Hermawati, Risnandha (2021) Perhitungan Waktu dan Rencana Anggaran Pelaksanaan Proyek Apartemen Tamansari Prospero Tower Beatus Sidoarjo Menggunakan Aluminium Formwork. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.
Text
10111710013033-Undergraduate_Thesis.pdf - Accepted Version Restricted to Repository staff only until 1 October 2023. Download (14MB) | Request a copy |
|
Text
10111710013033-Undergraduate_Thesis.pdf Restricted to Repository staff only Download (14MB) | Request a copy |
Abstract
Proyek konstruksi merupakan suatu kegiatan yang berlangsung dalam jangka waktu terbatas dengan sumber daya yang beragam. Oleh karena itu, pengerjaan proyek membutuhkan manajemen konstruksi untuk membantu pengaturan sumber daya yang efektif dan efisien.
Proyek akhir ini merencanakan manajemen konstruksi pada Proyek Pembangunan Apartemen Tamansari Prospero Tower Beatus yang terletak di Jl. Kahuripan Raya Kav. 23-27, Sidoarjo. Konstruksi beton bertulang pada apartemen ini memiliki 2 bagian utama yaitu bangunan podium dan tower utama sebanyak 28 lantai. Proyek akhir ini merencanakan penggantian metode pelaksanaan dari yang sebelumnya meggunakan bekisting baja menjadi aluminium formwork mulai dari lantai 1 sampai dengan lantai 10. Hal tersebut dilakukan karena proyek memiliki lantai tipikal serta dapat mempercepat pekerjaan struktur.
Penyusunan proyek akhir dimulai dari mengidentifikasi item pekerjaan kemudian menghitung volume dan produktivitas. Perhitungan tersebut akan menentukan durasi item pekerjaan yang selanjutnya digunakan untuk menyusun penjadwalan. Penjadwalan menggunakan Precedence Diagram Method dengan mengaplikasikan program bantu Microsoft Project. Hasil analisa perhitungan waktu diperoleh selama 78 hari kerja dan biaya pelaksanaan sebesar Rp8.606.296.107,12.
===================================================================================================
A construction project is an activity that takes place in a limited period of time with various resources. Therefore, project work requires construction management to help manage resources effectively and efficiently.
This final project plans construction management at Tamansari Prospero Apartment Project Beatus Tower which is located on Jl. Kahuripan Raya Kav. 23-27, Sidoarjo. The reinforced concrete construction in this apartment has 2 main parts, namely the podium building and the main tower with 28 floors. This final project plans to change the implementation method from the previous one using steel formwork to aluminum formwork starting from the 1st floor to the 10th floor. This is chosen because the project has a typical floor and can speed up structural work.
The preparation for this final project starts from identifying the work items then calculating the volume and productivity. The calculation will determine the duration of the work item which is then used to arrange the schedule. Scheduling using the Precedence Diagram Method by applying the Microsoft Project. The results of time calculation is 78 work days and the implementation cost obtains Rp8.606.296.107,12.
Item Type: | Thesis (Undergraduate) |
---|---|
Uncontrolled Keywords: | Estimasi Waktu, Estimasi Biaya, Microsoft Project, Penjadwalan, Time Estimation, Cost Estimation, Microsoft Project, Network Planning |
Subjects: | H Social Sciences > HD Industries. Land use. Labor > HD1391 Apartment houses T Technology > T Technology (General) > T56.8 Project Management T Technology > TA Engineering (General). Civil engineering (General) |
Divisions: | Faculty of Vocational > Civil Infrastructure Engineering (D4) |
Depositing User: | Risnandha Hermawati |
Date Deposited: | 26 Aug 2021 08:52 |
Last Modified: | 26 Aug 2021 08:52 |
URI: | http://repository.its.ac.id/id/eprint/90446 |