Desain Pembangkit Listrik Tenaga Air Di Ciamis, Jawa Barat

Rabel, Afry (2019) Desain Pembangkit Listrik Tenaga Air Di Ciamis, Jawa Barat. Diploma thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 10111510000030-Undergraduate-Thesis.pdf] Text
10111510000030-Undergraduate-Thesis.pdf - Accepted Version
Restricted to Repository staff only

Download (9MB) | Request a copy

Abstract

Bendungan Leuwikeris memiliki tinggi jatuh sebesar 75 meter dengan potensi debit irigasinya 46,6 m3/detik. Debit irigasi tersebut digunakan untuk mengairi lahan pertanian. Besar head dan debit tersebut memiliki potensi untuk dimanfaatkan menjadi pembangkit listrik karena memiliki head diatas 10 meter. Pada perencanaan ini, debit air yang digunakan untuk memutar turbin adalah debit air irigasi yang hanya dipinjam sementara dimana nantinya debit tersebut akan dikembalikan lagi ke sungai eksisting sehingga dapat masuk ke saluran irigasi. Metode perencanaan yang digunakan adalah menghitung tinggi jatuh yang ada kemudian menghitung gaya yang terjadi sehingga diidapatkan spesifikasi material yang stabil terhadap gaya yang ada. Kemudian untuk perencanaan selanjutnya adalah perhitungan daya yang dihasilkan. Dari hasil perhitungan, didapat besar energi yang dihasilkan dari desain pembangkit listrik dengan tinggi jatuh efektif sebesar 64,243 meter adalah 19,97 MegaWatt per detik
======================================================================================================
Leuwikeris Dam has head of 75 meters with the irrigation
discharge of 46.6 m3/second. The irrigation discharge is used to irrigated agricultural land. That head and discharge have a potential of a hydropower because it has more than 10 meters head.
In this planning, the water discharge used to rotate the
turbine is the discharge of irrigation water which is only
borrowed while the discharge will be returned back to the
existing river so that it can enter the irrigation channels. The methods used are counting the head. After that, we can count the forces that are there so we can determine the right specifications that are stable to the force. Next, we can count the energy that can be produced.
From the calculation result, gained energy result from the
design of the power plant with an effective head of 64,243 meters is 19,97 Megawatts per second.

Item Type: Thesis (Diploma)
Additional Information: RSIS 627.8 Rab d-1 3100019082853
Uncontrolled Keywords: Bendungan, Leuwikeris, PLTA
Subjects: T Technology > TC Hydraulic engineering. Ocean engineering > TC167 Dams, reservoirs
T Technology > TK Electrical engineering. Electronics Nuclear engineering > TK1322.6 Electric power-plants
Divisions: Faculty of Vocational > Civil Infrastructure Engineering (D3)
Depositing User: AFRY RABEL
Date Deposited: 18 Mar 2020 07:35
Last Modified: 21 Mar 2020 08:43
URI: http://repository.its.ac.id/id/eprint/67106

Actions (login required)

View Item View Item