Perencanaan Waktu Dan Biaya PIER 1 – PIER 8 Jembatan Taman Hiburan Pantai Kenjeran Surabaya

Ahadian, Arif Fajar and Sari, Bayu Dwi Ana Nia (2015) Perencanaan Waktu Dan Biaya PIER 1 – PIER 8 Jembatan Taman Hiburan Pantai Kenjeran Surabaya. Diploma thesis, Institut Technology Sepuluh Nopember.

[thumbnail of 3112030058-3112030064-Undergraduate Thesis.pdf]
Preview
Text
3112030058-3112030064-Undergraduate Thesis.pdf - Published Version

Download (8MB) | Preview

Abstract

Jembatan Taman Hiburan Pantai (THP) Kenjeran Surabaya
– Jawa Timur, dimana lokasi proyek direncanakan mulai jalan
Tambak Deres sampai dengan jalan Sukolilo Kenjeran. Jembatan
THP Kenjeran ini direncanakan memiliki panjang total kurang
lebih 470 m. Dalam proyek Akhir ini akan melakukan perencanaan
waktu dan biaya Pier 1 – Pier 8 proyek Jembatan Taman Hiburan
Pantai Kenjeran Surabaya.
Produktivitas dan kebutuhan sumber daya setiap pekerjaan
dihitung berdasarkan analisis modern oleh Ir. Soedrajat dan
pengamatan yang dilakukan dilapangan, sehingga dapat diketahui
metode pembiayaan dari masing-masing jenis pekerjaan dan
produktivitas.
Dengan aplikasi software MS. Project 2010, hasil durasi dan
produktivitas tiap pekerjaaan dapat dijadikan input bersama
dengan metode pelaksanaannya dan hasilnya dapat diketahui
durasi pelaksanaan proyek tersebut adalah 9 (sembilan) bulan 3
(tiga) hari dengan total biaya pelaksanaan sebesar Rp
59.247.273.913,65
==========================================================================================================
Taman Hiburan Pantai (THP) Kenjeran bridge
Surabaya—East Java, the project will be located at Tambak Deres
streetuntilSukolilo Kenjeran street. ThisTHP Kenjeran bridge is
estimated to have total lengthabout 470 m. In this final project,
there will be time and cost planning of Pier 1 – Pier 8 project of
Taman Hiburan Pantai Kenjeran bridge Surabaya.
The productivity and the resource requirements of each
job are calculated based on modern analysis by Ir.Soedrajat and
field observations, so the financing method of each kind of job and
the productivity can be known.
Through the MS. Project 2010 software application, the
results of the duration and the productivity of each job can be used
as the input together with the method of the implementation and
the results show that the duration of the project implementation is
9 (nine) months 3 (three) days and the total cost of the
implementation is Rp 59.247.273.913,65

Item Type: Thesis (Diploma)
Additional Information: RSS 624.2 Aha p
Uncontrolled Keywords: Produktivitas pekerjaan, biaya pelaksanaan, metode pelaksanaan
Subjects: T Technology > TF Railroad engineering and operation > TF193 Estimates, costs, etc.
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22401-(D3) Diploma 3
Depositing User: Mr. Tondo Indra Nyata
Date Deposited: 21 Jun 2019 04:01
Last Modified: 21 Jun 2019 04:01
URI: http://repository.its.ac.id/id/eprint/63187

Actions (login required)

View Item View Item