Pada musim hujan di sebagian kota Surabaya terjadi genangan, khususnya di catchment saluran sekunder Petemon Sidomulyo. Tinggi genangan pada kawasan tersebut 20cm dengan lama genangan ±56 menit. Pada saat terjadi hujan dengan intensitas tinggi biasanya terjadi genangan pada bahu jalan dan bangunan di sekitarnya. Berdasarkan pada kondisi tersebut maka tugas akhir ini bertujuan untuk mengevaluasi kembali sistem drainase yang ada pada saluran yang terpengaruh, yaitu saluran Petemon Sidomulyo.
Dalam evaluasi sistem drainase saluran sekunder Petemon Sidomulyo ini dimulai dengan survey lokasi, pengumpulan data hujan, tata guna lahan, data genangan, dan data topografi. Data tersebut diperlukan untuk analisis yang meliputi perhitungan curah hujan rata-rata, perhitungan curah hujan rencana metode log person type III, perhitungan debit rencana metode rasional, perhitungan kapasitas eksisting dan pengaruh back water.
Setelah dilakukan perhitungan diketahiui Q kapasitas saluran primer 27,204 m3/detik serta Q kapasitas saluran sekunder 3,865 m3/detik, dan terjadi pengaruh back water sepanjang 879,3905m pada saluran sekunder, maka akan dibangun 1 pompa dengan kapasitas 1,5 m3/detik. Dalam mewujudkan catchment saluran sekunder Petemon Sidomulyo yang bebas banjir maka harus ada tindakan dan kerjasama yang baik antara masyarakat dan Pemerintah Kota Surabaya, karena dalam mengatasi masalah ini terdapat masalah banjir yang kompleks.
==================================================================================================================On the rainy season, most part of Surabaya was flooded especcially on catchment of Petemon sidomulyo secondary drainage. The flood is 20 cms high and the duration is 56 minutes. If the rain intensity is high, there will be puddles around the sideroads and the buildings. Based on those investigations, this final project aims to evaluate the drainage system of petemon sidomulyo.
The evaluate of petemon sidomulyo secondary drainage system begin with location surveying, rain data collecting, land use data, flood data, and topography data. These datas are used to analyze average rainfall calculation, plan rainfall calculation with log person type III method, plan debit calculation with rasional method, existing capacity calculation, and back water effect.
After the calculation, has known that Q capacity of primary drainage is 27,204 /sec, so the water will flooded and occurs the back water effect on 879,3905 ms long. So it will be installed a water pump with 1,5 /sec capacity so that the water does not overflow onto the sideroads and residental area. on realizing simo kwagean roads which free flooding, then there must be an action and good collaboration between the peoples and the City Goverment of Surabaya.

Item Type: Thesis (Diploma)
Uncontrolled Keywords: back water, genangan, drainase, pompa, petemon sidomulyo
Subjects: T Technology > TC Hydraulic engineering. Ocean engineering
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22401-(D3) Diploma 3
Depositing User: - APRILLIA WIJAYANTI NINGRUM
Date Deposited: 24 Mar 2017 03:27
Last Modified: 05 Mar 2019 01:59
URI: http://repository.its.ac.id/id/eprint/2213

Actions (login required)

View Item View Item