020 03:18
Last Modified: 13 Dec 2023 11:04
URI: http://repository.its.ac.id/id/eprint/80497

Actions (login required)

View Item View Item