Darmayanti, Juwita (2026) Rancangan Perbaikan Proses Bisnis dengan Menggunakan Metode Business Process Improvement pada Tim Kerja Layanan Infrastruktur Digital 2 (LID2). Masters thesis, Institut Teknologi Sepuluh Nopember.
|
Text
6032241102-Master_Thesis.pdf - Accepted Version Restricted to Repository staff only Download (9MB) | Request a copy |
Abstract
Tim Kerja Layanan Infrastruktur Digital 2 (LID2) menangani penerbitan Izin Stasiun Radio (ISR) Kapal Laut, tetapi waktu siklus prosesnya masih melebihi target. Rata-rata waktu verifikasi tercatat 15,45 menit (target ≤ 10 menit), technical analysis 8,10 menit (target ≤ 6 menit), dan validasi 7,20 menit (target ≤ 4 menit). Hasil analisis Fishbone Diagram menunjukkan tiga akar masalah, yaitu komposisi SDM yang tidak seimbang (1 verifikator, 2 technical analyst, 1 validator), pencatatan manual di Excel pribadi dan koordinasi lisan yang berulang, serta proses bisnis yang belum didokumentasikan dengan notasi baku. Penelitian ini menggunakan metode Business Process Improvement (BPI) Harrington melalui empat fase, yaitu Organizing for Improvement, Understanding the Process, Streamlining, serta Measurements and Controls. Proses bisnis dipetakan dengan Business Process Model and Notation (BPMN) menggunakan Microsoft Visio, lalu setiap aktivitas diklasifikasikan ke dalam Real Value Added (RVA), Business Value Added (BVA), dan Non Value Added (NVA). Waktu siklus diukur pada 55 berkas ISR, kemudian diuji kecukupan, keseragaman, normalitas, dan perbedaannya dengan uji berpasangan. Proses existing terdiri atas 64 aktivitas (46 RVA, 10 BVA, 8 NVA) dengan efisiensi waktu siklus 52,22%. Penerapan sepuluh dari dua belas streamlining tools menghapus 8 aktivitas NVA dan mengubah 10 aktivitas, sehingga proses usulan berisi 56 aktivitas. Berdasarkan pengukuran pada rancangan usulan, total waktu siklus turun dari 68,65 menjadi 39,62 menit (42,29%), dengan verifikasi 9,01 menit, technical analysis 5,10 menit, dan validasi 3,99 menit, sehingga ketiga target tercapai. Efisiensi waktu siklus naik menjadi 90,54% dan perbedaannya signifikan (Sig. < 0,001). Penelitian ini juga menghasilkan SOP baru yang dilengkapi backup role dan cross-training, KPI tiga dimensi, serta template lembar kerja digital. Evaluasi penerimaan oleh pelaksana teknis menghasilkan rata-rata skor 4,78 dari skala 5 (kategori sangat setuju), sehingga rancangan diterima. Pada penelitian ini, usulan dapat dijalankan dengan SDM dan sarana yang sudah ada dan komposisi tim saat ini mencukupi untuk volume bulan puncak melalui backup role yang dirancang dalam standard operating procedure (SOP).
=======================================================================================================================================
The Digital Infrastructure Service Work Team 2 (LID2) handles the issuance of Radio Station Licenses (ISR) for ships, but its cycle times still exceed the targets. Verification takes 15.45 minutes on average (target ≤ 10 minutes), technical analysis 8.10 minutes (target ≤ 6 minutes), and validation 7.20 minutes (target ≤ 4 minutes). A Fishbone Diagram analysis points to three root causes: an unbalanced staff composition (1 verifier, 2 technical analysts, 1 validator), manual record keeping in personal Excel files combined with repeated verbal coordination, and business processes that have not been documented with a standard notation. This study applies Harrington's Business Process Improvement (BPI) method through four phases: Organizing for Improvement, Understanding the Process, Streamlining, and Measurements and Controls. The processes are mapped in Business Process Model and Notation (BPMN) using Microsoft Visio, and each activity is classified as Real Value Added (RVA), Business Value Added (BVA), or Non Value Added (NVA). Cycle times were measured on 55 ISR files and tested for adequacy, uniformity, normality, and paired differences. The existing process consists of 64 activities (46 RVA, 10 BVA, 8 NVA) with a cycle time efficiency of 52.22%. Applying ten of the twelve streamlining tools removes all 8 NVA activities and modifies 10 others, leaving 56 activities in the proposed process. Based on measurements of the proposed design, total cycle time falls from 68.65 to 39.62 minutes (42.29%), with verification at 9.01 minutes, technical analysis at 5.10 minutes, and validation at 3.99 minutes, so all three targets are met. Cycle time efficiency rises to 90.54%, and the difference is significant (Sig. < 0.001). The study also delivers a new SOP with backup roles and cross-training, a three-dimensional KPI set, and a digital worksheet template. An acceptance evaluation by technical staff members gave an average score of 4.78 on a five-point scale (strongly agree), so the design was accepted. In this study, the proposal can be implemented using existing human resources and facilities, the current team composition is sufficient to handle peak-month volumes through backup roles defined within the standard operating procedure (SOP).
| Item Type: | Thesis (Masters) |
|---|---|
| Uncontrolled Keywords: | Business Process Improvement, Efisiensi Waktu Siklus, Layanan Infrastruktur Digital, Izin Stasiun Radio, Business Process Improvement, Cycle Time Efficiency, BPMN, Digital Infrastructure Services, Radio Station License |
| Subjects: | T Technology > T Technology (General) > T58.6 Management information systems |
| Divisions: | Interdisciplinary School of Management and Technology (SIMT) > 61101-Master of Technology Management (MMT) |
| Depositing User: | Juwita Darmayanti |
| Date Deposited: | 17 Nov 2026 06:45 |
| Last Modified: | 18 Nov 2026 06:33 |
| URI: | http://repository.its.ac.id/id/eprint/146067 |