Alternatif Perkuatan Lereng Pada Ruas Jalan Trenggalek - Ponorogo KM 23+650

Dharmawansyah, Dedy (2011) Alternatif Perkuatan Lereng Pada Ruas Jalan Trenggalek - Ponorogo KM 23+650. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 3105105002-Undergraduate_Theses.pdf]
Preview
Text
3105105002-Undergraduate_Theses.pdf - Accepted Version

Download (5MB) | Preview

Abstract

Pada pertengahan tahun 2010, ruas jalan Trenggalek-
Ponorogo KM 23 +650 terjadi kelongsoran sepanjang ± 50 m
dengan ketinggian 7 m dan mengikis hampir separuh dari badan
jalan. Akibat dari kejadian tersebut arus lalu lintas disepanjang
jalan tersebut terhambat. Beberapa bulan setelah kejadian, Dinas
Pekerjaan Umum Bina Marga Propinsi Jawa timur melakukan
perbaikan mulai dari dasar lereng sampai ketinggian 3,5 m
dengan menggunakan konstruksi retaining wall dan gabion
(Perkuatan eksisting) sedangkan pada separuh bagian lereng
lainnya yang berada diatas perkuatan eksisting sampai badan
jalan belum diperbaiki sampai saat ini. Selama masa pemakaian,
konstruksi retaining wall yang terpasang sudah tidak berfungsi
secara optimal; ini dibuktikan dengan terjadinya keretakan pada
konstruksi tersebut yang dikuatirkan akan menyebabkan lereng
longsor kembali.
Dari analisa stabilitas pada lereng asli diperoleh SF
sebesar 1,0888, sedangkan dengan perkuatan eksisting diperoleh
SF sebesar 1,13; ini menunjukkan bahwa lereng masih dalam
kondisi kritis sehingga diperlukan sistem perkuatan. Untuk itu,
direncanakan perkuatan yang terdiri dari dua bagian yaitu
perkuatan tambahan pada lereng yang sudah diperbaiki
(perkuatan eksisting) dan perkuatan pada lereng yang belum
ii
diperbaiki. Alternatif perkuatan yang akan digunakan terdiri dari
mini pile, sheet pile, geotextile wall dan gabion.
Hasil yang diperoleh dari perencanaan pada Tugas Akhir
ini yaitu diperlukan tambahan perkuatan dengan menggunakan
mini pile ukuran 20x20 cm yang dipasang mulai elevasi -3,5 m
dari permukaan jalan sampai 1,5 m dibawah bidang gelincir
(panjang total 6.0 meter), dengan jarak 0,5 m. Untuk tambahan
perkuatan pada eksisting retaining wall yang sudah retak
digunakan sheet pile yang ditanam sampai kedalaman 8 m.
Perkuatan pada bagian lereng atas yang belum diperbaiki
digunakan gabion dengan ukuran panjang 180 cm, lebar 90 cm
dan tinggi 45 cm. Gabion tersebut dipasang mulai dari elevasi -
3,5 m sampai permukaan jalan. ========== In the middle of 2010, landslide occured on road between
Trenggalek-Ponorogo (KM 23 +650). It was about 50 m length
and 7 m height; almost half of the road was eroded by the
landslide. Consequently, the traffic was interrupted. In order to fix
the road, the Department of Public Works of East Java Province
construct reinforcement at the bottom of the slope till 3.5 m
heigh, using retaining wall and gabion. On that retaining wall,
however, cracks were found everywhere; it means that the
retaining wall did not function properly. It shows that the slope is
not stable that means another landslide can occur anytime.
Because of that reason, this Final Project (Tugas Akhir/TA) will
design the slope reinforcement to prevent the slope from
landslide.
From analysis carried out, it is found that the safety factor
(SF) of the initial slope is 1.0888; SF of the slope with the
existing reinforcement is 1.13. In order to make the slope
becomes stable, slope reinforcement chosen is combination of
mini pile, sheet pile, geotextile wall and gabion.
The design obtained is mini-pile 20x20 cm size has to be
installed from elevation -3.5 m from the road surface till 1.5 m
below the sliding plane (total mini pile length is 6.0 meters), with
distance of 0,5 m. Besides, sheet pile has to be installed in front
iv
of the existing retaining wall; it is 8 m depth. The unprotected
slope (located above the existing gabion) is reinforced using
gabion; the gabion size is 180 cm length, 90 cm width and 45 cm
height. This gabion is mounted from elevation of -3.5 m till to the
road surface elevation 0.0).

Item Type: Thesis (Undergraduate)
Additional Information: RSS 624.151 363 Dha a 3100011044525
Uncontrolled Keywords: Trenggalek-Ponorogo, Landslide slope, Gabion, Geotextile wall, Sheet pile, Minipile
Subjects: T Technology > TA Engineering (General). Civil engineering (General) > TA455.S6 Soil (Materials of engineering and construction)
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22201-(S1) Undergraduate Thesis
Depositing User: - Davi Wah
Date Deposited: 04 Nov 2019 09:13
Last Modified: 04 Nov 2019 09:28
URI: http://repository.its.ac.id/id/eprint/71228

Actions (login required)

View Item View Item