Prastianto, Ditabasworo (2022) Manajemen Pelaksanaan Konstruksi Pada Bendungan Leuwikeris Desa Ancol Kecamatan Cineam Kabupaten Tasikmalaya. Other thesis, Institut Teknologi Sepuluh Nopember.
Text
10111510000091-Undergraduate_Thesis.pdf - Accepted Version Restricted to Repository staff only Download (26MB) | Request a copy |
Abstract
Untuk memenuhi kebutuhan air irigasi, pengendalian banjir, penyediaan air baku dan penyediaan energi listrik maka BBWS Citanduy memandang perlu untuk mengadakan Bendungan Leuwikeris. Suatu bendungan yang dibangun dengan cara menimbunkan bahan-bahan seperti: batu, krakal, kerikil, pasir dan tanah pada komposisi tertentu dengan fungsi sebagai pengempang atau pengangkat permukaan air yang terdapat didalam waduk di udiknya disebut bendungan tipe urugan atau "bendungan urugan".
Bendungan Leuwikeris termasuk kedalam bendungan urugan zona inti tegak dimana bahan timbunan teridir dari Zona 1 sebagai inti bendungan, Zona 2a sebagai filter halus, Zona 2b sebagai filter kasar, Zona 3 sebagai timbunan batu dan Zona 4 sebagai rip-rap. Pada laporan tugas akhir ini membahas menganai pelaksanaan konstruksi pada pembangunan bendungan leuwikeris.
Dalam penulisan laporan tugas akhir ini menggunakan metode pelaksanaan yang sesuai dengan kondisi lapangan sehingga data yang diperoleh dapat digunakan untuk menghitung volume pekerjaan, jumlah alat berat yang dibutuhkan, produktifitas alat kerja, rencana anggaran biaya, durasi pekerjaan dan mendapatkan Kurva S dengan bantuan Ms-Project.
Dari hasil analisa perhitungan tersebut diperoleh pelaksanaan pembangunan Bendungan Leuwikeris memakan waktu selama 678 hari kalender dengan total rencana anggaran sebesar Rp. 1.246.170.258.373,00 (Satu Triliyun Dua Ratus Empat Puluh Enam Miliyar Seratus Tujuh Puluh Juta Dua Ratus Lima Puluh Delapan Ribu Tiga Ratus Tujuh Puluh Tiga Rupiah).
=====================================================================================================
To meet the needs of irrigation water, flood control, raw water supply and electricity supply, BBWS Citanduy deems it necessary to construct the Leuwikeris Dam. A dam that is built by stockpiling materials such as: stones, gravel, sand and soil in a certain composition with a function as a containment or lifting of the water level contained in the reservoir in the village is called an embankment type dam or "fill dam".
The Leuwikeris dam is included in the embankment dam in the upright core zone where the embankment material consists of Zone 1 as the dam core, Zone 2a as a fine filter, Zone 2b as a coarse filter, Zone 3 as a rock pile and Zone 4 as a rip-rap. In this final project report discusses the implementation of construction on the construction of the Leuwikeris dam.
In this final project report using an implementation method that is in accordance with field conditions so that the data obtained can be used to calculate the volume of work, the number of heavy equipment needed, work equipment productivity, budget plan, work duration and get the S Curve by using Ms-Project.
From the analysis of these calculations, the implementation of the Leuwikeris Dam construction took 678 days with a total implementation cost of Rp. 1,246,170,258,373.00
Item Type: | Thesis (Other) |
---|---|
Uncontrolled Keywords: | Kurva s, produktifitas alat berat, rencana anggaran biaya, bendungan urugan, s curve, productivity, budget plan, eart fill dam |
Subjects: | T Technology > TC Hydraulic engineering. Ocean engineering > TC167 Dams, reservoirs T Technology > TH Building construction > TH437 Building--Cost control. T Technology > TH Building construction > TH438 Construction industry--Management. Project management. |
Divisions: | Faculty of Vocational > Civil Infrastructure Engineering (D4) |
Depositing User: | Ditabasworo prastianto |
Date Deposited: | 18 Feb 2022 05:21 |
Last Modified: | 01 Nov 2022 04:18 |
URI: | http://repository.its.ac.id/id/eprint/94612 |