Pembangunan Box Culvert merupakan salah satu program
Pemerintah Kota Surabaya dan diharapkan juga bisa
memecahkan masalah banjir dan kemacetan. Didalam
pelaksanaan pembangunan proyek saluran air diperlukan adanya
standarisasi Box Culvert, baik dari segi desain maupun harga
yang disesuaikan dengan situasi dan kondisi wilayah Surabaya.
Standarisasi tersebut dimaksudkan untuk mempermudah bagi
perencana proyek mengoptimal hasil perencanaannya dan bagi
kontraktor akan mengefisienkan waktu pelaksanaan karena
desain dan harga sudah terstandarisasi. Akan tetapi sampai saat
ini Dinas PU Bina Marga dan Pematusan Pemerintah kota
Surabaya belum mempunyai standar desain dan harga dari
saluran precast, adapun PU Bina Marga menggunakan standar
desain dan harga dari konsultan perencana.
Pada tugas akhir ini dilakukan analisa deskriptif untuk
menentukan jenis dan tipe ukuran yang sering digunakan di
wilayah pemerintahan kota Surabaya. Selanjutnya dilakukan
analisa struktur dan perhitungan harga perkiraan sendiri dengan
menggunakan metode analisa harga satuan pekerjaan dari desain
dan ukuran yang sering digunakan di wilayah pemerintahan kota
Surabaya. Selain itu, di dalam tugas akhir ini ditentukan selisih
perhitungan antara HPS dengan harga penawaran dari beberapa
kontraktor, berdasarkan data historis tersebut akan diketahui
apakah HPS dapat dijadikan patokan untuk pengadaan saluran
precast.
Kesimpulan yang didapat dari penulisan ini adalah untuk
jenis saluran U-Ditch terdapat 15 dan Top-Bottom terdapat 3.
Rata-rata harga perkiraan sendiri lebih murah dibandingkan
dengan harga penawaran kontraktor. Perbandingan harga
perkiraan sendiri dengan harga rata-rata penawaran kontraktor
untuk cover dan u-gutter yaitu 3.4% - 54.23%. Rata-rata
perbandingan harga perkiraan sendiri dengan harga rata-rata
penawaran kontraktor untuk Top-Bottom yaitu -35.75%.

===============================================================================

Box Culvert development is one of government programs of
Surabaya City and the program is expected to be one of the
solutions to solve the problem of flooding and traffic jams. In the
Box Culvert implementation required the standardization of Box
Culvert, both in terms of design and price whole is adjusted to the
situation and condition areas of Surabaya. The standardization is
intended to make it easier for projecct planning to optimize the
planning results and for the contractor will streamline
implementation time schedule because the design and the price
has been standardization. But until now Public Works
Department of Office Highways and Drainage not have design
standards and the price of Box Culvert, as for Public Works
Department of Office Highways and Drainage using a standard
design and price of the consultant planner.
In this final project descriptive analysis to determine the type
and size that is often used in Government of Surabaya City.
Furthermorem the analysis of the structure and calculation of the
owner estimate by using the method of unit price analysis of
designs and sizes are frequently used in the Government of
Surabaya City. Moreover, in this final project is determined the
difference between the calculation of Owner Estimate with price
quotes from multiple contractors, based on that historical data
will be known whether the Owner Estimate can be used as a
benchmark for the procurement of Box Culvert.
The conclusion of this paper is for U-Ditch there are 15
sizes and Top-Bottom there are 3 sizes. The average price of own
estimates cheaper than the offering price of the contractor. The
ratio of the price of its own estimates with the average price for
the contractor offers for cover and u-gutter is 3.4% - 54.23%.
The average ratio of the price of its own estimates with the
average price for the contractor offers for Top-Bottom is -
35.75%.

Item Type: Thesis (Undergraduate)
Additional Information: RSS 627.54 Feb a
Uncontrolled Keywords: Standar Dimensi Saluran Precast; Harga Perkiraan Sendiri; Dinas PU Bina marga kota Surabaya; Standardization of Box Culvert; Owner Estimate; Public Works Department of Office Highways and Drainage
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
T Technology > TH Building construction > TH437 Building--Cost control.
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22201-(S1) Undergraduate Thesis
Depositing User: Anis Wulandari
Date Deposited: 14 Jun 2017 02:06
Last Modified: 26 Dec 2018 08:15
URI: http://repository.its.ac.id/id/eprint/41646

Actions (login required)