Analisa Perencanaan Proyek Kapal Cepat Rudal dengan Metode CPM dan What If Analysis

Firmansyah, Muhammad Reza (2017) Analisa Perencanaan Proyek Kapal Cepat Rudal dengan Metode CPM dan What If Analysis. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 4312100100 -Undergraduate-theses.pdf]
Preview
Text
4312100100 -Undergraduate-theses.pdf - Published Version

Download (1MB) | Preview

Abstract

Kinerja buruk yang menyebabkan keterlambatan waktu, rendahnya kualitas, dan pembengkakan biaya seringkali terjadi dalam suatu proyek. Penjadwalan mempunyai peranan yang penting untuk mengendalikan proyek tersebut. Penjadwalan yang baik dibutuhkan karena akan berpengaruh pada kinejra produk. Kegiatan penjadwalan direncanakan agar waktu penyelesaian proyek dapat sependek mungkin dengan tetap memperhitungkan biaya sehingga proyek berada dalam kondisi optimum.
Keterlambatan pada proyek dapat ditimbulkan dari penyedia jasa, pengguna jasa maupun pihak lain yang berdampak pada penambahan waktu dan biaya diluar rencana. Keterlambatan pelaksanaan proyek dapat memberi pengaruh yang cukup besar terhadap biaya. Tambahan pekerja ataupun biaya yang harus disediakan oleh penyedia jasa secara langsung maupun tidak lansung merupakan suatu keharusan untuk mengejar keterlambatan pelaksanaan proyek.
Dapat dilakukan perencanan proyek untuk mengetahui apakah proyek sudah berada dalam kondisi yang optimum. Alternatif yang dapat digunakan untuk mengatasi keterlambatan proyek adalah dengan menambah tenaga kerja dan waktu, selanjutnya yaitu mencari solusi optimum dengan memperhitungkan durasi dan pertambahan dari masing-masing alternatif.

=====================================================================================

The poor performance caused the delay time, poor quality, and cost overruns often occur in a project. Scheduling has an important role to control the project. Good scheduling required because it will affect the kinejra product. Scheduling activities are planned so that the project completion time can be as short as possible while taking into account the cost of that project are in optimum condition.
Project delay can be caused by service providers, service users and other parties that have an impact beyond the additional time and cost plans. Project delay caused a considerable influence on the costs. Additional costs that must be provided by the service provider directly or indirectly is a must to pursue project delay reputation of the company.
Project planning can be done to determine whether the project is already in an optimum condition. Alternatives that can be used to overcome the delay in the project is to increase labor and equipment, the next is to look for the optimum solution taking into account the duration and gain of each alternative.

Item Type: Thesis (Undergraduate)
Uncontrolled Keywords: CPM; What If Analysis; Keterlambatan Proyek; Project Delay
Subjects: T Technology > T Technology (General) > T56.8 Project Management
Divisions: Faculty of Marine Technology (MARTECH) > Ocean Engineering > 38201-(S1) Undergraduate Thesis
Depositing User: - MUHAMMAD REZA FIRMANSYAH
Date Deposited: 21 Mar 2017 02:18
Last Modified: 06 Mar 2019 02:34
URI: http://repository.its.ac.id/id/eprint/2367

Actions (login required)

View Item View Item