Analisis Optimasi Penggunaan Alat Berat Dengan Programa Linier Pada Proyek Pematangan Lahan Kawasan Bank Indonesia

Feruzzi, Adya Muhammad (2022) Analisis Optimasi Penggunaan Alat Berat Dengan Programa Linier Pada Proyek Pematangan Lahan Kawasan Bank Indonesia. Other thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 03111840000137-Undregraduate_thesis.pdf] Text
03111840000137-Undregraduate_thesis.pdf
Restricted to Repository staff only

Download (3MB) | Request a copy

Abstract

Pekerjaan cut and fill merupakan salah satu pekerjaan proyek konstruksi yang membutuhkan bantuan alat berat, terutama jika volume tanah yang digali atau ditimbun relatif besar. Proyek Pematangan Lahan Kawasan Bank Indonesia yang terletak di Kabupaten Karawang akan melaksanakan pekerjaan cut and fill dengan volume yang relatif besar. Sehingga, proyek ini membutuhkan bantuan alat berat untuk menyelesaikan pekerjaan tersebut. Dengan banyaknya jumlah dan berbagai jenis alat berat yang dibutuhkan, perlu dilakukan analisis optimasi terhadap alat berat yang akan digunakan. Tugas Akhir ini dilakukan dengan tujuan merencanakan beberapa kombinasi alat berat yang layak digunakan dalam pekerjaan cut and fill yang sesuai dengan kondisi lapangan, serta menentukan kombinasi alat berat yang menghasilkan biaya minimum dengan memperhatikan target waktu dan volume pekerjaan. Analisis optimasi dilakukan dengan programa linier. Terlebih dahulu dilakukan perencanaan alat berat untuk kondisi lapangan yang ada. Alat berat yang digunakan adalah excavator, dump truck, dan bulldozer. Digunakan 2 (dua) tipe dari masing-masing alat berat untuk mendapatkan 6 alternatif kombinasi alat berat yang berbeda. Setelah itu dilakukan perhitungan produktivitas dan biaya pemakaian dari tiap alat berat. Analisis optimasi dilakukan dengan membuat permodelan matematis dari persoalan optimasi yang diinginkan, yaitu meminimumkan biaya pemakaian alat berat. Variabel keputusan pada persoalan ini adalah jumlah dari masing-masing kombinasi alat berat. Fungsi kendala adalah kendala waktu dan produksi dari alat berat. Dari hasil analisis didapatkan bahwa kombinasi I yang merupakan kombinasi dari 17 excavator PC300, 15 bulldozer D65P, dan 22 dump truck 20T Hino, merupakan solusi optimum untuk menyelesaikan pekerjaan cut and fill. Kombinasi I tersebut membutuhkan biaya alat berat per jam sebesar Rp.22.745.617,78.
======================================================================================================================================
Cut and fill work is one of the construction project jobs that requires heavy equipment assistance, especially if the volume of soil excavated or stockpiled is relatively large. The Bank Indonesia Regional Land Development Project, located in Karawang Regency, will carry out a relatively large volume of cut and fill work. Thus, this project requires the help of heavy equipment to complete the work. With the large number and various types of heavy equipment needed, it is necessary to carry out an optimization analysis of the heavy equipment to be used. This final project is carried out with the aim of planning several combinations of heavy equipment that are suitable for use in cut and fill work according to field conditions, as well as determining the combination of heavy equipment that produces minimum costs by taking into account the target time and volume of work. Optimization analysis is done by linear programming. First, heavy equipment planning is carried out for the existing field conditions. The heavy equipment used are excavators, dump trucks, and bulldozers. 2 (two) types of each heavy equipment are used to obtain 6 alternative combinations of different heavy equipment. After that, the calculation of productivity and usage costs of each heavy equipment is carried out. Optimization analysis is done by making a mathematical model of the desired optimization problem, which is to minimize the cost of using heavy equipment. The decision variable in this problem is the number of each combination of heavy equipment. The constraint functions are the time and production constraints of the machine. From the results of the analysis, it was found that combination I, which is a combination of 17 PC300 excavators, 15 D65P bulldozers, and 22 Hino 20T dump trucks, is the optimum solution to complete cut and fill work. The combination I requires an hourly heavy equipment cost of Rp.22,745,617,78.

Item Type: Thesis (Other)
Uncontrolled Keywords: Alat berat, Cut and Fill, Optimasi, Pematangan Lahan, Pemrograman Linier, Cut and Fill, Heavy Equipment, Land Grading, Linear Programming, Optimization
Subjects: H Social Sciences > HT Communities. Classes. Races > HT133 City and Towns. Land use,urban
Divisions: Faculty of Civil, Planning, and Geo Engineering (CIVPLAN) > Civil Engineering > 22201-(S1) Undergraduate Thesis
Depositing User: Mr. Marsudiyana -
Date Deposited: 14 Jan 2026 03:27
Last Modified: 14 Jan 2026 03:27
URI: http://repository.its.ac.id/id/eprint/129595

Actions (login required)

View Item View Item