Dampak Modifikasi Bekisting Kolom Menggunakan Semi Sistem Terhadap Waktu Dan Biaya Pelaksanaan Proyek Pembangunan Gedung Kampus C Universitas Aisyiyah Yogyakarta

Najihan, Hanindya Fatihatun (2022) Dampak Modifikasi Bekisting Kolom Menggunakan Semi Sistem Terhadap Waktu Dan Biaya Pelaksanaan Proyek Pembangunan Gedung Kampus C Universitas Aisyiyah Yogyakarta. Other thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 2035201041-Undergraduate_Thesis.pdf] Text
2035201041-Undergraduate_Thesis.pdf - Accepted Version
Restricted to Repository staff only until 1 April 2024.

Download (16MB) | Request a copy

Abstract

Pekerjaan bekisting pada pelaksanaan proyek konstruksi menjadi salah satu aspek yang berpengaruh terhadap biaya dan waktu pelaksanaan proyek. Produktifitas dari pekerjaan bekisting akan mempengaruhi pekerjaan selanjutnya dan akan berpengaruh pada biaya dan waktu pelaksanaan proyek konstruksi. Oleh karenanya perlu dilakukan pemilihan jenis bekisting yang akan dipakai sesuai dengan proyek yang akan dibangun. Tujuan Proyek Akhir ini membandingkan waktu dan biaya pelaksanaan proyek yang ditinjau menggunakan bekisting konvensional dengan bekisting semi sistem pada struktur kolom.
Pertimbangan penggunaan bekisting semi sistem adalah material yang digunakan lebih awet dan tahan lama jika dibandingkan dengan penggunaan bekisting konvensional dan pemasangan yang relatif lebih mudah yang akan mempercepat durasi pemasangan. Selain itu pada proyek ini memiliki dimensi kolom yang tipikal sehingga bekisting semi sistem cocok digunakan pada pelaksanaan proyek pembangunan gedung Kampus C Universitas Aisyiyah Yogyakarta yang ditinjau pada Proyek Akhir ini.
Hasil yang didapatkan dalam perhitungan pelaksanaan pembangunan Gedung Kampus C Universitas Aisyiyah Yogyakarta menggunakan bekisting semi sistem pada kolom membutuhkan durasi 178 hari dan total biaya pelaksanaan sebesar Rp23.637.427.558. Sedangkan perhitungan pelaksanaan pembangunan menggunakan bekisting konvensional (secara keseluruhan) membutuhkan durasi 193 hari dan total biaya pelaksanaan sebesar Rp23.859.466.002. Selisih durasi pelaksanaan selama 15 hari, dan selisih biaya sebesar Rp222.038.444.- Maka penggunaan bekisting semi sistem berpengaruh lebih cepat dan lebih murah dibanding dengan penggunaan bekisting konvensional.
================================================================================================
Formwork work in the implementation of construction projects is one aspect that affects the cost and time of project implementation. The productivity of the formwork work will affect subsequent work and will affect the cost and time of construction project implementation. Therefore, it is necessary to select the type of formwork that will be used according to the project to be built. The purpose of this final project is to compare the time and cost of implementing the project under review using conventional formwork with semi-system formwork on a column structure.
The consideration of using semi-system formwork is that the material used is more durable and long-lasting when compared to the use of conventional formwork and relatively easy installation which will speed up the duration of installation. In addition, this project has typical column dimensions so that the semi-system formwork is suitable for use in the construction project of the Campus C building of Aisyiyah University Yogyakarta which is reviewed in this Final Project.
The results obtained in the calculation of the implementation of the construction of Campus C Building, Aisyiyah University Yogyakarta using semi-system formwork on the column requires a duration of 178 days and a total implementation cost of Rp.23,637,427,558. While the calculation of the implementation of the construction using conventional formwork (as a whole) requires a duration of 193 days and a total implementation cost of Rp.23,859,466.002. The difference in implementation duration is 15 days, and the cost difference is Rp.222,038,444.- So the use of semi-system formwork is faster and cheaper than the use of conventional formwork.

Item Type: Thesis (Other)
Uncontrolled Keywords: bekisting semi sistem, biaya pelaksanaan, kurva S, waktu pelaksanaan, semi system formwork, implementation cost, S curve, implementation time.
Subjects: T Technology > TH Building construction > TH438 Construction industry--Management. Project management.
Divisions: Faculty of Vocational > Civil Infrastructure Engineering (D4)
Depositing User: Hanindya Fatihatun Najihan
Date Deposited: 11 Feb 2022 08:56
Last Modified: 01 Nov 2022 03:34
URI: http://repository.its.ac.id/id/eprint/93729