Krisbiantoro, Ratri Fahrur (2022) Perhitungan Waktu dan Biaya Pelaksanaan Proyek Pembangunan Gedung Pelayanan (Fisik) RSUD Tidar Kota Magelang Menggunakan Metode Half Slab. Other thesis, Institut Teknologi Sepuluh Nopember.
Text
2035201043-Undergraduate_Thesis.pdf - Accepted Version Restricted to Repository staff only until 1 April 2024. Download (16MB) | Request a copy |
Abstract
Pemilihan suatu metode pelaksanaan pekerjaan adalah tahapan yang sangat penting dalam suatu perencanaan proyek konstruksi. Metode pelaksanaan pekerjaan akan mempengaruhi kebutuhan waktu dan biaya yang diperlukan. Salah satu inovasi dan teknologi dalam proyek konstruksi adalah penggunaan precast half slab sebagai pengganti dari metode konvensional (cor in-situ), metode precast half slab pada pelaksanaan konstruksi pelat lantai bangunan memiliki kelebihan dibandingkan metode konvensional diantaranya pelaksanaan pekerjaan yang lebih cepat karena pekerjaan tidak terpengaruh cuaca dan tenaga kerja, kebutuhan sumber daya yang relatif lebih kecil sehingga berpengaruh terhadap kebutuhan biaya, serta kualitas atau hasil pekerjaan yang lebih baik.
Proyek pembangunan gedung pelayanan (fisik) RSUD Tidar Kota Magelang terdiri 1 basement dan 8 lantai ini dilaksanakan dengan menggunakan metode pengecoran secara konvensional. Elemen pelat lantai yang semula dikerjakan dengan metode konvensional (cor in-situ) akan dirubah menjadi metode precast half slab, metode precast half slab dipilih karena bangunan tersebut memiliki sifat typical serta repetisi pada pelat lantai bangunan, sehingga akan sesuai apabila diterapkan metode tersebut. Pada proyek akhir ini, akan dihitung waktu dan biaya pelaksanaan pekerjaan menggunakan metode precast half slab pada pelat lantai sebagai alternatif metode pelaksanaan yang dapat mempercepat waktu serta menghemat biaya pelaksanaan pekerjaan.
Perhitungan waktu dan biaya pelaksanaan proyek pembangunan gedung pelayanan (fisik) RSUD Tidar Kota Magelang ini dimulai dengan menyusun item pekerjaan, menghitung volume, menyusun metode pelaksanaan, menghitung kebutuhan sumberdaya, menghitung produktivitas, waktu dan durasi, menghitung Rencana Anggaran Pelaksanaan (RAP), menyusun penjadwalan proyek. Hasil akhir dari proyek akhir ini adalah metode pelaksanaan pekerjaan, rekapitulasi biaya pelaksanaan, durasi pekerjaan serta penjadwalan pekerjaan.
Dari perhitungan diperoleh hasil biaya pekerjaan menggunakan metode half slab senilai Rp29.997.030.000,- dengan waktu pelaksanaan selama 211 hari.
======================================================================================================
The selection of a work implementation is a very important stage in planning a construction project. the method of carrying out the work will affect the time and cost required. One of the innovations and technologies in construction projects is the use of half slabs as a substitute for the conventional method (cast in-situ), the precast half slab method in the construction of building floor slabs has advantages over other conventional methods, the execution of work is faster because the work is not affected by the weather. and labor, the need for relatively smaller resources so that it affects the need for costs, as well as better quality or work results.
The construction project of the service building (physical) of Tidar Hospital, Magelang City, consists of 1 basement and 8 floors which is carried out using conventional methods. The floor slab elements which were originally worked with the conventional method (cast in-situ) will be changed to the half slab precast method, the half slab precast method was chosen because the building has distinctive properties and repetitions on the building floor slab, so it will be appropriate if this method is applied. At the end of this, the time and cost of carrying out the work will be calculated using the precast half slab method, an alternative method of implementation that can speed up time and save on work execution costs.
building time and implementation costs for the implementation of the construction (physical) of Tidar Hospital, Magelang City, begins with compiling work items, calculating volume, compiling implementation methods, calculating resource requirements, calculating productivity, time and duration, calculating the Implementation Budget Plan (RAP), compiling project scheduling. The final result of this final project is the method of carrying out the work, recapitulation of implementation costs, duration of work and job scheduling.
From the calculation, it is obtained that the cost of work using the half slab method is Rp. 29.997.030.000,- with an implementation time of 211 days.
Item Type: | Thesis (Other) |
---|---|
Uncontrolled Keywords: | pelat pracetak, metode pelaksanaan, penjadwalan proyek, rencana anggaran pelaksanaan, precast half slab, implementation method, project scheduling, implementation budget plan. |
Subjects: | T Technology > TH Building construction > TH438 Construction industry--Management. Project management. |
Divisions: | Faculty of Vocational > Civil Infrastructure Engineering (D4) |
Depositing User: | Ratri Fahrur Krisbiantoro |
Date Deposited: | 14 Feb 2022 01:19 |
Last Modified: | 01 Nov 2022 00:52 |
URI: | http://repository.its.ac.id/id/eprint/93727 |