Malamassam, Leonart (2016) Analisa Produktivitas Pekerja Dengan Metode Time Study Pada Proyek Pembangunan Gedung Teknik Industri ITS. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.
Preview |
Text
3109100089-Undergraduate-Theses.pdf - Published Version Download (2MB) | Preview |
Abstract
Produktivitas pekerja menentukan keberhasilan
pelaksanaan jadwal proyek konstruksi, karena berdampak kepada
kesesuaian antara perencanaan jadwal konstruksi dengan
progres pekerjaan di lapangan. Oleh karena itu, pekerjaan
struktur beton bertulang yang merupakan salah satu aktivitas
kritis dalam perencanaan jadwal sebuah proyek perlu dianalisa
produktivitas pekerjanya.
Tugas akhir ini bertujuan untuk menganalisa
produktivitas pekerja pada pekerjaan struktur beton bertulang
dan mencari faktor apa saja yang dapat mempengaruhi
produktivitas pekerja pada proyek pembangunan Gedung Teknik
Industri ITS. Perhitungan produktivitas dilakukan dengan metode
Time Study. Metode time study adalah metode pengukuran
produktivitas tenaga kerja di lapangan dengan cara menentukan
standard time suatu pekerjaan. Standard time diperoleh dari
pengamatan. Pada pengamatan akan diukur nilai basic time yang
akan diolah menjadi standard time, dan digunakan untuk
menghitung nilai produktivitas.
Dari hasil perhitungan diperoleh nilai produktivitas
pekerja pada pekerjaan pemasangan bekisting kolom, bekisting
balok, dan bekisting pelat berturut-turut adalah 7.07 m2/OH,
28.32 m2/OH, dan 35.81 m2/OH. Untuk nilai produktivitas
pekerja pada pekerjaan pemasangan tulangan kolom, tulangan
balok, dan tulangan pelat berturut-turut adalah 228.86 kg/OH,
397.55 kg/OH, dan 28.73 kg/OH. Sedangkan nilai produktivitas
pada pekerjaan pengecoran kolom, pengecoran balok, dan
pengecoran pelat berturut-turut adalah 78.14 m3/OH, 43.02
m3/OH, dan 16.42 m3/OH. Dari hasil analisa produktivitas
menunjukkan bahwa letak antara material dan tempat
pengerjaan, jumlah pekerja, relaxation allowances, material yang
digunakan, dan penggunaan alat dalam pekerjaan adalah faktorfaktor
yang mempengaruhi produktivitas pekerja pada pekerjaan
struktur beton bertulang.
==========================================================================
Labour productivity determine the success of project
schedule realization, because its impact on conformity between
project schedule and the progress in the site of construction.
Therefore, the labour productivity of reinforced concrete
structures works as one of the critical activity on project
schedule, need to be analyzed.
This final project aims to analyze labour productivity of
reinforced concrete structures works and to find the factors that
can affect the productivity of labour in the ITS Industrial
Engineering Building project. The productivity is calculated by
using time study method. Time study is a measuring method to
calculate productivty of labour in the site of construction by
observe and determine the standard time of a work. Standard time
is obtained form observation. On the observation, we will obtain
the value of basic time, and then it will be processed to standard
time that used for calculate the productivity.
Based on result of calculation, the productivity value of a
labour for each installation of column formwork, beam formwork,
and slab formwork respectively are 7.07 m2/OH, 28.32 m2/OH,
and 35.81 m2/OH. productivity value of a labour for each
installation of column reinforcement, beam reinforcement, and
slab reinforcement respectively are 228.86 kg/OH, 397.55 kg/OH,
and 28.73 kg/OH. And the productivity value of a labour for
column casting, beam casting, and slab casting respectively
are78.14 m3/OH, 43.02 m3/OH, and 16.42 m3/OH. While the
result of productivity analysis shows that location between
materials and workplace, the number of labours, relaxation
allowances, materials used, and utilization of tools are the factors
that can affect the labour productivity on reinforced concrete
structures works.
Item Type: | Thesis (Undergraduate) |
---|---|
Additional Information: | RSS 331.118 Mal a |
Uncontrolled Keywords: | Produktivitas, Standard Time, Basic Time, Faktor yang mempengaruhi produktivitas, Productivity, Factors That Affect Productivity. |
Subjects: | T Technology > TA Engineering (General). Civil engineering (General) |
Divisions: | Faculty of Civil Engineering and Planning > Civil Engineering > 22201-(S1) Undergraduate Thesis |
Depositing User: | Anis Wulandari |
Date Deposited: | 21 Aug 2017 05:05 |
Last Modified: | 21 Aug 2017 05:05 |
URI: | http://repository.its.ac.id/id/eprint/48681 |
Actions (login required)
View Item |