Nugraha, Aldhi Kusuma (2021) Optimasi Penempatan Group Tower Crane Pada Proyek Pembangunan Apartemen Westown View Surabaya. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.
Text
03111540000058-Undergraduate_Thesis.pdf - Accepted Version Restricted to Repository staff only until 1 April 2023. Download (4MB) | Request a copy |
Abstract
Pada perencanaan awal konstruksi proyek Apartemen Westown View Surabaya, tower crane yang digunakan lebih dari satu tower crane, atau bisa disebut dengan group tower crane. Dengan adanya lebih dari satu tower crane bukan berarti semua masalah pekerjaan pengangkatan bisa teratasi, karena semakin banyak tower crane menyebabkan sering terjadinya tabrakan ataupun tumpang tindih antar tower crane. Tabrakan dan tumpang tindih tersebut bahkan dapat terjadi apabila jib crane bekerja pada level yang berbeda. Dari permasalahan tersebut perlu adanya pengoptimalan lokasi untuk group tower crane. Lokasi yang optimal adalah lokasi yang memiliki indeks konflik dan keseimbangan beban kerja antar tower crane terkecil. Karena tower crane yang digunakan lebih dari satu, maka penempatan tower crane harus sesuai pada titik yang optimal.
Untuk memperoleh titik optimal tower crane, terdapat 3 skenario yang harus dilakukan dalam mengerjakan Tugas Akhir ini. Masing-masing skenario memiliki perbedaan sendiri-sendiri. Pada skenario yang pertama ini dicari titik optimal tower crane pada kondisi asli di lapangan sesuai dengan data denah titik supply dan radius tower crane. Lalu pada skenario yang kedua dicari titik optimal tower crane pada kondisi titik supply yang telah di modifikasi penempatannya tetapi radius tower crane yang digunakan sama seperti data yang ada di lapangan. Kemudian pada skenario yang ketiga dicari titik optimal tower crane pada kondisi titik supply seperti Skenario 2 tetapi radius tower crane yang digunakan diperkecil sampai mencapai radius yang optimal.
Dari 3 skenario yang telah dilakukan penelitian disimpulkan bahwa Skenario 3 dengan koordinat TC1 (12 ; 36) dan TC 2 (114 ; 42) yang memiliki nilai indeks konflik (NC) sebesar 0 persilangan dan keseimbangan beban kerja antar tower crane (σ) 0,457 jam, sebagai skenario yang paling optimal.
=====================================================================================================
At initial planning, the construction of the Westown View Surabaya Apartment project designed to use more than one tower crane or named as group tower crane. The using of group tower crane does not mean all the problems of lifting work can be solved, because there are potential frequent collisions or overlaps among tower cranes. The collisions and overlaps usually occur when jib cranes work at different height levels. From this problem, it is important to optimize the group tower crane placement. An optimal placement is a scenario that has lowest index conflict and workload balance among the tower cranes.
To get the optimal placement of tower cranes there was 3 scenarios to fulfill in this final assignment Each scenario is different from the other. In the first scenario, tower crane position is sought in the original condition in the field, according to the data of the existing supply point and original radius of tower crane. Then in the second scenario, the tower crane position is sought in the condition of the supply point that has been modified but the radius of tower crane used is the same as the data in the field. Then in the third scenario, the optimal point of tower crane is sought in the same supply point conditions as Scenario 2 but the radius of tower crane used is reduced until it reaches the optimal radius.
From the 3 scenarios that have been done research, it is concluded that Scenario 3 which tower crane group placement at the coordinates of TC1 (12 ; 36) and TC 2 (114 ; 42) with an value of conflict index (NC) of 0 crossover and the workload balance between tower crane (σ) 0,457 hours, as the most optimal scenario.
Item Type: | Thesis (Undergraduate) |
---|---|
Uncontrolled Keywords: | tower crane, indeks konflik, keseimbangan beban kerja, optimasi penempatan, tower crane, index conflict, workload balance, placement optimization |
Subjects: | H Social Sciences > HD Industries. Land use. Labor > HD1391 Apartment houses T Technology > TA Engineering (General). Civil engineering (General) T Technology > TJ Mechanical engineering and machinery > TJ1363 Cranes, derricks, etc. |
Divisions: | Faculty of Civil, Planning, and Geo Engineering (CIVPLAN) > Civil Engineering > 22201-(S1) Undergraduate Thesis |
Depositing User: | Aldhi Kusuma Nugraha |
Date Deposited: | 01 Mar 2021 07:35 |
Last Modified: | 01 Mar 2021 07:35 |
URI: | http://repository.its.ac.id/id/eprint/83021 |
Actions (login required)
View Item |