Kajian Durasi Pemeliharaan Pembangkit Listrik Tenaga Uap untuk Meningkatkan Equivalent Availability Factor

Purjanto, Dody Awin (2019) Kajian Durasi Pemeliharaan Pembangkit Listrik Tenaga Uap untuk Meningkatkan Equivalent Availability Factor. Masters thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 09211650015027-Master_Thesis.pdf]
Preview
Text
09211650015027-Master_Thesis.pdf

Download (5MB) | Preview

Abstract

Pemeliharaan periodik (overhaul) pembangkit listrik tergolong sebagai sebuah proyek. Durasi penyelesaian proyek yang lebih cepat menandakan keberhasilan. Terlebih dalam industri kelistrikan, dimana semakin cepat beroperasi akan meningkatkan ketersediaan (availibility) pembangkit listrik yang pada akhir juga memperbesar pendapatan dalam komersial tenaga listrik. Standard job pemeliharaan dari pihak owner disusun menjadi work breakdown structure (WBS) proyek pemeliharaan. Dengan menggunakan teknik penjadwalan proyek berupa jaringan kerja (network), dengan didukung oleh data durasi penyelesaian pekerjaan, maka akan didapatkan lintasan kritis (critical path). Seluruh aktivitas yang berada pada critical path dapat dilakukan crashing untuk dapat mempercepat penyelesaian pekerjaan sehingga memperpendek durasi pemeliharaan. Crashing dilakukan dengan cara memanfaatkan nilai cost slope pada aktivitas kritis. Sehingga didapatkan informasi biaya pada beberapa durasi yang memungkinkan. Kajian durasi pemeliharaan pembangkit listrik menggunakan cost slope mendapatkan durasi dipercepat dengan biaya terkecil, yaitu 28 hari. Dengan durasi pemeliharaan selama 28 hari tersebut total biaya sebesar Rp. 3.854.670.611,- dan dengan tambahan pendapatan sebesar Rp. 429.643.368,- dari pendapatan normal sebesar Rp. 21.404.712.886,-.
========================================================================================================================
The maintenance period of a power plant is classified as a project. When project’s duration is faster than scheduled then the project signifies success. For electricity industry, faster operate can increase availability, so that increase the income. Standard jobs of maintenance from owner is prepared into a project’s work breakdown structure (WBS). By using network technique to scheduling of project, also supported by data of work duration, it will get a critical path. All activities that are on the critical path can be crashed to speed up work in shortening the duration of maintenance. Crashing is done by utilizing the cost slope of critical activities. So that information can be obtained about the costs of several possible durations. The study of the power plant’s maintenance using a cost slope gets an accelerated duration with the smallest cost, which is 28 days. With the duration of maintenance for 28 days the total cost is 3,854,670,611 rupiahs and with an additional income of 429,643,368 rupiahs from normal income of 21,404,712,886 rupiahs.

Item Type: Thesis (Masters)
Uncontrolled Keywords: overhaul, pembangkit listrik, availibility, WBS, critical path, crashing, dan cost slope.
Subjects: T Technology > T Technology (General) > T56.8 Project Management
Divisions: Faculty of Business and Management Technology > Management Technology
Depositing User: Dody Awin Purjanto
Date Deposited: 25 Mar 2025 03:51
Last Modified: 25 Mar 2025 03:51
URI: http://repository.its.ac.id/id/eprint/68595