Penjadwalan Waktu Pelaksanaan Pekerjaan Dan Rencana Anggaran Biaya Pelaksanaan Proyek Transmart Carrefour Rungkut Surabaya

Karimah, Fadlilatul and Himawan, Muhammad Ladzuardi (2017) Penjadwalan Waktu Pelaksanaan Pekerjaan Dan Rencana Anggaran Biaya Pelaksanaan Proyek Transmart Carrefour Rungkut Surabaya. Diploma thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 3114030082-3114030116-NON_DEGREE.pdf]
Preview
Text
3114030082-3114030116-NON_DEGREE.pdf - Published Version

Download (31MB) | Preview

Abstract

Proyek pembangunan Transmart Carrefour Rungkut Surabaya dengan luas bangunan ± 5487,2 m2 memerlukan penjadwalan pelaksanaan yang di tinjau dari perhitungan waktu dan biaya pelaksanaan. Perhitungan waktu dan biaya pelaksanaan menggunakan sumber referensi buku dan pengalaman kontraktor karena dalam perhitungan RAB pelaksana biaya yang dibutuhkan harus real. Maka tugas akhir ini membahas mengenai penjadwalan pelaksanaan di tinjau dari segi biaya dan waktu.
Analisa yang dilakukan pada perhitungan waktu dan biaya pelaksanaan ini meliputi gambar desain bangunan, perhitungan volume tiap pekerjaan, sumber daya seperti pekerja, material dan alat berat yang digunakan, produktifitas pekerjaan. Setelah analisa sudah didapatkan maka dapat menghitung waktu pelaksanaan dan biaya pelaksanaan yang diperlukan.
Dengan menggunakan metode AOA pada proyek Transmart Carrefour Rungkut Surabaya dapat dioptimalisasikan. Sehingga dalam analisa perhitungannya mengadopsi dari analisa harga satuan dan metode pelaksanaan yang ada. Data tersebut di kelola kembali dengan metode AOA sehingga menghasilkan waktu dan biaya optimal. Hasil yang diperoleh berdasarkan analisa perhitungan didapatkan waktu pelaksanaan selama 7 bulan 25 hari atau 235 hari. Biaya pelaksanaan dibutuhkan sebesar Rp 47.949.581.235,84.
==============================================================================================
Transmart Carrefour Rungkut Surabaya development project with a building area of ± 5487.2 m2 requires scheduling implementation in review of the calculation of time and cost of implementation. The calculation of time and cost of implementation using the reference book source and contractor experience because in the calculation of RAB implementing the required cost must be real. So this final project discusses the scheduling of implementation in review in terms of cost and time.
Analyzes performed on time calculations and implementation costs include building design drawings, work volume calculations, resources such as workers, materials and heavy equipment used, work productivity. After the analysis has been obtained then it can calculate the execution time and implementation cost required.
By using AOA method in Transmart Carrefour Rungkut Surabaya project can be optimized. So in the analysis of the calculation adopted from the analysis of unit price and existing execution methods. The data is rearranged with the AOA method resulting in optimal time and cost. The results obtained based on the calculation analysis obtained the implementation time for 7 months 25 days or 235 days. The implementation fee is Rp 47,949,581,235.84.

Item Type: Thesis (Diploma)
Uncontrolled Keywords: Scheduling Implementation, time and cost implemention.
Subjects: T Technology > TH Building construction > TH437 Building--Cost control.
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22401-(D3) Diploma 3
Depositing User: Muhammad Ladzuardi Himawan
Date Deposited: 17 Nov 2017 03:43
Last Modified: 06 Mar 2019 03:04
URI: http://repository.its.ac.id/id/eprint/43617

Actions (login required)

View Item View Item