Kondisi topografi di Pulau Kei Kecil, Kabupaten Maluku Tenggara yang berbukit-bukit menyebabkan sering terjadinya fluktuasi muka air di sungai sehingga saat musim hujan terjadi banjir dan saat musim kemarau mengalami kekeringan. Hal ini dapat mengganggu aktivitas manusia dalam hal pemenuhan kebutuhan air baku atau pertanian, dimana salah satu sumber air yaitu dari sungai (Misdanik, 2017). Maka dari itu, pemerintah Kabupaten Maluku Tenggara merencanakan untuk membuat embung di empat lokasi di Pulau Kei Kecil, salah satunya yaitu di Desa Ohoinol. Bagian yang akan dibahas pada tugas akhir ini yaitu Bendung-tanah
Bendung yang direncanakan adalah bendung tipe urugan atau bendung-tanah. Perencanaan bendung-tanah dan penyelidikan kondisi tanah sudah dilakukan oleh perencana dan didapatkan kondisi tanah pada BH-2 yaitu tanah lunak lempung sampai kedalaman 15 m dari permukaan dengan nilai SPT<10. Elevasi bendung tertinggi yaitu sebesar 11 meter dengan elevasi muka air banjir mencapai 7 meter. Serta lokasi Pulau Kei Kecil memiliki potensi gempa yang cukup besar yaitu PGA sebesar 0.392g.
Dalam Tugas Akhir ini akan dievaluasi terkait stabilitas bendung-tanah dari aspek geoteknik dengan mempertimbangkan adanya zona gempa sekaligus perencanaan perkuatan jika perencanaan eksisting bendung Ohoinol ini tidak stabil. Berdasarkan perhitungan pada zona tengah dengan data tanah BH-2, dibutuhkan waktu 17 tahun untuk selesai konsolidasi sebesar 90% sehingga direncanakan percepatan menggunakan Prefabricated Vertical Drain (PVD) dengan jarak 1.25 meter pola segiempat. Direncanakan agar bisa mencapai konsolidasi sebesar 90% dalam waktu 25 minggu. Dari hasil analisa konsolidasi pada zona tengah mengalami konsolidasi sebesar 1.39 meter, zona timur dan zona barat mengalami konsolidasi segera sebesar 0.02 meter – 0.04 meter. Evaluasi perencanaan awal tubuh bendung menggunakan bantuan program Plaxis 8.6. Skema evaluasi dibagi empat kondisi yaitu kondisi kosong, kondisi muka air normal, kondisi muka air banjir, dan kondisi rapid drawdown dengan pengaruh gempa dan tanpa pengaruh gempa.
Analisa stabilitas bendung tanah dengan dibagi per potongan tubuh bendung A-G. Analisa perencanaan eksisting didapatkan hasil SF yang kurang dari kriteria pada potongan C, D, E sehingga direncanakan beberapa perkuatan tanah berupa, penggunaan geotextile, micropile beton dan kombinasi geotextile dan micropile beton. Dari ketiga jenis perkuatan tersebut, dipilih perkuatan yang paling ekonomis menurut biaya materialnya saja yaitu micropile. ==========================================================================================================
Topographic condition on the Kei Kecil Island, Southeast Maluku district is hilly, causing frequent fluctuation of water level in the river when during rainy season there is flooding and during the dry season drought. This can affect with human activities in terms of the needs of water or agriculture, where one of the source of water is from the river (Misdanik, 2017). Therefore, the government of Southeast Maluku is planning to create retention basin at four locations in Kei Kecil Island, one of which is in Ohoinol Village. The part that will be discussed in this final project is Earthfill-Dam.
The Planned Dam is Earthfill type Dam. Earthfill-dam planning and soil investigation have been done by the planner and found on BH-2 soil type is soft clay with a depth of 15 meter from surface with SPT value < 10. The highest elevation of the dam is 11 meters with flood water level reaches 7 meters. And the location of Kei Kecil Island has the potential of a large earthquake with PGA of 0.392g.
In this Final Project will be evaluated related to earthfill-dam stability from the geotechnical aspect by considering the seismic zone as well as the reinforcement plan if the existing dam planning of the Ohoinol dam are unstable. Based on calculations in the middle zone with BH-2 soil data, it takes 17 year to complete the consolidation by 90% so then planned acceleration using Prefabricated Vertical Drain (PVD) with a distance of 1.25 meter and rectangular pattern. Planned to achieve consolidation of 90% within 25 weeks. From the consolidation analysis in the middle zone, the consolidation is 1.39 meters, where the eastern and western zone the consolidation is immediate with the value of 0.02 meters – 0.04 meters. Evaluation of the existing plan of the dam using Plaxis 8.6 program. The evaluation scheme is divided into four conditions, empty condition, normal water level condition, flood water level condition, and rapid drawdown condition with earthquake and without earthquake effect.
Earthfill-dam stability analysis of this final project based on the cross section of the dam from A-G. Existing plan analysis obtained results of SF less than the criteria on the cross section C, D, E, therefore planned the reinforcement such as, the use of geotextile, micropile, or combination of geotextile and micropile. From the three types of reinforcement, chosen micropile for its economycal aspect
Item Type: | Thesis (Undergraduate) |
---|---|
Additional Information: | RSS 627.8 Mau p-1 3100018074466 |
Uncontrolled Keywords: | Earthfill-Dam; Ohoinol; PVD; Immediate Settlement; Dam Body; Micropile; Geotextile; Plaxis |
Subjects: | T Technology > TA Engineering (General). Civil engineering (General) > TA347 Finite Element Method T Technology > TA Engineering (General). Civil engineering (General) > TA749 Soil stabilization T Technology > TC Hydraulic engineering. Ocean engineering > TC167 Dams, reservoirs |
Divisions: | Faculty of Civil Engineering and Planning > Civil Engineering > 22201-(S1) Undergraduate Thesis |
Depositing User: | Dica Rasyid Maulidhani |
Date Deposited: | 20 Mar 2018 05:00 |
Last Modified: | 25 Sep 2020 04:18 |
URI: | http://repository.its.ac.id/id/eprint/50453 |
Actions (login required)
View Item |