Perencanaan embung Tambak Pocok Kabupaten Bangkalan

Salam, Abdus (2015) Perencanaan embung Tambak Pocok Kabupaten Bangkalan. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 3110100083-Presentation.pdf]
Preview
Text
3110100083-Presentation.pdf - Presentation

Download (589kB) | Preview
[thumbnail of 3110100083-Paper.pdf]
Preview
Text
3110100083-Paper.pdf - Published Version

Download (1MB) | Preview
[thumbnail of 3110100083-Undergraduate_Theses.pdf]
Preview
Text
3110100083-Undergraduate_Theses.pdf - Published Version

Download (7MB) | Preview

Abstract

Desa Tambak Pocok Kecamatan Tanjung Bumi
Kabupaten Bangkalan adalah salah satu desa atau daerah yang
kebutuhan air bakunya belum terpenuhi. Pada saat musim
kemarau desa ini mengalami kesulitan air, sumber mata air
utama penduduk yaitu sumur, sungai dan sumber mata air
lainnya mengalami kekeringan. Padahal mayoritas penduduk
di desa tersebut menggunakan air sumur untuk memenuhi
kebutuhan sehari-hari. Sedangkan dilihat dari kondisi daerah
desa Tambak Pocok merupakan daerah yang terdiri dari
cekungan dan dataran berbukit, sehingga sangat cocok untuk
digunakan sebagai tempat untuk menampung air. Dengan
memanfaatkan kondisi topografi yang ada di desa tersebut,
maka Embung adalah salah satu alternatif solusi untuk
menampung air saat hujan turun dan memanfaatkan air
tersebut saat musim kemarau. Dengan adanya embung
tersebut, maka air hujan yang terbuang pada saat musim hujan
dapat di tampung, di simpan dan di manfaatkan pada saat
musim kemarau untuk memenuhi kebutuhan air sehari-hari
masyarakat di desa tersebut, antara lain untuk air minum,
mandi, cuci, dan kakus.
Perhitungan yang dipakai dalam perencanaan embung
Tambak Pocok yaitu meliputi perhitungan curah hujan rencana
dengan menggunakan metode Log normal, Pearson Tipe III,
dan Log Pearson Tipe III, analisa debit tersedia menggunakan
v
metode FJ Mock, debit rencana menggunakan metode
hidrograf Nakayasu, analisa kebutuhan air menggunakan
metode analisa geometri, analisa tampungan menggunakan
lengkung kapasitas waduk dan mass curve, sedangkan untuk
penelusuran banjir menggunakan metode tahap demi tahap
(step by step ), analisa tubuh embung dan kestabilannya, serta
analisa spillway dan kestabilannya.
Dari perhitungan yang telah dilakukan diperoleh curah
hujan rencana periode ulang 25 tahun sebesar 82.561 mm,
debit rencana periode ulang 25 tahun sebesar13.613, debit
andalan sebesar 0.000001153 m3/detik, proyeksi jumlah
penduduk pada tahun 2038 sebesar 14511 jiwa, dan kebutuhan
air total yang dibutuhkan adalah sebesar 0.022 m3/detik.
Mercu bangunan pelimpah (spillway) menggunakan mercu
tipe Ogee tipe I pada elevasi +72.50 dan elevasi banjir yang
terjadi pada elevasi +73.15. Tubuh bendungan menggunakan
urugan tanah dengan kemiringan hulu dan hilir adalah sebesar
1:2, elevasi puncak bendung terletak pada elevasi +75.00,
dasar bendungan terletak pada elevasi +64.00, tinggi jagaan
pada tubuh bendungan dipakai sebesar 2.5 meter, dan panjang
tubuh bendungan sebesar 66 m. Perhitungan stabilitas tubuh
bendungan dan spillway aman terhadap gaya-gaya yang terjadi
baik dalam kondisi muka air banjir maupun dalam kondisi
muka air normal dengan Sf = 1.7 > 1.5 (Sf minimum). ========== Tambak Pocok District of Tanjung Bumi Bangkalan
is one of the village that needs of supplay water insatiable. At
the dry season the village is experiencing water shortages, the
main water source population wells, rivers and other water
sources having dryness.whereas majority village population
using well water to meet their daily needs on a day. Beside
that from the rural areas Tambak Pocok is an area consisting
of the basin and hilly terrain, so it is suitable for use as a place
to store the water. By utilizing the existing topography in the
village, then Embung is one alternative solution to store water
when it rains and the water use during the dry season. The
presence of Reservoir, the rain water is wasted during the
rainy season can be accommodated, stored and utilized during
the dry season to meet the daily water needs of the people in
the village, such as for drinking water, bathing, washing, and
toilet.
The calculations used in the planning of the reservoir
Tambak Pocok among as rainfall calculation using the log
normal, Pearson Type III, and Log Pearson Type III, available
discharge analysis of method FJ Mock, discharge plans using
hydrograph Nakayasu methods, water demand analysis using
the geometry analysis method, reservoir analysis using
vii
reservoir capacity and mass curve, whereas for search flood
routing of step by step method, and stability analysis of dam
and spillway.
From the calculations is rainfall return period of 25
years for 82.561 mm, discharge plans return period of 25
years at 13.613m3/s, discharge is the mainstay of
0.000001153 m3/second, the projected total population in
2038 amounted to 14.511 people, and the total water
requirement needed is 0.022 m3/s. Spillway using Ogee type I
at elevation +72.50 and flood elevation of + 73.15.The Dam
using soil embankment with upstream and downstream slope
is equal to 1: 2, the top of dam elevation of +75.00, The Dam
base is located an elevation of +64.00, free high the dam is
used by 2.5 meters, and length of body the dam is 66 meters.
The calculation of Dam stability and spillway Stability of
safe for the forces for flood water level and the normal water
level conditions with Sf = 1.7 > 1.5 ( Sf Minimum).

Item Type: Thesis (Undergraduate)
Additional Information: RSS 627.86 Sal p
Uncontrolled Keywords: Air baku, Spillway, Embung, Raw Water, Spillway, Reservoir
Subjects: T Technology > TC Hydraulic engineering. Ocean engineering > TC167 Dams, reservoirs
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22201-(S1) Undergraduate Thesis
Depositing User: - Davi Wah
Date Deposited: 10 May 2019 06:04
Last Modified: 10 May 2019 06:04
URI: http://repository.its.ac.id/id/eprint/62994

Actions (login required)

View Item View Item