PPIC adalah proses yang digunakan oleh perusahaan untuk merencanakan dan mengendalikan
produksi serta persediaan barang guna memastikan produk tersedia pada waktu yang tepat dan
dalam jumlah yang tepat. Pada penelitian ini didasarkan dari pengalaman penulis dalam
kegiatan magang yaitu pada CV. Ultra Engineering terdapat masalah dalam ketepatan waktu
proses produksi salah satu benda yaitu Pillow Support. Dalam penelitian ini untuk pengumpulan
data sebelum dan sesudah pengoptimalan menggunakan metode wawancara, yang dimana
penulis melakukan wawancara kepada operator – operator pada beberapa POS pembuatan
Pillow Support, penulis memilih metode tersebut dikarenakan terdapat kendala yang dimana
CV. Ultra Engineering pada saat penelitian dilakukan sedang banyak orderan dan juga sedang
tidak membuat benda Pillow Support sehingga penulis memilih untuk metode wawancara dan
penulis juga menggunakan beberapa metode lain dalam penulisan ini yaitu metode median
analisis dan Focus Grub Discussion (FGD). Dari hasil yang di dapat bawasannya
pengoptimalan waktu pembuatan Pillow Support dapat dioptimalkan dengan cara merubah alur
proses pembuatan sehingga waktu yang dapat dioptimalkan menjadi 152 menit yang
sebelumnya membutuhkan waktu 185 menit untuk satu benda dan juga penulis menemukan
faktor penyebab keterlambatan yaitu pada saat proses pengerjaan pada beberapa POS ada benda
masuk lain (benda urgent) yang ingin dilakukan pengerjaan pada beberapa POS sehingga benda
yang sedang dilakukan pengerjaan harus di hentikan sehingga terjadi hambatan dalam
pengerjaan benda Pillow Support.
========================================================================================================================
PPIC is a process used by companies to plan and control production and inventory to ensure
that products are available at the right time and in the right quantity. This research is based on
the author's experience during an internship at CV. Ultra Engineering, where there was an issue
with the timeliness of the production process for one item, the Pillow Support. In this study,
data collection before and after optimization was conducted using interviews, where the author
interviewed operators at various POS (points of sale) involved in the production of Pillow
Support. This method was chosen due to challenges faced by CV. Ultra Engineering during the
study, including high order volumes and the fact that Pillow Support production was not
ongoing at the time. Therefore, the author opted for interviews and also used other methods in
this study, such as median analysis and Focus Group Discussion (FGD). The results indicated
that the optimization of the Pillow Support production time could be achieved by modifying
the production flow, reducing the time from 185 minutes to 152 minutes per item. Additionally,
the author identified a key cause of delays: the introduction of urgent items into the production
process at several POS, which required halting the production of Pillow Support and created
bottlenecks.
Item Type: | Thesis (Other) |
---|---|
Uncontrolled Keywords: | PPIC, Production Plan, Optimasi |
Subjects: | A General Works > AI Indexes (General) A General Works > AI Indexes (General) A General Works > AS Academies and learned societies (General) A General Works > AS Academies and learned societies (General) T Technology > T Technology (General) > T56.8 Project Management T Technology > T Technology (General) > T58.8 Productivity. Efficiency T Technology > TS Manufactures > TS155 Production control. Production planning. Production management T Technology > TS Manufactures > TS176 Manufacturing engineering. Process engineering (Including manufacturing planning, production planning) |
Divisions: | Faculty of Vocational > Mechanical Industrial Engineering (D4) |
Depositing User: | Rexxy Rivaldo |
Date Deposited: | 03 Aug 2024 04:31 |
Last Modified: | 03 Aug 2024 04:31 |
URI: | http://repository.its.ac.id/id/eprint/112768 |
Actions (login required)
View Item |