Ahmadi, Khoirul and Abdurrohman, Syukri (2018) Metode Pelaksanaan Pembangunan Bangunan Pelimpah (Spillway) Pada Bendungan Gondang, Kabupaten Karanganyar, Jawa Tengah. Diploma thesis, Institut Teknologi Sepuluh Nopember.
Preview |
Text
10111500000039-10111500000117-Non_Degree.pdf - Accepted Version Download (13MB) | Preview |
Abstract
Bendungan Gondang merupakan sebuah proyek yang dikelola oleh Kementerian Pekerjaan Umum dan Perumahan Rakyat Balai Besar Wilayah Sungai (BBWS) Bengawan Solo yang terletak pada wilayah Desa Gondang, Kecamatan Kerjo, Kabupaten Karanganyar, Provinsi Jawa Tengah. Bendungan Gondang direncanakan memenuhi kebutuhan air irigasi, kebutuhan air baku, dan mengatasi masalah banjir pada wilayah Kabupaten Karanganyar dan Kabupaten Sragen. Bendungan Gondang direncanakan dengan debit banjir rencana periode ulang 1000 tahun dengan data hujan harian selama 10 tahun serta luas DAS Karanganyar sebesar 20,19 km².
Spillway adalah bangunan yang digunakan untuk mengalirkan debit banjir agar tidak melimpas pada tubuh bendungan. Pada spillway Bendungan Gondang ini memiliki jenis bangunan pelimpah type samping atau type side spillway. Sehingga tugas akhir ini akan direncanakan metode pelaksanaan dan konstruksi proyek pembangunan side spillway lengkap dengan bangunan pelengkapnya yaitu: saluran pengarah, saluran transisi, saluran peluncur dan bangunan peredam energi pada Bendungan Gondang Karanganyar.
Dalam proses pembangunan side spillway perlu dikaji terlebih dahulu metode yang digunakan dalam pembangunan side spillway agar penerapan di lapangan sesuai dengan perencanaan. Sehingga perlu dibuat sebuah dokumen metode pelaksanaan side spillway pada Bendungan Gondang Karanganyar.
Data yang dibutuhkan dalam pelaksanaan pembangunan spillway ini meliputi beberapa tahap-tahap pekerjaan antara lain: Pekerjaan persiapan, pekerjaan surveying/ pemetaan, pekerjaan tanah, pekerjaan treatment/ grouting, dan pekerjaan pembetonan. Dari dokumen penulisan metode pelaksanaan ini diharapkan dapat membantu dalam pembangunan Spillway pada Bendungan Gondang Karanganyar.
Sehingga dalam tahapa akhir penulisan Tugas Akhir ini menentukan langkah-langkah metode pelaksanaan yang logis dan tepat berdasrakan analisa teoritis dan analisa perhitungan kebutuhan alat berat.
============================================================
Gondang Dam is a project run by the Ministry of Public Works and the Housing of the River Territory (BBWS) of Bengawan Solo located in Gondang Village, Kerjo Subdistrict, Karanganyar Regency, Central Java Province. Gondang dam is planned to meet the needs of irrigation water, raw water needs, and overcoming the problem of flooding in the area of Karanganyar Regency and Sragen Regency. Gondang dam is planned with a flood discharge plan 1000 year return period with daily rainfall data for 10 years and Karanganyar DAS area of 20.19 km².
Spillway is a building that is used to drain the flood discharge so as not to ran off on the dam body. In spillway Gondang Dam has a type of building type side splinters or type side spillway. So this final project will be planned implementation and construction method of side spillway development project complete with its complementary building that is: steering channel, transition channel, launcher channel and building of energy reducer at Gondang Karanganyar Dam.
In the process of building the side spillway needs to be studied in advance the methods used in the construction of side spillway for the application in the field in accordance with the planning. So that need to be made a document method of implementation of side spillway on Gondang Karanganyar Dam.
The data required in this spillway development involves several stages of work: Preparatory work, surveying/ mapping work, soil work, treatment / grouting work, and a concreting work. From the writing document this method of implementation is expected to assist in the construction of Spillway on Gondang Dam Karanganyar.
So in the final step of writing this Final Project determines the steps of logical and precise implementation methods based on theoretical analysis and calculation analysis of equipment needs.
Item Type: | Thesis (Diploma) |
---|---|
Uncontrolled Keywords: | Implementation Method, Side Spillway, Development. |
Subjects: | T Technology > TA Engineering (General). Civil engineering (General) T Technology > TC Hydraulic engineering. Ocean engineering T Technology > TC Hydraulic engineering. Ocean engineering > TC555 Spillways. Energy dissipation. Hydraulic jump. |
Divisions: | Faculty of Vocational > Civil Infrastructure Engineering (D3) |
Depositing User: | Syukri Abdurrohman |
Date Deposited: | 01 Jul 2021 07:02 |
Last Modified: | 01 Jul 2021 07:02 |
URI: | http://repository.its.ac.id/id/eprint/56882 |
Actions (login required)
View Item |